PROPOSED PHASE 2 FACTORY FOR OLAM

Project Schedule

ID Task Name Duration Start Finish Sep '10 Oct '10 Nov '10 Dec '10 Jan '11 Feb '11 Mar '11 Apr '11 May '11 Jun '11 Jul '11 Aug '11 Sep '11
2/0 9/0 5/09 2/0 9/0 6/0 3/10 0/1 7/1 4/1 1/1 7/11 4/1 1/1 8/1 5/12 2/1 9/1 6/1 2/019/01 6/0 3/0 0/0 6/02 3/0 0/0 7/0 6/03 3/0 0/0 7/0 3/04 0/0 7/0 4/0 1/05 8/05 5/0 2/0 9/0 5/06 2/0 9/0 6/0 3/07 0/0 7/0 4/0 1/0 7/08 4/0 1/0 8/0 4/09 1/0 8/0
1 Commencement 0 wks 15/09/10 15/09/10 15/09

2 Feasibility Study 4 wks 15/09/10 12/10/10

3 Design 11.4 wks 13/10/10 30/12/10

4 Architectural Design 7.4 wks 13/10/10 2/12/10

5 50% 2 wks 13/10/10 26/10/10

6 Owner Review & Approval 1 wk 29/10/10 4/11/10

7 90% 4 wks 5/11/10 2/12/10

8 Structural Design 6 wks 5/11/10 16/12/10

9 40% 3 wks 5/11/10 25/11/10

10 90% 3 wks 26/11/10 16/12/10

11 HVAC, Sanitary & Plumbing, Electrical 7 wks 5/11/10 23/12/10

12 40% 3 wks 5/11/10 25/11/10

13 Owners Approval 1 wk 26/11/10 2/12/10

14 90% 3 wks 3/12/10 23/12/10

15 Fire Protection 4 wks 5/11/10 2/12/10

16 50% 2 wks 5/11/10 18/11/10

17 90% 2 wks 19/11/10 2/12/10

18 Coordination 1 wk 24/12/10 30/12/10

19 Permits 13.4 wks 12/10/10 13/01/11

20 List of Documentations required 0 wks 12/10/10 12/10/10 12/10

21 Owners documents 3 wks 13/10/10 2/11/10

22 Drawings 3 wks 27/10/10 16/11/10

23 Fire Protection submission 1 wk 3/12/10 9/12/10

24 Approval 3 wks 10/12/10 30/12/10

25 Building Permit Submission 1 wk 17/12/10 23/12/10

26 Approval 3 wks 24/12/10 13/01/11

27 Tender 17 wks 12/10/10 8/02/11

28 List of tenderers 0 wks 12/10/10 12/10/10 12/10

29 Prequalification 2 wks 13/10/10 26/10/10

30 Documentation 4 wks 3/12/10 30/12/10

31 Tender Invitation 0 wks 30/12/10 30/12/10 30/12

32 Tender Period 3 wks 31/12/10 20/01/11

33 Tender Close 0 wks 20/01/11 20/01/11 20/01

34 Evaluation 4 days 21/01/11 26/01/11

35 Recommendations 4 days 27/01/11 1/02/11

36 Award 1 wk 2/02/11 8/02/11

37 Construction (7 months) 30 wks 16/02/11 13/09/11

38 Piling 4 wks 16/02/11 15/03/11

39 Superstructure 22 wks 16/03/11 16/08/11

40 Completion 8 wks 20/07/11 13/09/11

Project: Olam 2 Task Split Progress Milestone Task


Date: 6/11/10