Insert Company Name -Insert start date *Note: Insert number of Man Power to the Gantt Bar for get values of Planned Weekly Accomplishement and Planned Cumulative Accomplishme
-Insert Number of Days
Project Start Date 10/12/2020 (Monday) Display Week 3 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10
Project Lead 26 Oct 2020 2 Nov 2020 9 Nov 2020 16 Nov 2020 23 Nov 2020 30 Nov 2020 7 Dec 2020 14 Dec 2020
26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
PRED
%
WBS TASK ECES START END DAYS M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
SOR DONE
1 MATT FOOTING -
0.1 Rebar Fabrication & Hauling Mon 10/12/20 Fri 10/30/20 19 100% 6 6 6 6 6
0.1 Compaction Mon 11/02/20 Mon 11/09/20 8 100% 8 8 8 8 8 8 8 8
0.1 FDT Tue 11/10/20 Tue 11/10/20 1 100%
0.1 Layout of Matt Footing Sun 11/29/20 Mon 11/30/20 2 10%
0.1 Rebar Installation Tue 12/01/20 Thu 12/10/20 10 0% 12 12 12 12 12 12 12 12 12 12
0.1 Formworks Fri 12/11/20 Sat 12/19/20 9 0% 14 14 14 14 14 14 14 14 14
0.1 Concrete Pouring Sun 12/20/20 Mon 12/21/20 1 0% 14
0.1 Curing Mon 12/21/20 Mon 12/21/20 1 0%
0.1 Stripping Mon 12/21/20 Tue 12/22/20 2 0%
1 ISOLATED FOOTING -
0.1 Rebar Fabrication & Hauling Mon 11/23/20 Sun 12/06/20 14 30% 6 6 6 6 6 6 6 5 5 5 5 5 5 5
0.1 Compaction Fri 11/20/20 Wed 12/02/20 12 50% 2 2 2 2 2 2 2 2 2 2 2 2
0.1 FDT Wed 12/02/20 Wed 12/02/20 1 0%
1 PLINTHS / PEDESTAL -
0.1 Fabrication of Rebar Mon 11/23/20 Wed 12/02/20 10 30% 0 0 0 0 0 0 0 0 0 0
0.1 MS Plate & Anchor Bolt Fabrication Mon 11/23/20 Wed 12/02/20 10 0% 4 4 4 4 4 4 4 4 4 4