Professional Documents
Culture Documents
as of Wed 01-03-23
Dates
Start: Thu 01-12-22 Finish: Fri 19-05-23
Baseline Start: Mon 01-03-21 Baseline Finish: Thu 19-08-21
Actual Start: NA Actual Finish: NA
Start Variance: 640 days Finish Variance: 638 days
Duration
Scheduled: 170 days Remaining: 170 days
Baseline: 170 days Actual: 0 days
Variance: 0 days Percent Complete: 0%
Work
Scheduled: 3,976 hrs Remaining: 3,976 hrs
Baseline: 0 hrs Actual: 0 hrs
Variance: 3,976 hrs Percent Complete: 0%
Costs
Scheduled: ₹ 3,658,240.00 Remaining: ₹ 3,658,240.00
Baseline: ₹ 0.00 Actual: ₹ 0.00
Variance: ₹ 3,658,240.00