ID Task Name Units Work Delay Start Finish 5 Footing 100% 80 hrs 0 days Fri 09-12-22 Sun 18-12-22 6 Column upto Plinth Level 100% 80 hrs 0 days Mon 12-12-22 Wed 21-12-22 7 Backfilling in Footing 100% 56 hrs 0 days Fri 16-12-22 Thu 22-12-22 8 Plinth Beam 100% 56 hrs 0 days Mon 19-12-22 Sun 25-12-22 9 Earth Filling in Plinth Level 100% 32 hrs 0 days Fri 23-12-22 Mon 26-12-22 10 Anti Termite Treatment 100% 32 hrs 0 days Sun 25-12-22 Wed 28-12-22 11 CC Flooring with PCC 100% 40 hrs 0 days Sun 25-12-22 Thu 29-12-22 12 Column GF to 1st Floor 100% 80 hrs 0 days Mon 19-12-22 Wed 28-12-22 13 1st Floor Slab 100% 160 hrs 0 days Sat 24-12-22 Thu 12-01-23 14 Brickwork at Ground Floor 100% 112 hrs 0 days Mon 23-01-23 Sun 05-02-23 15 Internal Plaster at GF 100% 112 hrs 0 days Wed 01-02-23 Tue 14-02-23 16 Flooring Work - GF 100% 56 hrs 0 days Wed 15-02-23 Tue 21-02-23 19 Column 1st to 2nd Floor 100% 120 hrs 0 days Fri 13-01-23 Fri 27-01-23 20 2nd Floor Slab 100% 160 hrs 0 days Fri 20-01-23 Wed 08-02-23 22 Internal Plaster at 1st Floor 100% 112 hrs 0 days Fri 17-02-23 Thu 02-03-23 23 Flooring Work - 1st 100% 56 hrs 0 days Fri 03-03-23 Thu 09-03-23 26 Column 2nd to 3rd Floor 100% 96 hrs 0 days Fri 10-02-23 Tue 21-02-23 27 3rd Floor Slab 100% 160 hrs 0 days Thu 16-02-23 Tue 07-03-23 28 Brickwork at 2nd Floor 100% 96 hrs 0 days Sat 18-03-23 Wed 29-03-23 29 Internal Plaster at 2nd Floor 100% 120 hrs 0 days Sat 25-03-23 Sat 08-04-23 30 Flooring Work - 2nd 100% 56 hrs 0 days Sun 09-04-23 Sat 15-04-23 33 Column 3rd to Terrace Floor 100% 96 hrs 0 days Thu 09-03-23 Mon 20-03-23 34 Terrace Floor Slab 100% 160 hrs 0 days Wed 15-03-23 Mon 03-04-23 35 Brickwork at 3rd Floor 100% 112 hrs 0 days Fri 14-04-23 Thu 27-04-23 36 Internal Plaster at 3rd Floor 100% 112 hrs 0 days Sat 22-04-23 Fri 05-05-23 37 Flooring Work - 3rd 100% 56 hrs 0 days Wed 03-05-23 Tue 09-05-23 40 Parapet Wall 100% 56 hrs 0 days Thu 06-04-23 Wed 12-04-23 41 External Plaster 100% 160 hrs 0 days Mon 10-04-23 Sat 29-04-23 42 Terrace Water Proofing 100% 80 hrs 0 days Sun 23-04-23 Tue 02-05-23 44 Cleaning Snags Work 100% 80 hrs 0 days Sat 06-05-23 Mon 15-05-23 45 Finish & Handover 100% 40 hrs 0 days Mon 15-05-23 Fri 19-05-23 21 Brickwork at 1st Floor 100% 120 hrs 0 days Thu 09-02-23 Thu 23-02-23
4 Earth Movers 144 hrs
ID Task Name Units Work Delay Start Finish 4 Excavation 100% 64 hrs 0 days Wed 07-12-22 Wed 14-12-22 5 Footing 100% 80 hrs 0 days Fri 09-12-22 Sun 18-12-22
5 Carpenter 320 hrs
ID Task Name Units Work Delay Start Finish 17 Door & Window Work - GF 100% 80 hrs 0 days Wed 22-02-23 Fri 03-03-23 24 Door & Window Work - 1st 100% 80 hrs 0 days Wed 22-02-23 Fri 03-03-23 31 Door & Window Work - 2nd 100% 80 hrs 0 days Tue 28-03-23 Thu 06-04-23 38 Door & Window Work - 3rd 100% 80 hrs 0 days Tue 25-04-23 Thu 04-05-23
6 Painter 568 hrs
ID Task Name Units Work Delay Start Finish 18 Internal Painting - GF 100% 112 hrs 0 days Tue 07-03-23 Mon 20-03-23 25 Internal Painting - 1st 100% 112 hrs 0 days Sun 12-03-23 Sat 25-03-23 32 Internal Painting - 2nd 100% 112 hrs 0 days Mon 03-04-23 Sun 16-04-23 43 External Painting 100% 120 hrs 0 days Wed 26-04-23 Wed 10-05-23 39 Internal Painting - 3rd 100% 112 hrs 0 days Sun 30-04-23 Sat 13-05-23