Activity ID Activity Name Original Schedule Start Finish Total 2021 2022 2023 2024

Duration % Float M M
A J J A S ON D J FMAMJ J A SO N D J FMAMJ J A SO N D J F
Complete
MAIN PASSANGER TERMINAL BUILDING(MPTB) 617 0% 05-Mar-21 17-Jul-23 101
SUB-STRUCTURE WORKS 78 0% 08-Nov-21 21-Mar-22 13
SUPER-STRUCTURE WORKS 201 0% 12-Jan-22 27-Dec-22 204
PLUMBING & DRAINAGE WORKS 617 0% 05-Mar-21 17-Jul-23 101
PIER 2 479 0% 05-Mar-21 12-Jun-23 13
SUB-STRUCTURE WORKS 34 0% 29-Mar-22 31-May-22 0
SUPER-STRUCTURE WORKS 48 0% 04-May-22 22-Jul-22 174
PLUMBING & DRAINAGE WORKS 479 0% 05-Mar-21 12-Jun-23 13
GROUND FLOOR 396 0% 05-Mar-21 17-Jan-23 97
SECTION 2.11 396 0% 05-Mar-21 17-Jan-23 97
SECTION 2.12 377 0% 05-Mar-21 16-Dec-22 115
SECTION 2.13 374 0% 05-Mar-21 12-Dec-22 118
SECTION 2.14 385 0% 05-Mar-21 29-Dec-22 107
FIRST FLOOR 197 0% 03-Jun-22 08-May-23 35
SECTION 2.11 143 0% 03-Jun-22 30-Jan-23 88
SECTION 2.12 127 0% 09-Jun-22 10-Jan-23 101
SECTION 2.13 148 0% 27-Jun-22 02-Mar-23 69
SECTION 2.14 171 0% 18-Jul-22 08-May-23 35
SECOND FLOOR 215 0% 09-Jun-22 12-Jun-23 13
SECTION 2.11 166 0% 09-Jun-22 15-Mar-23 62
SECTION 2.12 182 0% 09-Jun-22 15-Apr-23 46
SECTION 2.13 190 0% 27-Jun-22 17-May-23 28
SECTION 2.14 193 0% 18-Jul-22 12-Jun-23 13
PIER 3 481 0% 05-Mar-21 14-Jun-23 105
CAR PARK 464 0% 05-Mar-21 17-May-23 122
PUMP HOUSE 5 0% 05-Mar-21 11-Mar-21 0
NEW POWER STATION 5 0% 05-Mar-21 11-Mar-21 0
TESTING & COMMISSIONING 60 0% 05-Jul-23 12-Oct-23 0

PRE TESTING & COMMISSIONING 30 0% 05-Jul-23 23-Aug-23 0


FINAL TESTING & COMMISSIONING 30 0% 23-Aug-23 12-Oct-23 0
PROJECT CLOSEOUT 34 0% 12-Oct-23 06-Dec-23 0

A1440 Snagging & Clearance 30 0% 12-Oct-23 29-Nov-23 0


A1450 Handover of Documents(O&M Manuals, Warranties) 4 0% 12-Oct-23 18-Oct-23 30
A1430 As-Built Drawing Submissions & Appr ovals 4 0% 29-Nov-23 06-Dec-23 0