ID Task % Complete Work Order Task Name Support PIC Duration Start Finish 0 December 2020 January 2021

Support PIC Duration Start Finish 0 December 2020 January 2021 Feb
Mode 17 22 27 02 07 12 17 22 27 01 06 11 16 21 26 31
1 83% U1 SE 2020 (22 November 2020 ‐ 31 January 2021) 71 days Sun 22/11/20 12:55Sun 31/01/21 11:59 P
8 93% BOILER WORKS 38 days Sun 22/11/20 12:55Tue 29/12/20 6:00 P
10 92% Boiler ‐ Furnace & Gas Path works 38 days Sun 22/11/20 12:55Tue 29/12/20 6:00 P
12 0% Hanger springs for boiler ‐ rest of them have to be  M1/Co20 days Wed 09/12/20 7:30 Mon 28/12/20 6:00 
replaced AM PM
19 85% 20/102265 PSH‐1: replace/rebuild tubes after thickeness  M1/Co20 days Wed 02/12/20 7:30 Mon 21/12/20 6:00  02/12 21/12
measurement AM PM
22 95% PSH‐2 & SSH split ring casting inspection, repair & replace M1/Co21 days Sun 29/11/20 6:00  Tue 08/12/20 1:30  29/11 08/12
if needed PM AM
23 95% Final SSH & RH inspection & repair tie bar spacers M1/Co15 days Mon 30/11/20 7:30 Mon 14/12/20 6:00 P 30/11 14/12
29 0% Remove Scaffolding in Boiler SSH Civil/Co96 hrs Mon 21/12/20 6:00 Fri 25/12/20 6:00 PM 21/12 25/12
30 0% Remove Gondola & Remove Scaffold in Bottom Slope Civil/Co72 hrs Fri 18/12/20 6:00 PMMon 21/12/20 6:00 P 18/12 21/12
33 96% Backpass Area 29 days Mon 23/11/20 12:5 Mon 21/12/20 6:00 P
45 0% Close Backpass manhole M1 1 day Fri 18/12/20 7:30 AMFri 18/12/20 6:00 PM 18/12 18/12
58 97% Wind Box System 31 days Tue 24/11/20 7:30 AThu 24/12/20 6:00 P
65 0% Close Windbox manhole M1 1 day Wed 23/12/20 7:30 Wed 23/12/20 6:00 P 23/12 23/12
68 88% Penthouse Area 29 days Mon 23/11/20 12:5 Mon 21/12/20 6:00 P
76 0% Close Penthouse manhole M1 1 day Mon 21/12/20 7:30 Mon 21/12/20 6:00 P 21/12 21/12
77 80% SSCC Area (Bottom Ash Conveyor) 31 days Wed 25/11/20 7:30 Sat 26/12/20 12:00 A
79 75% 19/70406 SSCC‐ inspection & repair if needed (submerged  Scaffold M1/Co26 days Mon 30/11/20 7:30 Fri 25/12/20 6:00  30/11 25/12
pulleys; shafts; drive gearbox and motor; sprockets;  AM PM
chain tensioner; basalt. Replace skirt seal)
80 90% 20/107433 SSCC Seal Skirt replacement Scaffold M1/Co25 days Mon 30/11/20 7:30 Thu 24/12/20 6:00 PM 30/11 24/12
81 0% SSCC Oil Change M3 2 days Sun 20/12/20 7:30 AMon 21/12/20 6:00 P 20/12 21/12
103 97% FD Fan 22 days Mon 23/11/20 7:30 Mon 14/12/20 6:00 P
117 50% FDF A&B close Manhole M1 1 day Mon 14/12/20 7:30 Mon 14/12/20 6:00 P 14/12 14/12
148 80% Seal Air Fans System 7 days Wed 25/11/20 7:30 Tue 01/12/20 6:00 P
149 80% 20/107895 Seal air Dampers Inspection (incl. expantion joint) M1 7 days Wed 25/11/20 7:30 Tue 01/12/20 6:00 PM5/11 01/12
155 88% Air Heater 36 days Mon 23/11/20 7:30 Mon 28/12/20 6:00 P
161 80% 20/108018 A/H A Oil changes (support,guide,airmotor etc) M3 3 days Sat 05/12/20 7:30 AMon 07/12/20 6:00 P 05/12 07/12
162 80% 20/108046 A/H A Sector Plate adjustmet & LCS setting M1 6 days Tue 24/11/20 7:30 ASun 29/11/20 6:00 PM4/11 29/11
164 0% A/H A Remove scaffold Civil/Co1 day Mon 30/11/20 7:30 Mon 30/11/20 6:00 P 30/11 30/11
171 80% 20/108054 A/H B Sector Plate adjustmet & LCS setting M1 24 days Tue 24/11/20 7:30 AThu 17/12/20 6:00 PM4/11 17/12
173 0% A/H B Remove scaffold Civil/Co1 day Fri 18/12/20 7:30 AM
Fri 18/12/20 6:00 PM 18/12 18/12
175 0% A/H A & B close manhole M1 1 day Sun 20/12/20 7:30 ASun 20/12/20 6:00 PM 20/12 20/12
176 0% A/H A & B gearbox inspection (fluid coupling, pin rack  M1/Co10 days Sat 05/12/20 7:30  Mon 14/12/20 6:00  05/12 14/12
& sprocket adjustment) AM PM
182 90% A/H A & B inlet duct inspection and repair if needed M1/Co14 days Tue 15/12/20 7:30  Mon 28/12/20 6:00  15/12 28/12
AM PM
183 94% ESP 37 days Mon 23/11/20 12:5 Tue 29/12/20 6:00 P
193 0% ESP Close Manhole M1 1 day Mon 28/12/20 7:30 Mon 28/12/20 6:00 P 28/12 28/12
195 70% 20/108096 Inspect roof cladding ESP for leaking and repair if  Civil/Co20 days Tue 08/12/20 7:30  Sun 27/12/20 6:00  08/12 27/12
required AM PM
196 0% ESP Remove scaffolding Civil
1 day Mon 28/12/20 7:30 Mon 28/12/20 6:00 P 28/12 28/12
215 87% FGD WORKS 38 days Sun 22/11/20 12:55Tue 29/12/20 6:00 P
216 87% Mist Eliminator 36 days Sun 22/11/20 12:55Sun 27/12/20 6:00 P
221 90% 20/102089 Mist eliminator trays : full replacement M22 29 days Tue 24/11/20 7:30 ATue 22/12/20 6:00 PM4/11 22/12

Page 1
ID Task % Complete Work Order Task Name Support PIC Duration Start Finish 0 December 2020 January 2021 Feb
Mode 17 22 27 02 07 12 17 22 27 01 06 11 16 21 26 31
224 0% Close Absorber Tank Top Duct manhole M22 1 day Wed 23/12/20 7:30 Wed 23/12/20 6:00 P 23/12 23/12
225 0% 20/108280 ME valves inspection M22/C9 days Sat 19/12/20 7:30 ASun 27/12/20 6:00 PM 19/12 27/12
227 86% Absorber Tank 34 days Mon 23/11/20 12:5 Sun 27/12/20 2:00 A
233 65% 20/105483 Absorber wall Repair the liner M22 17 days Wed 02/12/20 7:30 Fri 18/12/20 6:00 PM 02/12 18/12
235 0% Scaffold dismantle Civil/Co2 days Sat 19/12/20 7:30 ASun 20/12/20 6:00 PM 19/12 20/12
237 65% 20/108280 Absorber tank: inspection of the floor M22 5 days Mon 21/12/20 7:30 Fri 25/12/20 6:00 PM 21/12 25/12
238 0% 20/108292 Limestone slurry pipes replacement juni‐aug doM22 17 days Wed 25/11/20 7:30 Fri 11/12/20 6:00 PM
240 65% Absorber Tank Agitator 20 days Wed 25/11/20 7:30 Mon 14/12/20 6:00 P
241 65% 20/108298 Agitator Mech Seals Service Scaffold M22 20 days Wed 25/11/20 7:30 Mon 14/12/20 6:00 P5/11 14/12
242 65% 20/108298 Agitator Replace Blades and shafts M22 20 days Wed 25/11/20 7:30 Mon 14/12/20 6:00 P5/11 14/12
243 100% Absorber Recirculation Pump 25 days Tue 24/11/20 7:30 AFri 18/12/20 6:00 PM
247 0% ARP Expantion Joint Replacement M22 17 days Wed 25/11/20 7:30 Fri 11/12/20 6:00 PM
250 0% Close Absorber Tank Bottom Manhole M22 1 day Sat 26/12/20 7:30 ASat 26/12/20 6:00 PM 26/12 26/12
254 95% FGD Inlet Duct 37 days Mon 23/11/20 7:30 Tue 29/12/20 6:00 P
255 85% 20/108192 Abs Inlet Duct Inspection & liner repair if needed M22/C30 days Mon 23/11/20 7:30 Tue 22/12/20 6:00 PM /11 22/12
259 83% FGD Outlet Duct 34 days Wed 25/11/20 7:30 Mon 28/12/20 6:00 P
260 75% 20/108206 FGD outlet duct Inspection & liner repair if needed M22/C30 days Wed 25/11/20 7:30 Thu 24/12/20 6:00 PM 5/11 24/12
261 75% 20/108212 FGD outlet duct expantion joint (GG‐X509) inspection M22 28 days Thu 26/11/20 7:30  Wed 23/12/20 6:00  26/11 23/12
AM PM
262 95% 20/108310 Stack Inlet Flue Expansion Joint (GG‐X510) Replacement M22/C27 days Wed 02/12/20 7:30 Mon 28/12/20 6:00  02/12 28/12
AM PM
265 47% FGD Bypass Duct 27 days Wed 02/12/20 7:30 Mon 28/12/20 6:00 P
266 60% 20/108178 FGD by‐pass duct : inspection & liner repair if needed M22/C10 days Fri 18/12/20 7:30  Sun 27/12/20 6:00  18/12 27/12
AM PM
269 0% 20/108233 FGD by‐pass guillotine damper: inspection & stroke test C1/M214 days Tue 15/12/20 7:30  Mon 28/12/20 6:00  15/12 28/12
AM PM
279 88% TURBINE WORKS 69 days Sun 22/11/20 12:55Fri 29/01/21 7:59 PM
280 91% TURBINE & AUXILIARY WORKS 38 days Mon 23/11/20 7:30 Wed 30/12/20 7:00 P
294 98% 20/102155 Turbine area Valve Service (ref. to Valve List). All drain  M2/C230 days Wed 25/11/20 7:30 Thu 24/12/20 6:00  5/11 24/12
control valves + actuators from HP‐LP heaters should  AM PM
opened and checked
295 35% 20/104625 Actuator minimum flow Replacement C2/M29 days Sat 19/12/20 7:30 ASun 27/12/20 6:00 PM 19/12 27/12
297 95% 20/108520  Turbine aux Valve Replacement (ref. to Valve List :  M2/Ar 25 days Wed 25/11/20 7:30 Sat 19/12/20 6:00  5/11 19/12
20/108524  HD‐LCV002, HD‐LCV005). Drain isolation valves from Hot  AM PM
20/108528  reheat, Cold Reheat, and Main Steam Pipeline.
20/108532 
20/108537
316 89% Condenser Steam Side 33 days Wed 25/11/20 2:55 Sun 27/12/20 6:00 P
319 90% 20/108712 20 Condenser Steam Side Inspection and repair M2/Co26 days Tue 22/12/20 6:00 PM27/11
Fri 27/11/20 7:30 AM 22/12
320 90% 20/108718 Condenser expansion joint inspection (physical check + M2/Co26 days Fri 27/11/20 7:30  Tue 22/12/20 6:00  27/11 22/12
clamp bolts tighteness inspection) AM PM
322 0% Condencer tube leak test (CWP inservice: inlet press  M2/O 1 day Sun 27/12/20 7:30  Sun 27/12/20 6:00  27/12 27/12
1~1,2 bar) AM PM
324 0% Condenser Steam Side Manhole closing (incl. PTW) M2 1 day Sun 27/12/20 7:30  Sun 27/12/20 6:00  27/12 27/12
AM PM
329 92% Stop Log ‐sea water intake 38 days Mon 23/11/20 7:30 Wed 30/12/20 7:00 P
332 95% 20/102336 Inspect Travelling Screen A + install modification seal  M2/Co27 days Thu 26/11/20 7:30  Fri 25/12/20 1:15  26/11 25/12
plate & rubber seal AM PM
333 95% 20/102336 Repair Trav Screen A + Touch Up paint. Repair the shaft M2/Co25 days Wed 02/12/20 7:30 Sat 26/12/20 6:00  02/12 26/12
AM PM
Page 2
ID Task % Complete Work Order Task Name Support PIC Duration Start Finish 0 December 2020 January 2021 Feb
Mode 17 22 27 02 07 12 17 22 27 01 06 11 16 21 26 31
335 0% Remove scaffold in A line M2/Co1 day Sun 27/12/20 7:30 ASun 27/12/20 6:00 PM 27/12 27/12
336 0% Equalizing water Stop Log A & remove Stop Log M2/Co1 day Tue 29/12/20 7:30 ATue 29/12/20 6:00 PM 29/12 29/12
339 95% 20/102341 Inspect Travelling Screen B + install modification seal  M2/Co28 days Thu 26/11/20 7:30  Sun 27/12/20 3:09  26/11 27/12
plate & rubber seal AM PM
340 95% Repair Trav Screen B + Touch Up paint. Repair the shaft M2/Co25 days Fri 04/12/20 7:30  Mon 28/12/20 6:00  04/12 28/12
AM PM
342 0% Remove scaffold in B line M2/Co1 day Tue 29/12/20 7:30 ATue 29/12/20 6:00 PM 29/12 29/12
343 0% Equlaizing water Stop Log B & remove Stop Log M2/Co1 day Wed 30/12/20 7:30 Wed 30/12/20 6:00 P 30/12 30/12
349 94% CWP A 23 days Thu 03/12/20 7:30 AFri 25/12/20 6:00 PM
351 85% CWP A discharge liner repair M2/Co10 days Tue 15/12/20 7:30 AThu 24/12/20 6:00 PM 15/12 24/12
356 94% CWP B 27 days Thu 03/12/20 7:30 ATue 29/12/20 6:00 P
358 85% CWP B Suction & Disch liner Repair M2/Co10 days Tue 15/12/20 7:30 AThu 24/12/20 6:00 PM 15/12 24/12
363 84% Condenser Sea Waterbox Side 24 days Mon 23/11/20 7:30 Wed 16/12/20 6:00 P
366 80% 20/108712 Manhole Waterbox A repair + Rubber lining and  M2/Co11 days Sun 06/12/20 7:30  Wed 16/12/20 6:00  06/12 16/12
coating inspection & repair AM PM
367 85% 20/108715 Condenser water box Line B Insp & Tubes Cleaning M2/Co10 days Fri 04/12/20 7:30 AM
Sun 13/12/20 6:00 PM 04/12 13/12
368 80% 20/108715 Manhole Waterbox B repair + Rubber lining and  M2/Co10 days Sun 06/12/20 7:30  Tue 15/12/20 6:00  06/12 15/12
coating inspection & repair AM PM
369 0% Close Condenser water box Line A & B manhole M2 1 day Wed 16/12/20 7:30 Wed 16/12/20 6:00 P 16/12 16/12
370 89% Condenser inlet header 12 days Mon 14/12/20 7:30 Fri 25/12/20 6:00 PM
372 80% Inspect Inlet Header & liner repair M2/Co12 days Mon 14/12/20 7:30 Fri 25/12/20 6:00 PM 14/12 25/12
373 86% Condenser Outlet Header 36 days Tue 24/11/20 7:30 ATue 29/12/20 6:00 P
376 85% 20/108862 CW Line Outlet Header Liner Inspection & Repair M2/Co25 days Fri 04/12/20 7:30 AM
Mon 28/12/20 6:00 P 04/12 28/12
377 0% Repair Ball Catchers, broken screen & function test M2/Co5 days Sun 20/12/20 7:30 AThu 24/12/20 6:00 PM
379 0% Remove Stop Log from seawater outfall M2/Co1 day Tue 29/12/20 7:30 ATue 29/12/20 6:00 PM 29/12 29/12
385 84% TURBINE ‐ GENERATOR 69 days Sun 22/11/20 12:55Fri 29/01/21 7:59 PM
387 67% Turbine System 69 days Sun 22/11/20 7:30 AFri 29/01/21 7:59 PM
388 66% Turbine Overhaul 69 days Sun 22/11/20 7:30 AFri 29/01/21 7:59 PM
396 72% B. Low Pressure Turbine (LP) 36.55 days Thu 26/11/20 7:30 AFri 01/01/21 1:44 PM
408 44% 3. Assembly Work 20.55 days Fri 11/12/20 6:00 PM
Fri 01/01/21 1:44 PM
411 40% LP Rotor Installation include Extenssion for  M2/TA14 days Mon 14/12/20 7:30 Sun 27/12/20 6:00  14/12 27/12
REPLACE BEARING #3 #4 AM PM
412 30% Installation LP A & B Nozzle Diaphragm Upper  M2/TA9 days Sun 20/12/20 7:30  Tue 29/12/20 1:44  20/12 29/12
Half & Packing CSG AM PM
413 0% Installation LP A&B Inner Upper Casing M2/TA2 days Tue 29/12/20 1:44 PThu 31/12/20 1:44 PM 29/12 31/12
414 0% Installation LP A & B Upper Half Bearing and  M2/TA2 days Fri 18/12/20 7:30  Sat 19/12/20 6:00  18/12 19/12
Pedestal AM PM
415 0% Assembly LP A & B Outer Upper Half Casing M2/TA1 day Thu 31/12/20 1:44  Fri 01/01/21 1:44  31/12 01/01
PM PM
416 50% C. High Intermediate Pressure Turbine (HIP) 58.05 days Sun 29/11/20 7:30 ATue 26/01/21 7:59 A
425 31% 2. Assembly Work 45.55 days Fri 11/12/20 1:15 PM
Tue 26/01/21 7:59 A
428 60% HIP Rotor Installation M2/TA7.05 days Sat 19/12/20 7:30 ASat 26/12/20 7:59 AM 19/12 26/12
429 0% Installation HIP Nozzle Diaphragm Upper Half  M2/TA27 days Sat 26/12/20 7:59  Fri 22/01/21 7:59  26/12 22/01
& Packing, Extend for IP Stage Nozzle  AM AM
Diaphragm Dishing Refurbishment 
430 0% Installation HIP Inner Upper Casing M2/TA1.5 days Fri 22/01/21 7:59 AM
Sat 23/01/21 1:44 PM 22/01 23/01
431 0% Installation HIP Upper Half Bearing and  M2/TA12 hrs Fri 22/01/21 7:59  Sat 23/01/21 10:29  22/01 23/01
Pedestal AM AM

Page 3
ID Task % Complete Work Order Task Name Support PIC Duration Start Finish 0 December 2020 January 2021 Feb
Mode 17 22 27 02 07 12 17 22 27 01 06 11 16 21 26 31
432 0% Assembly HIP Outer Upper Half Casing M2/TA1.5 days Sun 24/01/21 1:44 PTue 26/01/21 7:59 AM 24/01 26/01
433 88% D. Generator Bearing Inspection 5.5 days Mon 14/12/20 7:30 Sat 19/12/20 1:15 PM
440 0% Ressasembly Bearing #9 M2/TA1 day Fri 18/12/20 1:15 PMSat 19/12/20 1:15 PM 18/12 19/12
442 0% F. Restoration Work 28.5 days Thu 31/12/20 1:44 PFri 29/01/21 7:59 AM
443 0% Assembly of Flange Main Steam Pipe M2/TA0.5 days Tue 26/01/21 7:59 ATue 26/01/21 1:44 PM 26/01 26/01
444 0% Assembly of Cross Over Pipe M2/TA1 day Tue 26/01/21 7:59 AWed 27/01/21 7:59 A 26/01 27/01
445 0% Turning Equipment M2/TA1 day Thu 31/12/20 1:44 PFri 01/01/21 1:44 PM 31/12 01/01
447 0% G. Commissioning 28.01 days Fri 01/01/21 5:57 PMFri 29/01/21 7:59 PM
448 0% PTW Close for Mechanical Work M2/TA0 days Wed 27/01/21 7:59 Wed 27/01/21 7:59 A 27/0
449 0% Lube Oil Flushing M2/TA2 days Wed 27/01/21 7:59 Fri 29/01/21 7:59 AM 27/01 29/0
450 0% Turning M2/TA12 hrs Fri 29/01/21 7:59 AMFri 29/01/21 7:59 PM 29/01 29/
451 0% Valve Stroke Check M2/TA4 days Fri 01/01/21 5:57 PMTue 05/01/21 5:57 PM 01/01 05/01
469 93% Turbine LO System 32 days Wed 25/11/20 7:30 Sat 26/12/20 6:00 PM
470 90% LO System Inspection during Turbine Overhaul ‐  M2/Co30 days Fri 27/11/20 7:30  Sat 26/12/20 6:00  27/11 26/12
included to Turbine Overhaul scope AM PM
473 70% Check LOP coupling M2 4 days Wed 16/12/20 7:30 Fri 25/12/20 4:06 PM 16/12 25/12
477 94% EHC System 22 days Fri 27/11/20 7:30 A Fri 18/12/20 6:00 PM
480 0% EHC Oil Tank cleaning M2 1 day Mon 30/11/20 7:30 Mon 30/11/20 6:00 P
507 0% Compressor 21 days Wed 25/11/20 7:30 Tue 15/12/20 6:00 PM
508 0% Service Air Compressor B Overhaul removed M2/Co14 days Wed 25/11/20 7:30 Tue 08/12/20 6:00 PM
510 62% ELECTRICAL WORKS 38 days Sun 22/11/20 7:30 ATue 29/12/20 6:00 P
576 10% 125 & 250 VDC Power Supply system 30 days Wed 25/11/20 7:30 Thu 24/12/20 6:00 P
578 10% Replace batteries 125 & 250 VDC Include rack battery E/Prim30 days Wed 25/11/20 7:30 Thu 24/12/20 6:00 PM 5/11 24/12
769 0% START UP (INCLUDE OVERSPEED TEST) 2 days Fri 29/01/21 8:59 PMSun 31/01/21 11:59 P
775 0% 1st Vibration Check + Cooling Down O/M2/2 hrs Sat 30/01/21 4:59 P Sat 30/01/21 6:59 PM 30/01 30/
776 0% 1st Trim Balancing M2/TA5 hrs Sat 30/01/21 6:59 P Sat 30/01/21 11:59 P 30/01 30/
777 0% 2nd Start up + Vibration Check O/M2/5 hrs Sat 30/01/21 11:59  Sun 31/01/21 4:59 AM 30/01 31/
778 0% 2nd Cooling Down + Trim Balancing O/M2/19 hrs Sun 31/01/21 4:59 ASun 31/01/21 11:59 P 31/01 31

Page 4
Task Inactive Task Manual Summary Rollup External Milestone Baseline Milestone

Split Inactive Milestone Manual Summary Deadline Baseline Summary


Project: U1 SE (20 November -
Milestone Inactive Summary Start-only Critical Progress
Date: Fri 25/12/20 1:41 PM
Summary Manual Task Finish-only Critical Split Manual Progress

Project Summary Duration-only External Tasks Baseline

Page 5