G+3 Building Project

as of Wed 01-03-23

Dates
Start: Thu 01-12-22 Finish: Fri 19-05-23
Baseline Start: Mon 01-03-21 Baseline Finish: Thu 19-08-21
Actual Start: NA Actual Finish: NA
Start Variance: 640 days Finish Variance: 638 days

Duration
Scheduled: 170 days Remaining: 170 days
Baseline: 170 days Actual: 0 days
Variance: 0 days Percent Complete: 0%

Work
Scheduled: 3,976 hrs Remaining: 3,976 hrs
Baseline: 0 hrs Actual: 0 hrs
Variance: 3,976 hrs Percent Complete: 0%

Costs
Scheduled: ₹ 3,658,240.00 Remaining: ₹ 3,658,240.00
Baseline: ₹ 0.00 Actual: ₹ 0.00
Variance: ₹ 3,658,240.00

Task Status Resource Status


Tasks not yet started: 46 Work Resources: 2
Tasks in progress: 0 Overallocated Work Resources: 4
Tasks completed: 0 Material Resources: 0
Total Tasks: 46 Total Resources: 6