You are on page 1of 1

StackerReclaimer Slip Ring Replacement Plan

ID Task Task Name Duration Start Finish Predecessors 03 Oct '22 10 Oct '22 17 Oct '22
Mode T F S S M T W T F S S M T W T F S S M T W T
1 Stacker/Reclaimer Slip Ring Replacement 8.42 days Fri 30/09/22 7:00 AM Tue 18/10/22 11:00 AM 0%
2 Mobilize the new slip ring assembly 0.29 days Fri 30/09/22 7:00 AM Fri 30/09/22 3:00 PM 0%
3 Check integrity of monorail hoist 2 hrs Fri 30/09/22 7:00 AM Fri 30/09/22 9:00 AM 0%
4 Transport new slip ring from warehouse to coal dome 2 hrs Fri 30/09/22 9:00 AM Fri 30/09/22 11:00 AM 3 0%
area using boom truck at 245 degrees position
5 Lift new slip ring from coal dome ground elevation to 2 hrs Fri 30/09/22 11:00 AM Fri 30/09/22 2:00 PM 4 0%
stacker boom elevation using hoist HO-09
6 Secure the new slip ring and cover with anti-dust 1 hr Fri 30/09/22 2:00 PM Fri 30/09/22 3:00 PM 5 0%
protection.
7 Preparation Works 0.17 days Wed 12/10/22 7:00 AM Wed 12/10/22 11:00 AM 0%
8 Prepare PTW 1 hr Wed 12/10/22 7:00 AM Wed 12/10/22 8:00 AM 0%
9 Clean the working area free from dust particles 2 hrs Wed 12/10/22 7:00 AM Wed 12/10/22 9:00 AM 8SS 0%
10 Mobilize the tools, equipment and materials 2 hrs Wed 12/10/22 9:00 AM Wed 12/10/22 11:00 AM 9 0%
11 Clearing of the access on the slip ring chamber 0.25 days Wed 12/10/22 11:00 AM Wed 12/10/22 6:00 PM 0%
12 LOTO stacker equipment 1 hr Wed 12/10/22 11:00 AM Wed 12/10/22 12:00 PM 10 0%
13 Erect scaffold for lifting support above the slip ring 4 hrs Wed 12/10/22 1:00 PM Wed 12/10/22 5:00 PM 12 0%
chamber
14 Release the stacker belt tension 1 hr Wed 12/10/22 1:00 PM Wed 12/10/22 2:00 PM 13SS 0%
15 Sway the belt to the right side facing the conveyor drive 1 hr Wed 12/10/22 2:00 PM Wed 12/10/22 3:00 PM 14 0%
end and secure with rope
16 Remove conveyor rollers and side support 1 hr Wed 12/10/22 3:00 PM Wed 12/10/22 4:00 PM 15 0%
17 Remove the cable tray and piping connection on the 1 hr Wed 12/10/22 4:00 PM Wed 12/10/22 5:00 PM 16 0%
chamber cover
18 Remove the slip ring chamber cover 1 hr Wed 12/10/22 5:00 PM Wed 12/10/22 6:00 PM 17 0%
19 Unmount, disconnect and pullout of old slip ring assembly 0.58 days Thu 13/10/22 7:00 AM Fri 14/10/22 10:00 AM 0%

20 LOTO the main supply of the stacker/reclaimer 1 hr Thu 13/10/22 7:00 AM Thu 13/10/22 8:00 AM 18 0%
21 Disconnect water and air pipe line on the slip ring 1 hr Thu 13/10/22 8:00 AM Thu 13/10/22 9:00 AM 20 0%
assembly
22 Tag and disconnect all the power, control and fiber optic 8 hrs Thu 13/10/22 9:00 AM Thu 13/10/22 6:00 PM 21 0%
cable
23 Unmount and lift the old slip ring assembly from the 4 hrs Thu 13/10/22 6:00 PM Fri 14/10/22 10:00 AM 22 0%
chamber
24 Mount, reconnection of new slip ring assembly 0.54 days Fri 14/10/22 10:00 AM Sat 15/10/22 12:00 PM 0%
25 Drag, lower and mount the new slip ring assembly into 4 hrs Fri 14/10/22 10:00 AM Fri 14/10/22 3:00 PM 23 0%
the chamber
26 Reconnect all the power, control and fiber optic cable 8 hrs Fri 14/10/22 3:00 PM Sat 15/10/22 11:00 AM 25 0%

27 Reconnect the piping 1 hr Sat 15/10/22 11:00 AM Sat 15/10/22 12:00 PM 26 0%


28 Commission and test new slip ring assembly 0.46 days Sat 15/10/22 1:00 PM Sun 16/10/22 12:00 PM 0%
29 Conduct insulation resistance test on all cable 2 hrs Sat 15/10/22 1:00 PM Sat 15/10/22 3:00 PM 27 0%
30 Conduct contact resistance on all cable connection 2 hrs Sat 15/10/22 3:00 PM Sat 15/10/22 5:00 PM 29 0%
31 Conduct optical test on fiber optic connection 2 hrs Sat 15/10/22 5:00 PM Sat 15/10/22 7:00 PM 30 0%
32 Remove LOTO and energize the stacker/reclaimer 1 hr Sun 16/10/22 7:00 AM Sun 16/10/22 8:00 AM 31 0%
33 Conduct functional test on the pressurization system of 2 hrs Sun 16/10/22 8:00 AM Sun 16/10/22 10:00 AM 32 0%
the slip ring
34 Conduct functional test on the stacker slewing 2 hrs Sun 16/10/22 10:00 AM Sun 16/10/22 12:00 PM 33 0%
35 Re-instatement of stacker belt 0.79 days Sun 16/10/22 1:00 PM Tue 18/10/22 9:00 AM 0%
36 Re-instate slip ring chamber cover 1 hr Sun 16/10/22 1:00 PM Sun 16/10/22 2:00 PM 34 0%
37 Re-instate cable tray and piping connection on the 1 hr Sun 16/10/22 2:00 PM Sun 16/10/22 3:00 PM 36 0%
chamber cover
38 Re-instate conveyor rollers and side support 2 hrs Sun 16/10/22 3:00 PM Sun 16/10/22 5:00 PM 37 0%
39 Release rope and align belt conveyor 1 hr Sun 16/10/22 5:00 PM Sun 16/10/22 6:00 PM 38 0%
40 Re-tension the stacker belt 1 hr Sun 16/10/22 6:00 PM Sun 16/10/22 7:00 PM 39 0%
41 Remove the scaffold for the lifting support above the slip 4 hrs Mon 17/10/22 1:00 PM Mon 17/10/22 5:00 PM 40 0%
ring chamber
42 Remove LOTO for the stacker equipment 1 hr Tue 18/10/22 7:00 AM Tue 18/10/22 8:00 AM 41 0%
43 Function test the stacker belt conveyor 1 hr Tue 18/10/22 8:00 AM Tue 18/10/22 9:00 AM 42 0%
44 Housekeeping 0.08 days Tue 18/10/22 9:00 AM Tue 18/10/22 11:00 AM 0%
45 De-mobilize tools, equipment and materials 2 hrs Tue 18/10/22 9:00 AM Tue 18/10/22 11:00 AM 43 0%
46 Transport old slip ring assembly from stacker boom to 2 hrs Tue 18/10/22 9:00 AM Tue 18/10/22 11:00 AM 43 0%
Workshop

Page 1