ID Task Name Duration Start Finish % Complete Text2 Wed 10/11 Sat 13/11 Tue 16/11 Fri 19/11

Finish % Complete Text2 Wed 10/11 Sat 13/11 Tue 16/11 Fri 19/11 Mon 22/11
1 LINGKUP PEKERJAAN PENORMALAN VIBRASI TURBIN #2 UPK OMBILIN 10 days Sat 13/11/21 Mon 22/11/21 91% 91%
2 PRE-SHUT DOWN / PREPARATIONS 3 days Sat 13/11/21 Mon 15/11/21 100%
3 SAFETY PERMIT DAN LOTO 1 day Sat 13/11/21 Sat 13/11/21 100% 100%
4 COOLING DOWN 3 days Sat 13/11/21 Mon 15/11/21 100% 100%
5 PEKERJAAN TEAM INSTRUMENT DAN CONTROL 4 days Mon 15/11/21 Thu 18/11/21 100% 100%
100%
6 PEMBONGKARAN INSTUMENTASI BEARING 1 DAN BEARING 2 1 hr Mon 15/11/21 Mon 15/11/21 100% 100%
7 KALIBRASI SENSOR VIBRASI DAN TEMPERATUR 2 days Tue 16/11/21 Wed 17/11/21 100% 100%
8 PENGECEKAN MODUL MAIN STOP VALVE DAN GOVERNOR VALVE 3 days Mon 15/11/21 Wed 17/11/21 100% 100%
9 REASSEMBLY SENSOR VIBRASI DAN TEMPERATUR 1 day Thu 18/11/21 Thu 18/11/21 100% 100%
10 PEKERJAAN TEAM MEKANIK TURBIN 6 days Mon 15/11/21 Sat 20/11/21 100%
11 BUKA COVER TURNING GEAR 1 day Mon 15/11/21 Mon 15/11/21 100% 100%
12 PENGUKURAN DAN CENTERING THRUST BEARING 1 day Tue 16/11/21 Tue 16/11/21 100% 100%
13 BUKA COVER DAN BEARING 1 DAN 2 4 days Tue 16/11/21 Fri 19/11/21 100% 100%
14 CLEANING, INSPEKSI, BEARING 1 DAN BEARING 2 1 day Thu 18/11/21 Thu 18/11/21 100% 100%
15 ASSEMBLY BEARING 1 DAN 2 1 day Thu 18/11/21 Thu 18/11/21 100% 100%
16 ALLIGMENT TURBIN 1 day Sat 20/11/21 Sat 20/11/21 100% 100%
17 START-UP 2 days Sun 21/11/21 Mon 22/11/21 0%
18 RUNNING TURNING GEAR 1 day Mon 22/11/21 Mon 22/11/21 0% 0%
19 FIRING 1 day Mon 22/11/21 Mon 22/11/21 0% 0%