Who Does What as of Wed 01-03-23

G+3 Building Project

ID Indicators Resource Name Work

1 Worker 2,944 hrs


ID Task Name Units Work Delay Start Finish
5 Footing 100% 80 hrs 0 days Fri 09-12-22 Sun 18-12-22
6 Column upto Plinth Level 100% 80 hrs 0 days Mon 12-12-22 Wed 21-12-22
7 Backfilling in Footing 100% 56 hrs 0 days Fri 16-12-22 Thu 22-12-22
8 Plinth Beam 100% 56 hrs 0 days Mon 19-12-22 Sun 25-12-22
9 Earth Filling in Plinth Level 100% 32 hrs 0 days Fri 23-12-22 Mon 26-12-22
10 Anti Termite Treatment 100% 32 hrs 0 days Sun 25-12-22 Wed 28-12-22
11 CC Flooring with PCC 100% 40 hrs 0 days Sun 25-12-22 Thu 29-12-22
12 Column GF to 1st Floor 100% 80 hrs 0 days Mon 19-12-22 Wed 28-12-22
13 1st Floor Slab 100% 160 hrs 0 days Sat 24-12-22 Thu 12-01-23
14 Brickwork at Ground Floor 100% 112 hrs 0 days Mon 23-01-23 Sun 05-02-23
15 Internal Plaster at GF 100% 112 hrs 0 days Wed 01-02-23 Tue 14-02-23
16 Flooring Work - GF 100% 56 hrs 0 days Wed 15-02-23 Tue 21-02-23
19 Column 1st to 2nd Floor 100% 120 hrs 0 days Fri 13-01-23 Fri 27-01-23
20 2nd Floor Slab 100% 160 hrs 0 days Fri 20-01-23 Wed 08-02-23
22 Internal Plaster at 1st Floor 100% 112 hrs 0 days Fri 17-02-23 Thu 02-03-23
23 Flooring Work - 1st 100% 56 hrs 0 days Fri 03-03-23 Thu 09-03-23
26 Column 2nd to 3rd Floor 100% 96 hrs 0 days Fri 10-02-23 Tue 21-02-23
27 3rd Floor Slab 100% 160 hrs 0 days Thu 16-02-23 Tue 07-03-23
28 Brickwork at 2nd Floor 100% 96 hrs 0 days Sat 18-03-23 Wed 29-03-23
29 Internal Plaster at 2nd Floor 100% 120 hrs 0 days Sat 25-03-23 Sat 08-04-23
30 Flooring Work - 2nd 100% 56 hrs 0 days Sun 09-04-23 Sat 15-04-23
33 Column 3rd to Terrace Floor 100% 96 hrs 0 days Thu 09-03-23 Mon 20-03-23
34 Terrace Floor Slab 100% 160 hrs 0 days Wed 15-03-23 Mon 03-04-23
35 Brickwork at 3rd Floor 100% 112 hrs 0 days Fri 14-04-23 Thu 27-04-23
36 Internal Plaster at 3rd Floor 100% 112 hrs 0 days Sat 22-04-23 Fri 05-05-23
37 Flooring Work - 3rd 100% 56 hrs 0 days Wed 03-05-23 Tue 09-05-23
40 Parapet Wall 100% 56 hrs 0 days Thu 06-04-23 Wed 12-04-23
41 External Plaster 100% 160 hrs 0 days Mon 10-04-23 Sat 29-04-23
42 Terrace Water Proofing 100% 80 hrs 0 days Sun 23-04-23 Tue 02-05-23
44 Cleaning Snags Work 100% 80 hrs 0 days Sat 06-05-23 Mon 15-05-23
45 Finish & Handover 100% 40 hrs 0 days Mon 15-05-23 Fri 19-05-23
21 Brickwork at 1st Floor 100% 120 hrs 0 days Thu 09-02-23 Thu 23-02-23

4 Earth Movers 144 hrs


ID Task Name Units Work Delay Start Finish
4 Excavation 100% 64 hrs 0 days Wed 07-12-22 Wed 14-12-22
5 Footing 100% 80 hrs 0 days Fri 09-12-22 Sun 18-12-22

5 Carpenter 320 hrs


ID Task Name Units Work Delay Start Finish
17 Door & Window Work - GF 100% 80 hrs 0 days Wed 22-02-23 Fri 03-03-23
24 Door & Window Work - 1st 100% 80 hrs 0 days Wed 22-02-23 Fri 03-03-23
31 Door & Window Work - 2nd 100% 80 hrs 0 days Tue 28-03-23 Thu 06-04-23
38 Door & Window Work - 3rd 100% 80 hrs 0 days Tue 25-04-23 Thu 04-05-23

6 Painter 568 hrs


ID Task Name Units Work Delay Start Finish
18 Internal Painting - GF 100% 112 hrs 0 days Tue 07-03-23 Mon 20-03-23
25 Internal Painting - 1st 100% 112 hrs 0 days Sun 12-03-23 Sat 25-03-23
32 Internal Painting - 2nd 100% 112 hrs 0 days Mon 03-04-23 Sun 16-04-23
43 External Painting 100% 120 hrs 0 days Wed 26-04-23 Wed 10-05-23
39 Internal Painting - 3rd 100% 112 hrs 0 days Sun 30-04-23 Sat 13-05-23