Project Name: OUTLET BEKASI

Goal: Launching Outlet Mitra Bekasi dalam 2 Bulan


Action Step #1: Planning RAB dan Survey
Priority Task (Action Item) Phase Assigned
High Fiksasi RAB Finish Ghozy
High Mengukur Tempat Finish Ghozy
High Survey Ulang Finish Ghozy

Action Step #2: Purchasing Barang dan Persiapan Tempat


Priority Task (Action Item) Phase Assigned
High Purchasing Perlengkapan PeralaProgress Ghozy, Client
High Purchasing Bahan Baku Progress Ghozy, Client
Med Menyusun Perlengkapan Planning Ghozy, Indra
Med Merapihkan Tempat Planning Ghozy, Indra, Client

Action Step #3: Launch site


Priority Task (Action Item) Phase Assigned
High Training Goreng Planning Ghozy
HIgh Opening Planning Ghozy, Indra
Low Monitoring Operasional Planning Ghozy
Timeline Re
Status Start Date Due Date Planned Hours Department
100% 8-Mar 11-Mar 3 Day Office
100% 9-Mar 12-Mar 2 Day Office
100% 9-Mar 13-Mar 2 Day Office

Timeline Re
Status Start Date Due Date Planned Hours Department
100% 11-Mar 15-Mar 5 Days Office
100% 11-Mar 15-Mar 5 Days Office
100% 17-Mar 18-Mar 2 Days Office, Field Affair
100% 17-Mar 18-Mar 2 Days Office, Field Affair

Timeline Re
Status Start Date Due Date Planned Hours Department
100% 16-Mar 16-Mar 1 Day Office
100% 21-Mar 21-Mar 1 Day Office, Field Affair
100% 22-Mar 22-Jun 3 Months Office
Resources
Materials Required Cost Notes

Rp 200,000

Resources
Materials Required Cost Notes
Rp 15,823,000

Rp 250,000

Resources
Materials Required Cost Notes
Rp 1,000,000
Rp 750,000