COORDINATION MEETING OF

PT WASKITA KARYA REALTY

VASAKA BALI
Coordination Meeting
PROGRESS KONSTRUKSI

PROGRES
PEKERJAAN NILAI KONTRAK PEKERJAAN DESEMBER 2020
MINGGU LALU MINGGU INI S/D MINGGU INI

Konstruksi Cluster Evara E4 Rp 9.360.456.430 0,389% 0,208% 0,597%

Konstruksi Cluster Evara E3 Rp - 0% 0% 0%

Konstruksi Cluster Evara E2 Rp - 0% 0% 0%


Konstruksi Cluster Evara E1 Rp - 0% 0% 0%

Coordination Meeting
FOTO KEMAJUAN PROYEK
Progress Rumah Evara E-4

Coordination Meeting
FOTO KEMAJUAN PROYEK
Progress Rumah Evara Blok E-4 dan Blok E2-3

E2-3
Coordination Meeting
TIME SCHEDULE
(KURVA –S)

Coordination Meeting
TIME SCHEDULE | E4-1

Coordination Meeting
EVALUASI PEKERJAAN| E4-1
Durasi Rencana Durasi Realisasi
No. Uraian
Durasi start Finish start Finish progres(%)
Evara 4-1

A. PEKERJAAN STRUKTUR
A.1 PEK. SUB STRUKTUR 86 days Sat 14/11/20 Sat 10/04/21
1. PEK. BOWPLANK 28 days Sat 14/11/20 Wed 17/02/21
Pek. Bowplank 2 days Sat 14/11/20 Sat 12/12/20 Wed 04/11/20 Wed 04/11/20 100%
PEK. PONDASI TAPAK 2 days Sat 14/11/20 Sun 15/11/20
Pek. Galian Tanah 11 days Sat 14/11/20 Sun 15/11/20 Thu 19/11/20 Thu 19/11/20 100%
Antirayap+Pasir Urug 3 days Mon 16/11/20 Thu 26/11/20 Thu 19/11/20 Thu 19/11/20 100%
Lantai Kerja 1 day Mon 16/11/20 Wed 18/11/20 Fri 20/11/20 Fri 20/11/20 100%
Pembesian 1 day Thu 19/11/20 Thu 19/11/20 Thu 03/12/20 Thu 03/12/20 100%
Bekisting 3 days Fri 20/11/20 Fri 20/11/20 Sat 21/11/20 Mon 23/11/20 100%
Pengecoran 2 days Sat 21/11/20 Mon 23/11/20 Thu 03/12/20 Thu 03/12/20 100%
2 PEK. BATU KALI 1 day Tue 24/11/20 Wed 25/11/20
Pek. Galian Tanah 23 days Thu 26/11/20 Thu 26/11/20 Thu 19/11/20 Thu 19/11/20 100%
antirayap 3 days Thu 19/11/20 Sat 12/12/20 Thu 19/11/20 Thu 19/11/20 100%
Pasir Urug 1 day Thu 19/11/20 Sat 21/11/20 Tue 24/11/20 Wed 25/11/20 100%
Lantai Kerja 2 days Sun 22/11/20 Sun 22/11/20 Tue 24/11/20 Wed 25/11/20 100%
Pondasi Batu Kali Menerus 2 days Mon 23/11/20 Tue 24/11/20 Sun 08/12/20 Sun 08/12/20 100%
Pembesian Sloof 4 days Mon 23/11/20 Tue 24/11/20
Bekisting 3 days Wed 25/11/20 Sat 28/11/20
Pengecoran 2 days Mon 07/12/20 Wed 09/12/20
3 PEK. PONDASI BATAKO (TERAS DEPAN) 1 day Thu 10/12/20 Fri 11/12/20
Pek. Galian Tanah 22 days Sat 12/12/20 Sat 12/12/20 Thu 19/11/20 Thu 19/11/20 100%
antirayap 2 days Thu 19/11/20 Fri 11/12/20 Thu 19/11/20 Thu 19/11/20 100%
Pasir Urug 1 day Thu 19/11/20 Fri 20/11/20 Tue 01/12/20 Tue 01/12/20 100%
Lantai Kerja 2 days Sat 21/11/20 Sat 21/11/20 Tue 01/12/20 Tue 01/12/20 100%
Pondasi Batako 2 days Sun 22/11/20 Mon 23/11/20 Thu 03/12/20 50%
Pembesian Sloof 4 days Sun 22/11/20 Mon 23/11/20
Bekisting 3 days Tue 24/11/20 Fri 27/11/20
Pengecoran 2 days Sun 06/12/20 Tue 08/12/20
.A.2 PEK. UPPER STRUKTUR 1 day Wed 09/12/20 Thu 10/12/20
A.2.1 LANTAI DASAR 73 days Fri 11/12/20 Fri 11/12/20
1 PEK. TIE BEAM 38 days Fri 27/11/20 Wed 17/02/21
Perapihan Galian + Antirayap 38 days Fri 27/11/20 Wed 13/01/21 Sat 19/12/20 Sat 19/12/20 100%
Pembesian 1 day Fri 27/11/20 Wed 13/01/21 Wed 09/12/20 Wed 09/12/20 100%
Bekisting 3 days Fri 27/11/20 Fri 27/11/20 Sun 06/12/20 Tue 08/12/20 100%
Pengecoran 2 days Sat 28/11/20 Mon 30/11/20 Wed 09/12/20 Wed 09/12/20 100%
Pasang Batako 1 day Wed 02/12/20 Thu 03/12/20
2 PEK. PLAT LANTAI 3 days Fri 04/12/20 Fri 04/12/20
Pemadatan Tanah 4 days Mon 11/01/21 Wed 13/01/21
Pasir Urug 2 days Sat 09/01/21 Tue 12/01/21
Anti Rayap 1 day Sat 09/01/21 Sun 10/01/21
Plastik Cor 1 day Mon 11/01/21 Mon 11/01/21
Pengecoran 1 day Mon 11/01/21 Mon 11/01/21
3 PEK. KOLOM 1 day Tue 12/01/21 Tue 12/01/21
Pembesian 9 days Tue 12/01/21 Tue 12/01/21
Bekisting 3 days Sun 06/12/20 Mon 14/12/20
Pengecoran 4 days Sun 06/12/20 Tue 08/12/20

Coordination Meeting
TIME SCHEDULE | E4-2

Coordination Meeting
EVALUASI PEKERJAAN| E4-2
No. uraian
Durasi rencana Durasi Realisasi
Durasi Start Finish Start Finish Progres (%)
Evara 4-2
PEKERJAAN STRUKTUR 86 days Thu 26/11/20 Wed 17/02/21
A.1 PEK. SUB STRUKTUR 27 days Thu 26/11/20 Mon 01/03/21
1 PEK. BOWPLANK 2 days Thu 26/11/20 Wed 23/12/20
Pek. Bowplank 2 days Thu 26/11/20 Fri 27/11/20 Wed 11/11/20 Fri 27/11/20 100%
PEK. PONDASI TAPAK 11 days Sat 28/11/20 Fri 27/11/20
Pek. Galian Tanah 3 days Sat 28/11/20 Wed 09/12/20 Thu 12/11/20 Thu 12/11/20 100%
Antirayap + Pasir Urug 1 day Wed 02/12/20 Mon 30/11/20 Sun 15/11/20 Sun 15/11/20 100%
Lantai Kerja 1 day Thu 03/12/20 Wed 02/12/20 Fri 27/11/20 Fri 27/11/20 100%
Pembesian 3 days Fri 04/12/20 Thu 03/12/20 Mon 16/11/20 Tue 17/11/20 100%
Bekisting 2 days Mon 07/12/20 Sun 06/12/20 Fri 27/11/20 Fri 27/11/20 100%
Pengecoran 1 day Wed 09/12/20 Tue 08/12/20 Wed 11/11/20 57%
2 PEK. BATU KALI 22 days Wed 02/12/20 Wed 09/12/20
Pek. Galian Tanah 2 days Wed 02/12/20 Wed 23/12/20 Thu 12/11/20 Thu 12/11/20 100%
Antirayap 1 day Fri 04/12/20 Thu 03/12/20 Thu 12/11/20 Thu 12/11/20 100%
Pasir Urug 2 days Sat 05/12/20 Fri 04/12/20 Tue 17/11/20 Thu 19/11/20 100%
Lantai Kerja 2 days Sat 05/12/20 Sun 06/12/20 Thu 19/11/20 Mon 23/11/20 100%
Pondasi Batu Kali Menerus 4 days Mon 07/12/20 Sun 06/12/20
Pembesian Sloof 3 days Fri 18/12/20 Thu 10/12/20
Bekisting 2 days Mon 21/12/20 Sun 20/12/20
Pengecoran 1 day Wed 23/12/20 Tue 22/12/20
3 PEK. PONDASI BATAKO (TERAS DEPAN) 22 days Wed 02/12/20 Wed 23/12/20
Pek. Galian Tanah 2 days Wed 02/12/20 Wed 23/12/20 Thu 12/11/20 Thu 12/11/20 100%
Antirayap 1 day Fri 04/12/20 Thu 03/12/20 Mon 30/11/20 Mon 30/11/20 100%
Pasir Urug 2 days Sat 05/12/20 Fri 04/12/20 Mon 30/11/20 Mon 30/11/20 100%
Lantai Kerja 2 days Sat 05/12/20 Sun 06/12/20 Wed 09/12/20 65%
Pondasi Batako 4 days Mon 07/12/20 Sun 06/12/20
Pembesian Sloof 3 days Fri 18/12/20 Thu 10/12/20
Bekisting 2 days Mon 21/12/20 Sun 20/12/20
Pengecoran 1 day Wed 23/12/20 Tue 22/12/20
A.2 PEK. UPPER STRUKTUR 73 days Thu 10/12/20 Wed 23/12/20
A 2.1 LANTAI DASAR 38 days Thu 10/12/20 Mon 01/03/21
1 PEK. TIE BEAM 38 days Thu 10/12/20 Mon 25/01/21
Perapihan Galian + Antirayap 1 day Thu 10/12/20 Mon 25/01/21 Fri 04/12/20 Fri 04/12/20 100%
Pembesian 3 days Fri 11/12/20 Thu 10/12/20 Tue 17/11/20 Thu 19/11/20 100%
Bekisting 2 days Mon 14/12/20 Sun 13/12/20 Fri 04/12/20 Fri 04/12/20 100%
Pengecoran 1 day Wed 16/12/20 Tue 15/12/20
Pasang Batako 3 days Sat 23/01/21 Wed 16/12/20
2 PEK. PLAT LANTAI 4 days Thu 21/01/21 Mon 25/01/21
Pemadatan Tanah 2 days Thu 21/01/21 Sun 24/01/21
Pasir Urug 1 day Sat 23/01/21 Fri 22/01/21
Anti Rayap 1 day Sat 23/01/21 Sat 23/01/21
Plastik Cor 1 day Sun 24/01/21 Sat 23/01/21
Pengecoran 1 day Sun 24/01/21 Sun 24/01/21
3 PEK. KOLOM 9 days Fri 18/12/20 Sun 24/01/21
Pembesian 3 days Fri 18/12/20 Mon 04/01/21 Fri 11/12/20 25%
Bekisting 4 days Mon 21/12/20 Sun 20/12/20

Coordination Meeting Pengecoran 2 days Sat 26/12/20 Thu 24/12/20


TIME SCHEDULE | E4-3

Coordination Meeting
EVALUASI PEKERJAAN| E4-3
No. Urian
Durasi Rencana Durasi Realisasi
Durasi Start Finish Start Finish Progres (%)
Evara 4-3
A.1 PEK. SUB STRUKTUR 94 days Mon 02/11/20 Sat 13/02/21
1 PEK. BOWPLANK 27 days Mon 02/11/20 Sat 28/11/20
Pek. Bowplank 2 days Mon 02/11/20 Tue 03/11/20 Wed 04/11/20 Wed 04/11/20 100%
PEK. PONDASI TAPAK 2 days Mon 02/11/20 Tue 03/11/20
Pek. Galian Tanah 19 days Wed 04/11/20 Sun 22/11/20 Wed 11/11/20 Wed 11/11/20 100%
Antirayap + Pasir Urug 3 days Wed 04/11/20 Fri 06/11/20 Wed 11/11/20 Wed 11/11/20 100%
Lantai Kerja 1 day Sat 07/11/20 Sat 07/11/20 Sat 14/11/20 Wed 16/12/20 100%
Pembesian 1 day Sun 08/11/20 Sun 08/11/20 Wed 25/11/20 Wed 25/11/20 100%
Bekisting 3 days Tue 17/11/20 Thu 19/11/20 Mon 16/11/20 Mon 16/11/20 100%
Pengecoran 2 days Fri 20/11/20 Sat 21/11/20 Wed 25/11/20 Wed 25/11/20 100%
2 PEK. BATU KALI 1 day Sun 22/11/20 Sun 22/11/20
Pek. Galian Tanah 22 days Sat 07/11/20 Sat 28/11/20 Wed 11/11/20 Wed 11/11/20 100%
Antirayap 2 days Sat 07/11/20 Sun 08/11/20 Wed 11/11/20 Wed 11/11/20 100%
Pasir Urug 1 day Mon 09/11/20 Mon 09/11/20 Wed 11/11/20 Wed 11/11/20 100%
Lantai Kerja 2 days Tue 10/11/20 Wed 11/11/20 Sat 14/11/20 Mon 16/11/20 100%
Pondasi Batu Kali Menerus 2 days Tue 10/11/20 Wed 11/11/20 Tue 17/11/20 70%
Pembesian Sloof 4 days Thu 12/11/20 Sun 15/11/20
Bekisting 3 days Mon 23/11/20 Wed 25/11/20
Pengecoran 2 days Thu 26/11/20 Fri 27/11/20
3 PEK. PONDASI BATAKO (TERAS DEPAN) 1 day Sat 28/11/20 Sat 28/11/20
Pek. Galian Tanah 21 days Sat 07/11/20 Fri 27/11/20 Wed 11/11/20 Wed 11/11/20 100%
Antirayap 2 days Sat 07/11/20 Sun 08/11/20 Wed 11/11/20 Wed 11/11/20 100%
Pasir Urug 1 day Mon 09/11/20 Mon 09/11/20 Mon 30/11/20 Mon 30/11/20 100%
Lantai Kerja 2 days Mon 09/11/20 Tue 10/11/20 Mon 30/11/20 Mon 30/11/20 100%
Pondasi Batako 2 days Mon 09/11/20 Tue 10/11/20 Wed 09/12/20 75%
Pembesian Sloof 4 days Wed 11/11/20 Sat 14/11/20
Bekisting 3 days Sun 22/11/20 Tue 24/11/20
Pengecoran 2 days Wed 25/11/20 Thu 26/11/20
A.2 PEK. UPPER STRUKTUR 1 day Fri 27/11/20 Fri 27/11/20
A 2.1 LANTAI DASAR 73 days Mon 23/11/20 Sat 13/02/21
1 PEK. TIE BEAM 38 days Mon 23/11/20 Sat 09/01/21
Perapihan Galian+ Antirayap 38 days Mon 23/11/20 Sat 09/01/21 Wed 11/11/20 Wed 11/11/20 100%
Pembesian 1 day Mon 23/11/20 Mon 23/11/20 Wed 02/12/20 Wed 02/12/20 100%
Bekisting 3 days Tue 24/11/20 Thu 26/11/20 Tue 17/11/20 Wed 25/11/20 100%
Pengecoran 2 days Fri 27/11/20 Sat 28/11/20 Wed 02/12/20 Wed 02/12/20 100%
Pasang Batako 1 day Sun 29/11/20 Sun 29/11/20
2 PEK. PLAT LANTAI 3 days Thu 07/01/21 Sat 09/01/21
Pemadatan Tanah 4 days Tue 05/01/21 Fri 08/01/21
Pasir Urug 2 days Tue 05/01/21 Wed 06/01/21
Anti Rayap 1 day Thu 07/01/21 Thu 07/01/21
Plastik Cor 1 day Thu 07/01/21 Thu 07/01/21
Pengecoran 1 day Fri 08/01/21 Fri 08/01/21
3 PEK. KOLOM 1 day Fri 08/01/21 Fri 08/01/21
Pembesian 9 days Wed 02/12/20 Thu 10/12/20
Bekisting 3 days Wed 02/12/20 Fri 04/12/20
Pengecoran 4 days Sat 05/12/20 Tue 08/12/20
Coordination Meeting
TIME SCHEDULE | E4-5

Coordination Meeting
EVALUASI PEKERJAAN| E4-5
No. Uraian
Durasi Rencana Durasi Realisasi
Durasi Start Finish Start Finish Progres %
Evara 4-5
PEKERJAAN STRUKTUR 88 days Sun 08/11/20 Sat 13/02/21
A.1 PEK. SUB STRUKTUR 27 days Sun 08/11/20 Sat 05/12/20
1 PEK. BOWPLANK 2 days Sun 08/11/20 Mon 09/11/20
Pek. Bowplank 2 days Sun 08/11/20 Mon 09/11/20 Wed 04/11/20 Mon 23/11/20 100%
PEK. PONDASI TAPAK 13 days Tue 10/11/20 Sun 22/11/20
Pek. Galian Tanah 3 days Tue 10/11/20 Thu 12/11/20 Sun 08/11/20 Fri 13/11/20 100%
Antirayap + Pasir Urug 1 day Fri 13/11/20 Fri 13/11/20 Thu 12/11/20 Fri 13/11/20 100%
Lantai Kerja 1 day Sat 14/11/20 Sat 14/11/20 Thu 12/11/20 Mon 23/11/20 100%
Pembesian 3 days Tue 17/11/20 Thu 19/11/20 Mon 23/11/20 Mon 16/11/20 100%
Bekisting 2 days Fri 20/11/20 Sat 21/11/20 Fri 13/11/20 Mon 23/11/20 100%
Pengecoran 1 day Sun 22/11/20 Sun 22/11/20 Mon 23/11/20 Mon 23/11/20 100%
2 PEK. BATU KALI 22 days Fri 13/11/20 Sat 05/12/20
Pek. Galian Tanah 2 days Fri 13/11/20 Sat 14/11/20 Sun 08/11/20 Thu 12/11/20 100%
antirayap 1 day Sun 15/11/20 Sun 15/11/20 Thu 12/11/20 Mon 30/11/20 100%
Pasir Urug 2 days Mon 16/11/20 Tue 17/11/20 Mon 30/11/20 Mon 30/11/20 100%
Lantai Kerja 2 days Mon 16/11/20 Tue 17/11/20 Mon 30/11/20 Mon 30/11/20 100%
Pondasi Batu Kali Menerus 4 days Wed 18/11/20 Sat 21/11/20 Mon 30/11/20 Mon 30/11/20 100%
Pembesian Sloof 3 days Sun 29/11/20 Wed 02/12/20
Bekisting 2 days Thu 03/12/20 Fri 04/12/20
Pengecoran 1 day Sat 05/12/20 Sat 05/12/20
3 PEK. PONDASI BATAKO (TERAS DEPAN) 22 days Fri 13/11/20 Sat 05/12/20
Pek. Galian Tanah 2 days Fri 13/11/20 Sat 14/11/20 Sun 08/11/20 Thu 12/11/20 100%
antirayap 1 day Sun 15/11/20 Sun 15/11/20 Thu 12/11/20 Thu 12/11/20 100%
Pasir Urug 2 days Mon 16/11/20 Tue 17/11/20 Wed 02/12/20 Wed 02/12/20 100%
Lantai Kerja 2 days Mon 16/11/20 Tue 17/11/20 Wed 02/12/20 Wed 09/12/20 100%
Pondasi Batako 4 days Wed 18/11/20 Sat 21/11/20 Wed 02/12/20 Wed 02/12/21 100%
Pembesian Sloof 3 days Sun 29/11/20 Wed 02/12/20
Bekisting 2 days Thu 03/12/20 Fri 04/12/20
Pengecoran 1 day Sat 05/12/20 Sat 05/12/20
A.2 PEK. UPPER STRUKTUR 73 days Mon 23/11/20 Sat 13/02/21
A 2.1 LANTAI DASAR 38 days Mon 23/11/20 Sat 09/01/21
1 PEK. TIE BEAM 38 days Mon 23/11/20 Sat 09/01/21
Perapihan Galian + Antirayap 1 day Mon 23/11/20 Mon 23/11/20 Sun 08/11/20 Sun 29/11/20 100%
Pembesian 3 days Tue 24/11/20 Thu 26/11/20 Sun 29/11/20 Fri 27/11/20 100%
Bekisting 2 days Fri 27/11/20 Sat 28/11/20 Tue 17/11/20 Mon 30/11/20 100%
Pengecoran 1 day Sun 29/11/20 Sun 29/11/20 Sun 29/11/20 Sun 29/11/20 100%
Pasang Batako 3 days Thu 07/01/21 Sat 09/01/21
2 PEK. PLAT LANTAI 4 days Tue 05/01/21 Fri 08/01/21
Pemadatan Tanah 2 days Tue 05/01/21 Wed 06/01/21
Pasir Urug 1 day Thu 07/01/21 Thu 07/01/21
Anti Rayap 1 day Thu 07/01/21 Thu 07/01/21
Plastik Cor 1 day Fri 08/01/21 Fri 08/01/21
Pengecoran 1 day Fri 08/01/21 Fri 08/01/21
3 PEK. KOLOM 9 days Wed 02/12/20 Thu 10/12/20
Pembesian 3 days Wed 02/12/20 Fri 04/12/20 Fri 11/12/20 25%
Bekisting 4 days Sat 05/12/20 Tue 08/12/20
Pengecoran 2 days Wed 09/12/20 Thu 10/12/20
Coordination Meeting
TIME SCHEDULE | E4-6

Coordination Meeting
EVALUASI PEKERJAAN| E4-6 Durasi Rencana Durasi Realisasi
No. Uraian Durasi Start Finish Start Finish Progres %
Evara 4-6
A PEKERJAAN STRUKTUR 94 days Mon 02/11/20 Sat 13/02/21
A.1 PEK. SUB STRUKTUR 27 days Mon 02/11/20 Sat 28/11/20
1 PEK. BOWPLANK 2 days Mon 02/11/20 Tue 03/11/20
Pek. Bowplank 2 days Mon 02/11/20 Tue 03/11/20 Thu 05/11/20 Wed 5/11/20 100%
PEK. PONDASI TAPAK 19 days Wed 04/11/20 Sun 22/11/20
Pek. Galian Tanah 3 days Wed 04/11/20 Fri 06/11/20 Mon 09/11/20 Mon 09/11/20 100%
Antirayap + Pasir Urug 1 day Sat 07/11/20 Sat 07/11/20 Thu 12/11/20 Sat 14/11/20 100%
Lantai Kerja 1 day Sun 08/11/20 Sun 08/11/20 Mon 23/11/20 Mon 23/11/20 100%
Pembesian 3 days Tue 17/11/20 Thu 19/11/20 Thu 12/11/20 Sat 14/11/20 100%
Bekisting 2 days Fri 20/11/20 Sat 21/11/20 Mon 23/11/20 Wed 25/11/20 100%
Pengecoran 1 day Sun 22/11/20 Sun 22/11/20 Thu 23/11/20 Wed 25/11/20 100%
2 PEK. BATU KALI 22 days Sat 07/11/20 Sat 28/11/20
Pek. Galian Tanah 2 days Sat 07/11/20 Sun 08/11/20 Mon 09/11/20 Mon 09/11/20 100%
antirayap 1 day Mon 09/11/20 Mon 09/11/20 Sat 28/11/20 Sat 28/11/20 100%
Pasir Urug 2 days Tue 10/11/20 Wed 11/11/20 Sat 28/11/20 Sat 28/11/20 100%
Lantai Kerja 2 days Tue 10/11/20 Wed 11/11/20 Sun 29/11/20 Mon 30/11/20 100%
Pondasi Batu Kali Menerus 4 days Thu 12/11/20 Sun 15/11/20
Pembesian Sloof 3 days Mon 23/11/20 Wed 25/11/20
Bekisting 2 days Thu 26/11/20 Fri 27/11/20
Pengecoran 1 day Sat 28/11/20 Sat 28/11/20
3 PEK. PONDASI BATAKO (TERAS DEPAN) 22 days Sat 07/11/20 Sat 28/11/20
Pek. Galian Tanah 2 days Sat 07/11/20 Sun 08/11/20 Mon 09/11/20 Mon 09/11/20 100%
antirayap 1 day Mon 09/11/20 Mon 09/11/20 Mon 09/11/20 Wed 09/12/20 100%
Pasir Urug 2 days Tue 10/11/20 Wed 11/11/20 Mon 16/11/20 Tue 17/11/20 100%
Lantai Kerja 2 days Tue 10/11/20 Wed 11/11/20 Mon 16/11/20 Tue 17/11/20 100%
Pondasi Batako 4 days Thu 12/11/20 Sun 15/11/20 Sun 06/12/20 70%
Pembesian Sloof 3 days Mon 23/11/20 Wed 25/11/20
Bekisting 2 days Thu 26/11/20 Fri 27/11/20
Pengecoran 1 day Sat 28/11/20 Sat 28/11/20
A.2 PEK. UPPER STRUKTUR 73 days Mon 23/11/20 Sat 13/02/21
A 2.1 LANTAI DASAR 38 days Mon 23/11/20 Sat 09/01/21
1 PEK. TIE BEAM 38 days Mon 23/11/20 Sat 09/01/21
Perapihan Galian + Antirayap 1 day Mon 23/11/20 Mon 23/11/20 Thu 05/11/20 Mon 09/11/20 100%
Pembesian 3 days Tue 24/11/20 Thu 26/11/20
Bekisting 2 days Fri 27/11/20 Sat 28/11/20 Thu 12/11/20 Mon 16/11/20 100%
Pengecoran 1 day Sun 29/11/20 Sun 29/11/20
Pasang Batako 3 days Thu 07/01/21 Sat 09/01/21
2 PEK. PLAT LANTAI 4 days Tue 05/01/21 Fri 08/01/21
Pemadatan Tanah 2 days Tue 05/01/21 Wed 06/01/21
Pasir Urug 1 day Thu 07/01/21 Thu 07/01/21
Anti Rayap 1 day Thu 07/01/21 Thu 07/01/21
Plastik Cor 1 day Fri 08/01/21 Fri 08/01/21
Pengecoran 1 day Fri 08/01/21 Fri 08/01/21
3 PEK. KOLOM 9 days Wed 02/12/20 Thu 10/12/20
Pembesian 3 days Wed 02/12/20 Fri 04/12/20
Bekisting 4 days Sat 05/12/20 Tue 08/12/20
Pengecoran 2 days Wed 09/12/20 Thu 10/12/20
Coordination Meeting
TIME SCHEDULE | E4-7

Coordination Meeting
EVALUASI PEKERJAAN| E4-7
No. Uraian
Durasi Rencana Durasi Realisasi
Durasi Start Finish Start Finish Progres%
Evara 4-7
A PEKERJAAN STRUKTUR 94 days Mon 02/11/20 Sat 13/02/21
A.1 PEK. SUB STRUKTUR 27 days Mon 02/11/20 Sat 28/11/20
1 PEK. BOWPLANK 2 days Mon 02/11/20 Tue 03/11/20
Pek. Bowplank 2 days Mon 02/11/20 Tue 03/11/20 Thu 05/11/20 Sat 21/11/20 100%
PEK. PONDASI TAPAK 19 days Wed 04/11/20 Sun 22/11/20
Pek. Galian Tanah 3 days Wed 04/11/20 Fri 06/11/20 Mon 09/11/20 Mon 9/11/20 100%
Antirayap + Pasir Urug 1 day Sat 07/11/20 Sat 07/11/20 Mon 09/11/20 Mon 9/11/20 100%
Lantai Kerja 1 day Sun 08/11/20 Sun 08/11/20 Mon 09/11/20 Thu 12/11/20 100%
Pembesian 3 days Tue 17/11/20 Thu 19/11/20 Tue 10/11/20 Sat 14/11/20 100%
Bekisting 2 days Fri 20/11/20 Sat 21/11/20 Sat 21/11/20 Sat 21/11/20 100%
Pengecoran 1 day Sun 22/11/20 Sun 22/11/20 Sat 21/11/20 Sat 21/11/20 100%
2 PEK. BATU KALI 22 days Sat 07/11/20 Sat 28/11/20
Pek. Galian Tanah 2 days Sat 07/11/20 Sun 08/11/20 Mon 09/11/20 Mon 9/11/20 100%
Antirayap 1 day Mon 09/11/20 Mon 09/11/20 Wed 09/12/20 Wed 9/12/20 100%
Pasir Urug 2 days Tue 10/11/20 Wed 11/11/20 Tue 10/11/20 Thu 10/12/20 100%
Lantai Kerja 2 days Tue 10/11/20 Wed 11/11/20 Wed 11/11/20 Sat 14/11/20 100%
Pondasi Batu Kali Menerus 4 days Thu 12/11/20 Sun 15/11/20
Pembesian Sloof 3 days Mon 23/11/20 Wed 25/11/20
Bekisting 2 days Thu 26/11/20 Fri 27/11/20
Pengecoran 1 day Sat 28/11/20 Sat 28/11/20
3 PEK. PONDASI BATAKO (TERAS DEPAN) 21 days Sat 07/11/20 Fri 27/11/20
Pek. Galian Tanah 2 days Sat 07/11/20 Sun 08/11/20 Thu 05/11/20 Thu 5/11/20 100%
Antirayap 1 day Mon 09/11/20 Mon 09/11/20 Mon 09/11/20 Mon 9/11/20 100%
Pasir Urug 2 days Mon 09/11/20 Tue 10/11/20 Sat 28/11/20 Sat 28/11/20 100%
Lantai Kerja 2 days Mon 09/11/20 Tue 10/11/20 Sat 28/11/20 Sat 28/11/20 100%
Pondasi Batako 4 days Wed 11/11/20 Sat 14/11/20 Mon 30/11/20 50%
Pembesian Sloof 3 days Sun 22/11/20 Tue 24/11/20
Bekisting 2 days Wed 25/11/20 Thu 26/11/20
Pengecoran 1 day Fri 27/11/20 Fri 27/11/20
A.2 PEK. UPPER STRUKTUR 73 days Mon 23/11/20 Sat 13/02/21
A 2.1 LANTAI DASAR 38 days Mon 23/11/20 Sat 09/01/21
1 PEK. TIE BEAM 38 days Mon 23/11/20 Sat 09/01/21
Perapihan Galian+ Antirayap 1 day Mon 23/11/20 Mon 23/11/20 Thu 05/11/20 Sat 11/7/20 100%
Pembesian 3 days Tue 24/11/20 Thu 26/11/20 Wed 25/11/20 Wed 25/11/20 100%
Bekisting 2 days Fri 27/11/20 Sat 28/11/20 Tue 10/11/20 Mon 14/12/20 100%
Pengecoran 1 day Sun 29/11/20 Sun 29/11/20 Wed 25/11/20 Wed 25/11/20 100%
Pasang Batako 3 days Thu 07/01/21 Sat 09/01/21
2 PEK. PLAT LANTAI 4 days Tue 05/01/21 Fri 08/01/21
Pemadatan Tanah 2 days Tue 05/01/21 Wed 06/01/21
Pasir Urug 1 day Thu 07/01/21 Thu 07/01/21
Anti Rayap 1 day Thu 07/01/21 Thu 07/01/21
Plastik Cor 1 day Fri 08/01/21 Fri 08/01/21
Pengecoran 1 day Fri 08/01/21 Fri 08/01/21
3 PEK. KOLOM 9 days Wed 02/12/20 Thu 10/12/20
Pembesian 3 days Wed 02/12/20 Fri 04/12/20 Fri 11/12/20 25%
Bekisting 4 days Sat 05/12/20 Tue 08/12/20
Pengecoran 2 days Wed 09/12/20 Thu 10/12/20
Coordination Meeting
TIME SCHEDULE | E4-8

Coordination Meeting
EVALUASI PEKERJAAN| E4-8
No. Uraian
Durasi Rencana Durasi Realisasi
Durasi Start Finish Start Finish Progres%
Evara 4-8
A PEKERJAAN STRUKTUR 86 days Thu 26/11/20 Mon 01/03/21
A.1 PEK. SUB STRUKTUR 27 days Thu 26/11/20 Wed 23/12/20
1 PEK. BOWPLANK 2 days Thu 26/11/20 Fri 27/11/20
Pek. Bowplank 2 days Thu 26/11/20 Fri 27/11/20 Wed 4 /11/20 Wed 4/11/20 100%
PEK. PONDASI TAPAK 11 days Sat 28/11/20 Wed 09/12/20
Pek. Galian Tanah 3 days Sat 28/11/20 Mon 30/11/20 Sat 14/11/20 Sat 14/11/20 100%
Antirayap + Pasir Urug 1 day Wed 02/12/20 Wed 02/12/20 Tue 17/11/20 Tue 17/11/20 100%
Lantai Kerja 1 day Thu 03/12/20 Thu 03/12/20 Wed18/11/20 Thu 19/11/20 100%
Pembesian 3 days Fri 04/12/20 Sun 06/12/20 Tue 1/12/20 Tue 1/12/20 100%
Bekisting 2 days Mon 07/12/20 Tue 08/12/20 Thu 19/11/20 Thu 19/11/20 100%
Pengecoran 1 day Wed 09/12/20 Wed 09/12/20 Tue1/12/20 Tue 1/12/20 100%
2 PEK. BATU KALI 22 days Wed 02/12/20 Wed 23/12/20
Pek. Galian Tanah 2 days Wed 02/12/20 Thu 03/12/20
Antirayap 1 day Fri 04/12/20 Fri 04/12/20
Pasir Urug 2 days Sat 05/12/20 Sun 06/12/20
Lantai Kerja 2 days Sat 05/12/20 Sun 06/12/20
Pondasi Batu Kali Menerus 4 days Mon 07/12/20 Thu 10/12/20
Pembesian Sloof 3 days Fri 18/12/20 Sun 20/12/20
Bekisting 2 days Mon 21/12/20 Tue 22/12/20
Pengecoran 1 day Wed 23/12/20 Wed 23/12/20
3 PEK. PONDASI BATAKO (TERAS DEPAN) 22 days Wed 02/12/20 Wed 23/12/20
Pek. Galian Tanah 2 days Wed 02/12/20 Thu 03/12/20 Sat 14/11/20 Sat14/11/20 100%
Antirayap 1 day Fri 04/12/20 Fri 04/12/20 Tue 17/11/20 Tue 17/11/20 100%
Pasir Urug 2 days Sat 05/12/20 Sun 06/12/20 Wed 2/12/20 Wed 2/12/20 100%
Lantai Kerja 2 days Sat 05/12/20 Sun 06/12/20 Wed 2/12/20 Wed 2/12/20 100%
Pondasi Batako 4 days Mon 07/12/20 Thu 10/12/20 Sat 5/12/20 50%
Pembesian Sloof 3 days Fri 18/12/20 Sun 20/12/20
Bekisting 2 days Mon 21/12/20 Tue 22/12/20
Pengecoran 1 day Wed 23/12/20 Wed 23/12/20
A.2 PEK. UPPER STRUKTUR 73 days Thu 10/12/20 Mon 01/03/21
A 2.1 LANTAI DASAR 38 days Thu 10/12/20 Mon 25/01/21
1 PEK. TIE BEAM 38 days Thu 10/12/20 Mon 25/01/21
Perapihan Galian + Antirayap 1 day Thu 10/12/20 Thu 10/12/20 Sat 14/11/20 Sat 14/11/20 100%
Pembesian 3 days Fri 11/12/20 Sun 13/12/20 Mon 7/12/20 Mon7/12/20 100%
Bekisting 2 days Mon 14/12/20 Tue 15/12/20 Fri 20/11/20 Wed 25/11/20 100%
Pengecoran 1 day Wed 16/12/20 Wed 16/12/20 Mon 7/12/20 Mon 7/12/20 100%
Pasang Batako 3 days Sat 23/01/21 Mon 25/01/21
2 PEK. PLAT LANTAI 4 days Thu 21/01/21 Sun 24/01/21
Pemadatan Tanah 2 days Thu 21/01/21 Fri 22/01/21
Pasir Urug 1 day Sat 23/01/21 Sat 23/01/21
Anti Rayap 1 day Sat 23/01/21 Sat 23/01/21
Plastik Cor 1 day Sun 24/01/21 Sun 24/01/21
Pengecoran 1 day Sun 24/01/21 Sun 24/01/21
3 PEK. KOLOM 9 days Fri 18/12/20 Mon 04/01/21
Pembesian 3 days Fri 18/12/20 Sun 20/12/20
Bekisting 4 days Mon 21/12/20 Thu 24/12/20
Coordination Meeting Pengecoran 2 days Sat 26/12/20 Mon 04/01/21
TIME SCHEDULE | E4-9

Coordination Meeting
EVALUASI PEKERJAAN| E4-9
No. Uraian
Durasi Rencana Durasi Realisasi
Durasi Start Finish Start Finish Progres %
Evara 4-9
A PEKERJAAN STRUKTUR 86 days Thu 26/11/20 Mon 01/03/21
A.1 PEK. SUB STRUKTUR 27 days Thu 26/11/20 Wed 23/12/20
1 PEK. BOWPLANK 2 days Thu 26/11/20 Fri 27/11/20
Pek. Bowplank 2 days Thu 26/11/20 Fri 27/11/20 Tue 17/11/20 Tue 17/11/20 100%
PEK. PONDASI TAPAK 11 days Sat 28/11/20 Wed 09/12/20
Pek. Galian Tanah 3 days Sat 28/11/20 Mon 30/11/20 Wed 18/11/20 Wed 18/11/20 100%
Antirayap+Pasir Urug 1 day Wed 02/12/20 Wed 02/12/20 Thu 19/11/20 Thu 19/11/20 100%
Lantai Kerja 1 day Thu 03/12/20 Thu 03/12/20 Sun 20/12/20 Sun 20/12/20 100%
Pembesian 3 days Fri 04/12/20 Sun 06/12/20 Wed 02/12/20 Wed 02/12/20 100%
Bekisting 2 days Mon 07/12/20 Tue 08/12/20 Thu 26/11/20 Tue 29/12/20 100%
Pengecoran 1 day Wed 09/12/20 Wed 09/12/20 Wed 02/12/20 Wed 02/12/20 100%
2 PEK. BATU KALI 22 days Wed 02/12/20 Wed 23/12/20
Pek. Galian Tanah 2 days Wed 02/12/20 Thu 03/12/20 Wed 18/11/20 Wed 18/11/20 100%
Antirayap 1 day Fri 04/12/20 Fri 04/12/20 Thu 19/11/20 Thu 19/11/20 100%
Pasir Urug 2 days Sat 05/12/20 Sun 06/12/20 Thu 19/11/20 Thu 19/11/20 100%
Lantai Kerja 2 days Sat 05/12/20 Sun 06/12/20 Sun 20/12/20 Sun 20/12/20 100%
Pondasi Batu Kali Menerus 4 days Mon 07/12/20 Thu 10/12/20 Thu 24/12/20 40%
Pembesian Sloof 3 days Fri 18/12/20 Sun 20/12/20
Bekisting 2 days Mon 21/12/20 Tue 22/12/20
Pengecoran 1 day Wed 23/12/20 Wed 23/12/20
3 PEK. PONDASI BATAKO (TERAS DEPAN) 22 days Wed 02/12/20 Wed 23/12/20
Pek. Galian Tanah 2 days Wed 02/12/20 Thu 03/12/20 Wed 18/11/20 Wed 18/11/20 100%
antirayap 1 day Fri 04/12/20 Fri 04/12/20 Thu 19/11/20 Thu 19/11/20 100%
Pasir Urug 2 days Sat 05/12/20 Sun 06/12/20 Wed 02/12/20 Wed 02/12/20 100%
Lantai Kerja 2 days Sat 05/12/20 Sun 06/12/20 Wed 02/12/20 Wed 02/12/20 100%
Pondasi Batako 4 days Mon 07/12/20 Thu 10/12/20
Pembesian Sloof 3 days Fri 18/12/20 Sun 20/12/20
Bekisting 2 days Mon 21/12/20 Tue 22/12/20
Pengecoran 1 day Wed 23/12/20 Wed 23/12/20
A.2 PEK. UPPER STRUKTUR 73 days Thu 10/12/20 Mon 01/03/21
A 2.1 LANTAI DASAR 38 days Thu 10/12/20 Mon 25/01/21
1 PEK. TIE BEAM 38 days Thu 10/12/20 Mon 25/01/21
Perapihan Galian +Antirayap 1 day Thu 10/12/20 Thu 10/12/20 Wed 18/11/20 Wed 18/11/20 100%
Pembesian 3 days Fri 11/12/20 Sun 13/12/20
Bekisting 2 days Mon 14/12/20 Tue 15/12/20 Thu 26/11/20 20%
Pengecoran 1 day Wed 16/12/20 Wed 16/12/20
Pasang Batako 3 days Sat 23/01/21 Mon 25/01/21
2 PEK. PLAT LANTAI 4 days Thu 21/01/21 Sun 24/01/21
Pemadatan Tanah 2 days Thu 21/01/21 Fri 22/01/21
Pasir Urug 1 day Sat 23/01/21 Sat 23/01/21
Anti Rayap 1 day Sat 23/01/21 Sat 23/01/21
Plastik Cor 1 day Sun 24/01/21 Sun 24/01/21
Pengecoran 1 day Sun 24/01/21 Sun 24/01/21
3 PEK. KOLOM 9 days Fri 18/12/20 Mon 04/01/21
Pembesian 3 days Fri 18/12/20 Sun 20/12/20
Bekisting 4 days Mon 21/12/20 Thu 24/12/20
Pengecoran 2 days Sat 26/12/20 Mon 04/01/21
Coordination Meeting
TIME SCHEDULE | E4-11

Coordination Meeting
EVALUASI PEKERJAAN| E4-11
No. Uraian
Durasi Renca Durasi Realisasi
Durasi Start Finish Start Finish Progres %
Evara 4-11
A PEKERJAAN STRUKTUR 86 days Fri 20/11/20 Tue 23/02/21
A.1 PEK. SUB STRUKTUR 27 days Fri 20/11/20 Thu 17/12/20
1 PEK. BOWPLANK 2 days Fri 20/11/20 Sat 21/11/20
Pek. Bowplank 2 days Fri 20/11/20 Sat 21/11/20 Thu 12/11/20 Mon 30/11/20 100%
PEK. PONDASI TAPAK 11 days Sun 22/11/20 Thu 03/12/20
Pek. Galian Tanah 3 days Sun 22/11/20 Tue 24/11/20 Sun 15/11/20 Sun 15/11/20 100%
Antirayap+Pasir Urug 1 day Wed 25/11/20 Wed 25/11/20 Sun 15/11/20 Mon 16/11/20 100%
Lantai Kerja 1 day Thu 26/11/20 Thu 26/11/20 Mon 30/11/20 Mon 30/11/20 100%
Pembesian 3 days Fri 27/11/20 Sun 29/11/20 Tue 8/12/20 Tue 17/11/20 100%
Bekisting 2 days Mon 30/11/20 Wed 02/12/20 Mon 30/11/20 Mon 30/11/20 100%
Pengecoran 1 day Thu 03/12/20 Thu 03/12/20 Thu12/11/20 49%
2 PEK. BATU KALI 22 days Wed 25/11/20 Thu 17/12/20
Pek. Galian Tanah 2 days Wed 25/11/20 Thu 26/11/20 Sun 15/11/20 Sun 15/11/20 100%
Antirayap 1 day Fri 27/11/20 Fri 27/11/20 Mon 7/12/20 Mon 7/12/20 100%
Pasir Urug 2 days Sat 28/11/20 Sun 29/11/20 Mon 7/12/20 Mon 7/12/20 100%
Lantai Kerja 2 days Sat 28/11/20 Sun 29/11/20 Tue 8/12/20 85%
Pondasi Batu Kali Menerus 4 days Mon 30/11/20 Fri 04/12/20
Pembesian Sloof 3 days Sat 12/12/20 Mon 14/12/20
Bekisting 2 days Tue 15/12/20 Wed 16/12/20
Pengecoran 1 day Thu 17/12/20 Thu 17/12/20
3 PEK. PONDASI BATAKO (TERAS DEPAN) 22 days Wed 25/11/20 Thu 17/12/20
Pek. Galian Tanah 2 days Wed 25/11/20 Thu 26/11/20 Thu 12/11/20 Thu 11/12/20 100%
Antirayap 1 day Fri 27/11/20 Fri 27/11/20 Sun 15/11/20 Sun 11/15/20 100%
Pasir Urug 2 days Sat 28/11/20 Sun 29/11/20
Lantai Kerja 2 days Sat 28/11/20 Sun 29/11/20
Pondasi Batako 4 days Mon 30/11/20 Fri 04/12/20
Pembesian Sloof 3 days Sat 12/12/20 Mon 14/12/20
Bekisting 2 days Tue 15/12/20 Wed 16/12/20
Pengecoran 1 day Thu 17/12/20 Thu 17/12/20
A.2 PEK. UPPER STRUKTUR 73 days Fri 04/12/20 Tue 23/02/21
A 2.1 LANTAI DASAR 38 days Fri 04/12/20 Tue 19/01/21
1 PEK. TIE BEAM 38 days Fri 04/12/20 Tue 19/01/21
Perapihan Galian + Antirayap 1 day Fri 04/12/20 Fri 04/12/20 Thu 12/11/20 Sat 21/11/20 100%
Pembesian 3 days Sat 05/12/20 Mon 07/12/20 Sat 5/12/20 Sun 6/12/20 100%
Bekisting 2 days Tue 08/12/20 Wed 09/12/20 Sat 21/11/20 Mon 23/11/20 100%
Pengecoran 1 day Thu 10/12/20 Thu 10/12/20 Sun 6/12/20 Sun 6/12/20 100%
Pasang Batako 3 days Sun 17/01/21 Tue 19/01/21
2 PEK. PLAT LANTAI 4 days Fri 15/01/21 Mon 18/01/21
Pemadatan Tanah 2 days Fri 15/01/21 Sat 16/01/21
Pasir Urug 1 day Sun 17/01/21 Sun 17/01/21
Anti Rayap 1 day Sun 17/01/21 Sun 17/01/21
Plastik Cor 1 day Mon 18/01/21 Mon 18/01/21
Pengecoran 1 day Mon 18/01/21 Mon 18/01/21
3 PEK. KOLOM 9 days Sat 12/12/20 Sun 20/12/20
Pembesian 3 days Sat 12/12/20 Mon 14/12/20
Bekisting 4 days Tue 15/12/20 Fri 18/12/20
Pengecoran 2 days Sat 19/12/20 Sun 20/12/20
Coordination Meeting
TIME SCHEDULE | E4-15

Coordination Meeting
EVALUASI PEKERJAAN| E4-15
No. Uraian
Durasi
Durasi Rencana
Start Finish Start
Durasi Realisasi
Finish progres %
Evara 4-15
A PEKERJAAN STRUKTUR 27 days Fri 20/11/20 Tue 23/02/21
A.1 PEK. SUB STRUKTUR 2 days Fri 20/11/20 Thu 17/12/20
1 PEK. BOWPLANK 2 days Fri 20/11/20 Sat 21/11/20
Pek. Bowplank 11 days Fri 20/11/20 Sat 21/11/20 Fri 13/11/20 Sat 28/11/20 100%
PEK. PONDASI TAPAK 3 days Sun 22/11/20 Thu 03/12/20
Pek. Galian Tanah 1 day Sun 22/11/20 Tue 24/11/20 Sun 15/11/20 Sun 15/11/20 100%
Antirayap+Pasir Urug 1 day Wed 25/11/20 Wed 25/11/20 Sun 15/11/20 Sun 15/11/20 100%
Lantai Kerja 3 days Thu 26/11/20 Thu 26/11/20 Sat 28/11/20 Sat 28/11/20 100%
Pembesian 2 days Fri 27/11/20 Sun 29/11/20 Wed 18/11/20 Thu 19/11/20 100%
Bekisting 1 day Mon 30/11/20 Wed 02/12/20 Sat 28/11/20 Sat 28/11/20 100%
Pengecoran 22 days Thu 03/12/20 Thu 03/12/20 Sun 15/11/20 39%
2 PEK. BATU KALI 2 days Wed 25/11/20 Thu 17/12/20
Pek. Galian Tanah 1 day Wed 25/11/20 Thu 26/11/20 Sun 15/11/20 Sun 15/11/20 100%
Antirayap 2 days Fri 27/11/20 Fri 27/11/20 Sun 15/11/20 Sun 15/11/20 100%
Pasir Urug 2 days Sat 28/11/20 Sun 29/11/20 Mon 7/12/20 Mon 7/12/20 100%
Lantai Kerja 4 days Sat 28/11/20 Sun 29/11/20 Mon 7/12/20 Mon 7/12/20 100%
Pondasi Batu Kali Menerus 3 days Mon 30/11/20 Fri 04/12/20 Tue 8/12/20 85%
Pembesian Sloof 2 days Sat 12/12/20 Mon 14/12/20
Bekisting 1 day Tue 15/12/20 Wed 16/12/20
Pengecoran 22 days Thu 17/12/20 Thu 17/12/20
3 PEK. PONDASI BATAKO (TERAS DEPAN) 2 days Wed 25/11/20 Thu 17/12/20
Pek. Galian Tanah 1 day Wed 25/11/20 Thu 26/11/20 Sun 15/11/20 Sun 15/11/20 100%
Antirayap 2 days Fri 27/11/20 Fri 27/11/20
Pasir Urug 2 days Sat 28/11/20 Sun 29/11/20
Lantai Kerja 4 days Sat 28/11/20 Sun 29/11/20
Pondasi Batako 3 days Mon 30/11/20 Fri 04/12/20
Pembesian Sloof 2 days Sat 12/12/20 Mon 14/12/20
Bekisting 1 day Tue 15/12/20 Wed 16/12/20
Pengecoran 73 days Thu 17/12/20 Thu 17/12/20
A.2 PEK. UPPER STRUKTUR 38 days Fri 04/12/20 Tue 23/02/21
A 2.1 LANTAI DASAR 38 days Fri 04/12/20 Tue 19/01/21
1 PEK. TIE BEAM 1 day Fri 04/12/20 Tue 19/01/21
Perapihan Galian + Antirayap 3 days Fri 04/12/20 Fri 04/12/20 Thu 15/11/20 Thu 15/11/20 100%
Pembesian 2 days Sat 05/12/20 Mon 07/12/20 Sat 5/12/20 Sat 5/12/20 100%
Bekisting 1 day Tue 08/12/20 Wed 09/12/20 Fri 20/11/20 Mon 23/11/20 100%
Pengecoran 3 days Thu 10/12/20 Thu 10/12/20 Sat 5/12/20 Sat 5/12/20 100%
Pasang Batako 4 days Sun 17/01/21 Tue 19/01/21
2 PEK. PLAT LANTAI 2 days Fri 15/01/21 Mon 18/01/21
Pemadatan Tanah 1 day Fri 15/01/21 Sat 16/01/21
Pasir Urug 1 day Sun 17/01/21 Sun 17/01/21
Anti Rayap 1 day Sun 17/01/21 Sun 17/01/21
Plastik Cor 1 day Mon 18/01/21 Mon 18/01/21
Pengecoran 9 days Mon 18/01/21 Mon 18/01/21
3 PEK. KOLOM 3 days Sat 12/12/20 Sun 20/12/20
Pembesian 4 days Sat 12/12/20 Mon 14/12/20
Bekisting 2 days Tue 15/12/20 Fri 18/12/20
Pengecoran 55 days Sat 19/12/20 Sun 20/12/20
Coordination Meeting
EVALUASI PEKERJAAN| E4-12
No. Uraian
Durasi Rencana Durasi Realisasi
Durasi Start Finish Start Finish Progres%
Evara 4-12
A PEKERJAAN STRUKTUR 346 days Thu 29/04/21 Mon 25/04/22
A.1 PEK. SUB STRUKTUR 279 days Thu 29/04/21 Wed 16/02/22
1 PEK. BOWPLANK 254 days Thu 29/04/21 Sat 22/01/22
Pek. Bowplank 9 days Thu 29/04/21 Sat 22/01/22
PEK. PONDASI TAPAK 19 days Sun 23/01/22 Thu 10/02/22
Pek. Galian Tanah 3 days Sun 23/01/22 Tue 25/01/22 09/12/2020 09/12/2020 100%
Antirayap + Pasir Urug 1 day Wed 26/01/22 Wed 26/01/22 10/12/2020 12/12/2020 100%
Lantai Kerja 1 day Thu 27/01/22 Thu 27/01/22
Pembesian 3 days Sat 05/02/22 Mon 07/02/22
Bekisting 2 days Tue 08/02/22 Wed 09/02/22
Pengecoran 1 day Thu 10/02/22 Thu 10/02/22
2 PEK. BATU KALI 22 days Wed 26/01/22 Wed 16/02/22
Pek. Galian Tanah 2 days Wed 26/01/22 Thu 27/01/22 09/12/2020 09/12/2020 100%
Antirayap 1 day Fri 28/01/22 Fri 28/01/22 10/12/2020 12/12/2020 100%
Pasir Urug 2 days Sat 29/01/22 Sun 30/01/22
Lantai Kerja 2 days Sat 29/01/22 Sun 30/01/22
Pondasi Batu Kali Menerus 4 days Mon 31/01/22 Thu 03/02/22
Pembesian Sloof 3 days Fri 11/02/22 Sun 13/02/22
Bekisting 2 days Mon 14/02/22 Tue 15/02/22
Pengecoran 1 day Wed 16/02/22 Wed 16/02/22
3 PEK. PONDASI BATAKO (TERAS DEPAN) 21 days Wed 26/01/22 Tue 15/02/22
Pek. Galian Tanah 2 days Wed 26/01/22 Thu 27/01/22 09/12/2020 09/12/2020 100%
Antirayap 1 day Fri 28/01/22 Fri 28/01/22 10/12/2020 10/12/2020 100%
Pasir Urug 2 days Fri 28/01/22 Sat 29/01/22
Lantai Kerja 2 days Fri 28/01/22 Sat 29/01/22
Pondasi Batako 4 days Sun 30/01/22 Wed 02/02/22
Pembesian Sloof 3 days Thu 10/02/22 Sat 12/02/22
Bekisting 2 days Sun 13/02/22 Mon 14/02/22
Pengecoran 1 day Tue 15/02/22 Tue 15/02/22
A.2 PEK. UPPER STRUKTUR 73 days Fri 11/02/22 Mon 25/04/22
A 2.1 LANTAI DASAR 38 days Fri 11/02/22 Mon 21/03/22
1 PEK. TIE BEAM 38 days Fri 11/02/22 Mon 21/03/22
Perapihan Galian+ Antirayap 1 day Fri 11/02/22 Fri 11/02/22 10/12/2020 30%
Pembesian 3 days Sat 12/02/22 Mon 14/02/22
Bekisting 2 days Tue 15/02/22 Wed 16/02/22
Pengecoran 1 day Thu 17/02/22 Thu 17/02/22
Pasang Batako 3 days Sat 19/03/22 Mon 21/03/22
2 PEK. PLAT LANTAI 4 days Thu 17/03/22 Sun 20/03/22
Pemadatan Tanah 2 days Thu 17/03/22 Fri 18/03/22
Pasir Urug 1 day Sat 19/03/22 Sat 19/03/22
Anti Rayap 1 day Sat 19/03/22 Sat 19/03/22
Plastik Cor 1 day Sun 20/03/22 Sun 20/03/22
Pengecoran 1 day Sun 20/03/22 Sun 20/03/22
3 PEK. KOLOM 9 days Sat 19/02/22 Sun 27/02/22
Pembesian 3 days Sat 19/02/22 Mon 21/02/22
Bekisting 4 days Tue 22/02/22 Fri 25/02/22
Pengecoran 2 days Sat 26/02/22 Sun 27/02/22
Coordination Meeting
EVALUASI PEKERJAAN| E4-16
No. Uraian
Durasi Rencana Durasi Realisasi
Durasi Strart Finish Strart Finish Progres%
Evara 4-16
A PEKERJAAN STRUKTUR 94 days Fri 23/04/21 Fri 08/10/21
A.1 PEK. SUB STRUKTUR 27 days Fri 23/04/21 Thu 05/08/21
1 PEK. BOWPLANK 2 days Fri 23/04/21 Sun 30/05/21
Pek. Bowplank 2 days Fri 23/04/21 Sat 24/04/21
PEK. PONDASI TAPAK 19 days Sun 25/04/21 Sat 24/04/21
Pek. Galian Tanah 3 days Sun 25/04/21 Mon 24/05/21 09/12/2020 09/12/2020 100%
Antirayap + Pasir Urug 1 day Wed 28/04/21 Tue 27/04/21 10/12/2020 12/12/2020 100%
Lantai Kerja 1 day Thu 29/04/21 Wed 28/04/21
Pembesian 3 days Sat 08/05/21 Thu 29/04/21
Bekisting 2 days Tue 11/05/21 Mon 10/05/21
Pengecoran 1 day Mon 24/05/21 Wed 12/05/21
2 PEK. BATU KALI 22 days Wed 28/04/21 Mon 24/05/21
Pek. Galian Tanah 2 days Wed 28/04/21 Sun 30/05/21 09/12/2020 09/12/2020 100%
Antirayap 1 day Fri 30/04/21 Thu 29/04/21 10/12/2020 12/12/2020 100%
Pasir Urug 2 days Sat 01/05/21 Fri 30/04/21
Lantai Kerja 2 days Sat 01/05/21 Sun 02/05/21
Pondasi Batu Kali Menerus 4 days Mon 03/05/21 Sun 02/05/21
Pembesian Sloof 3 days Tue 25/05/21 Thu 06/05/21
Bekisting 2 days Fri 28/05/21 Thu 27/05/21
Pengecoran 1 day Sun 30/05/21 Sat 29/05/21
3 PEK. PONDASI BATAKO (TERAS DEPAN) 21 days Wed 28/04/21 Sun 30/05/21
Pek. Galian Tanah 2 days Wed 28/04/21 Sat 29/05/21 09/12/2020 09/12/2020 100%
Antirayap 1 day Fri 30/04/21 Thu 29/04/21 10/12/2020 10/12/2020 100%
Pasir Urug 2 days Fri 30/04/21 Fri 30/04/21
Lantai Kerja 2 days Fri 30/04/21 Sat 01/05/21
Pondasi Batako 4 days Sun 02/05/21 Sat 01/05/21
Pembesian Sloof 3 days Mon 24/05/21 Wed 05/05/21
Bekisting 2 days Thu 27/05/21 Wed 26/05/21
Pengecoran 1 day Sat 29/05/21 Fri 28/05/21
A.2 PEK. UPPER STRUKTUR 73 days Tue 25/05/21 Sat 29/05/21
A 2.1 LANTAI DASAR 38 days Tue 25/05/21 Thu 05/08/21
1 PEK. TIE BEAM 38 days Tue 25/05/21 Thu 01/07/21
Perapihan Galian+ Antirayap 1 day Tue 25/05/21 Thu 01/07/21 10/12/2020 30%
Pembesian 3 days Wed 26/05/21 Tue 25/05/21
Bekisting 2 days Sat 29/05/21 Fri 28/05/21
Pengecoran 1 day Mon 31/05/21 Sun 30/05/21
Pasang Batako 3 days Tue 29/06/21 Mon 31/05/21
2 PEK. PLAT LANTAI 4 days Sun 27/06/21 Thu 01/07/21
Pemadatan Tanah 2 days Sun 27/06/21 Wed 30/06/21
Pasir Urug 1 day Tue 29/06/21 Mon 28/06/21
Anti Rayap 1 day Tue 29/06/21 Tue 29/06/21
Plastik Cor 1 day Wed 30/06/21 Tue 29/06/21
Pengecoran 1 day Wed 30/06/21 Wed 30/06/21
3 PEK. KOLOM 9 days Wed 02/06/21 Wed 30/06/21
Pembesian 3 days Wed 02/06/21 Thu 10/06/21
Bekisting 4 days Sat 05/06/21 Fri 04/06/21
Pengecoran 2 days Wed 09/06/21 Tue 08/06/21
Coordination Meeting
EVALUASI PEKERJAAN| E2-3
Durasi Rencana Durasi Realisasi
No. Uraian
Durasi Start Finish Start Finish Progres%
Evara 2-3
A PEKERJAAN STRUKTUR
A.1 PEK. SUB STRUKTUR
1 PEK. BOWPLANK 11/12/2020 11/12/2020 100%
Pek. Bowplank
PEK. PONDASI TAPAK
Pek. Galian Tanah 11/12/2020 80%
Antirayap + Pasir Urug
Lantai Kerja
Pembesian
Bekisting
Pengecoran
2 PEK. BATU KALI
Pek. Galian Tanah
Antirayap
Pasir Urug
Lantai Kerja
Pondasi Batu Kali Menerus
Pembesian Sloof
Bekisting
Pengecoran
3 PEK. PONDASI BATAKO (TERAS DEPAN)
Pek. Galian Tanah
Antirayap
Pasir Urug
Lantai Kerja
Pondasi Batako
Pembesian Sloof
Bekisting
Pengecoran
Coordination Meeting
THANK YOU

Head Office:
PT. Waskita Karya Realty
Gedung Waskita Rajawali Tower, 6th Floor
Jl. MT. Haryono Kav. No. 12 Bidara Cina, Jatinegara, Jakarta 13330
Ph. (+6221) 80600 880
Website: www.waskitarealty.co.id
Coordination Meeting

You might also like