CUSTOMER END-USER

1847-A PUMP PACKAGE


VENDOR
PROJECT TITLE
PENGADAAN POMPA TYPE
RECIPROCATING PUMP API 674 AREA
SPU-E DAN SPU-F SANGASANGA FIELD

PROJECT SCHEDULE

CUSTOMER : PT. LERINDRO INTERNASIONAL

END USER : PERTAMINA EP ASSET 5 SANGASANGA FIELD

PROJECT NAME : RECIPROCATING PUMP API 674 AREA SPU-E DAN SPU-F SANGASANGA

PO NO : JKT-200085

VENDOR : NATIONAL OILWELL VARCO

NOV PROJECT REF : JOB 20-EH018

DOCUMENT NO : NOV-PTLI-20EH018-DOC-001

REVISION
ISSUE DATE REVISION NOTES
N° PREPARED REVIEWED APPROVED

A 31-MAR-2021 FIRST ISSUE FOR APPROVAL HT SG


Customer PO: JKT-200085 PENGADAAN POMPA TYPE RECIPROCATING PUMP API 674 AREA SPU-E DAN SPU-F SANGASANGA FIELD
Customer Name : PT. LERINDRO INTERNASIONAL
End-User: PERTAMINA EP ASSET 5 SANGASANGA FIELD
ID Task Task Name Duration Start Finish November 2020 December 2020 January 2021 February 2021 March 2021 April 2021 May 2021 June 2021 July 2021 August 2021 September 202
Mode 28 2 7 12 17 22 27 2 7 12 17 22 27 1 6 11 16 21 26 31 5 10 15 20 25 2 7 12 17 22 27 1 6 11 16 21 26 1 6 11 16 21 26 31 5 10 15 20 25 30 5 10 15 20 25 30 4 9 14 19 24 29 3
1 1847A PUMP PACKAGE- PERTAMINA EP 201 days Tue 11/10/20 Tue 8/17/21
2 1847A PUMP PUMP PACKAGE 201 days Tue 11/10/20 Tue 8/17/21
3 Project Contract Review 28 days Tue 11/10/20 Thu 12/17/20
4 Purchase Order Receipt date 1 day Tue 11/10/20 Tue 11/10/20 100%
5 Order handover from proposals to projects 2 days Wed 11/11/20 Thu 11/12/20 100%
6 Technical and Design review 2 wks Sun 11/15/20 Thu 11/26/20 100%
7 Vendor Quote validation 2 wks Sun 11/29/20 Thu 12/10/20 100%
8 Order Processing and acknowledgement 1 wk Sun 12/13/20 Thu 12/17/20 100%
9 Package Documents & Drawings Submission/Approval 80 days Sun 2/7/21 Thu 5/27/21
10 Pump Package GAD Review & Submission 8 wks Sun 2/7/21 Thu 4/1/21 43%
11 Pulsation Dampener Drawing 4 wks Sun 4/4/21 Thu 4/29/21 0%
12 Relief Valve Datasheet 6 wks Sun 4/4/21 Thu 5/13/21 0%
13 Inspection and Test Plan 4 wks Sun 4/4/21 Thu 4/29/21 0%
14 Test Procedures 4 wks Sun 5/2/21 Thu 5/27/21 0%
15 Procurement Activities and Delivery to Fab Shop 140 days Sun 12/20/20 Thu 7/1/21
16 Pump Manufacturing at TULSA, USA 22 wks Sun 12/20/20 Thu 5/20/21
17 Pump Shipment to Dubai 6 wks Sun 5/23/21 Thu 7/1/21
18 Motor 17 wks Sun 1/31/21 Thu 5/27/21 26%
19 Belt Drive 10 wks Sun 2/14/21 Thu 4/22/21 24%
20 Relief Valve 8 wks Sun 2/14/21 Thu 4/8/21 30%
21 Dampeners 12 wks Sun 2/14/21 Thu 5/6/21 20%
22 Skid fabrication and painting 40 days Sun 5/2/21 Thu 6/24/21
23 1847A Pump Package - 02 Nos Tag No : SPU-E/F 40 days Sun 5/2/21 Thu 6/24/21
24 Skid, guard and supports fabrication 6 wks Sun 5/2/21 Thu 6/10/21 0%
25 Skid, guard and supports painting 2 wks Sun 6/13/21 Thu 6/24/21 0%
26 Assembly and Testing 10 days Sun 7/4/21 Thu 7/15/21
27 1847A Pump Package - 02 Nos Tag No : SPU-E/F 10 days Sun 7/4/21 Thu 7/15/21
28 Pump and Motor assembly and allignment 1 wk Sun 7/4/21 Thu 7/8/21
29 Mounting of Accessories 1 day Sun 7/11/21 Sun 7/11/21
30 Oil filling, Dampener charging, Preparing for testing 1 day Mon 7/12/21 Mon 7/12/21
31 Internal Pump package functional test 1 day Tue 7/13/21 Tue 7/13/21
32 Internal Punch List closure 2 days Wed 7/14/21 Thu 7/15/21
33 Packing and Shipment (Ex-Works) 23 days Sun 7/18/21 Tue 8/17/21
34 Oil and Nitrogen removal, Cleaning 1 day Sun 7/18/21 Sun 7/18/21
35 Documentation&Packing of the Skids 1 day Mon 7/19/21 Mon 7/19/21
36 Delivery, Ex-Works, Dubai 1 day Tue 7/20/21 Tue 7/20/21
37 Final Dossier (MRB&IOM) 4 wks Wed 7/21/21 Tue 8/17/21

Task Inactive Task Manual Summary Rollup External Milestone Critical

Split Inactive Milestone Manual Summary Deadline Critical Split


Date: Tue 3/30/21 Milestone Inactive Summary Start-only Path Predecessor Milestone Task Progress

Summary Manual Task Finish-only Path Predecessor Summary Task Manual Progress

Project Summary Duration-only External Tasks Path Predecessor Normal Task

NOV Ref: Job 20-EH018 Page 1 Project/Production/Fabrication Schedule


TAG No : SPU-E/F NOV-PTLI-20EH018-DOC-001
Rev : A