PROJECT : Relief Project

MASTER SCHEDULE (REV0.01) Dated 11Jul22


ID Task Name Duration Start Finish Planned
%
% Complete
Complete June 2022 July 2022 August 2022 September 2022 October 2022 November 2022 December 2022 January 2023 February 2023 March 2023 April 2023 May 2023
30 01 03 05 07 0911 13 15 17 19 21 23 25 27 29 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 02 040608 10 12 14 16 18 20 22 24 2628 30 01 03 05 07 0911 13 15 17 19 21 23 25 27 29 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 02 040608 10 12 14 16 18 20 22 24 2628 30 0204060810 12 141618 20 22 242628 30 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 02 04060810 12 14 16 18 20 22 24 2628 02 040608 10 12 14 16 18 20 22 24 26 28 30 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 0
1 RELIEF PROJECT: PROPOSED MASTER SCHEDULE 347 d 31-05-22 01-06-23 12.1037463976945%
10% 11 Jul, '22

2 Project Keydate 347 d 31-05-22 01-06-23 100% 0%

3 General 347 d 31-05-22 01-06-23 100% 0%


5 LOA, Award for MEP Package 0d 15-07-22 15-07-22 0% 0% LOA, Award for MEP Package 15 Jul '22

36 Mobilization & Temporary Work 70 d 31-05-22 11-08-22 60% 78% 11 Aug '22

44 Temporary Facilities 70 d 31-05-22 11-08-22 60% 77% 11 Aug '22

56 Temporary Gate (2 Gates) 26 d 04-07-22 01-08-22 30.7692307692308%


37% Temporary Gate (2 Gates) 01 Aug '22

57 Temporary Gate No.1 (use existing gate) - Additional Wheel cleaning at gate
161d 04-07-22 Temporary
20-07-22 Gate
50%No.160%
(use existing gate) - Additional Wheel cleaning at gate 1 20 Jul '22

58 Temporary Gate No.2 22 d 08-07-22 01-08-22 18.1818181818182%


21% Temporary Gate No.2 01 Aug '22

59 Temporary Gate No.2 - Leveling & concerete connnect to WHA road 10 d 08-07-22 18-07-22 Temporary
40% 50% Gate No.2 - Leveling & concerete connnect to WHA road 18 Jul '22

60 Temporary Gate No.2 - Foundation & temporary gate installation 8d 19-07-22 26-07-22 0% 0% Temporary Gate No.2 - Foundation & temporary gate installation 26 Jul '22

61 Temporary Gate No.2 - Wheel cleaning at gate 2 6d 25-07-22 01-08-22 0% 0% Temporary Gate No.2 - Wheel cleaning at gate 2 01 Aug '22

63 Temporary worker toilet (45 rooms) 47 d 06-06-22 Temporary76.5957446808511%


23-07-22 worker 95%
toilet (45 rooms) 23 Jul '22

66 TKC Office & Toilets (30 rooms) - Temporary fence (blind wall) 14 d 01-07-22 15-07-22 TKC Office & Toilets (30 rooms) - Temporary fence (blind wall)
78.5714285714286%
80% 15 Jul '22

69 TKC Office & Toilets (15 rooms) - Temporary fence (blind wall) 8d 16-07-22 23-07-22 0% 80% TKC Office & Toilets (15 rooms) - Temporary fence (blind wall) 23 Jul '22

70 Temporary moring talk & carpark area 42 d 10-06-22 Temporary


22-07-22 moring talk & carpark area
76.1904761904762%
93% 22 Jul '22

73 Temporary carpark 2 with walkway 14 d 08-07-22 22-07-22 28.5714285714286%


70% Temporary carpark 2 with walkway 22 Jul '22

77 Temporary formwork,scaffolding yard 44 d 14-06-22 30-07-22Temporary formwork,scaffolding yard


63.6363636363636%
61% 30 Jul '22

79 Temporary formwork,scaffolding yard - Temporary fence 18 d 10-07-22 30-07-22 50% Temporary formwork,scaffolding yard - Temporary fence
11.1111111111111% 30 Jul '22

80 Temporary Road (Blue Color) 37 d 08-06-22 15-07-22 Temporary Road (Blue Color)
91.8918918918919%
97% 15 Jul '22

84 Temporary Road - Rain drainage gutter 22 d 23-06-22 15-07-22 Temporary Road - Rain drainage gutter
86.3636363636364%
90% 15 Jul '22

85 Temporary Internal Road (Orange Color) 49 d 10-06-22 Temporary65.3061224489796%


31-07-22 Internal
69%Road (Orange Color) 31 Jul '22

87 Temporary Road - Pile head cut 30 d 15-06-22 15-07-22 90% Temporary


95% Road - Pile head cut 15 Jul '22

88 Temporary Road - Soil adjustment level 30 d 20-06-22 20-07-22 Temporary Road - Soil adjustment level
73.3333333333333%
75% 20 Jul '22

89 Temporary Road - Soil cement & compaction 31 d 24-06-22 25-07-22 Temporary Road - Soil cement & compaction
58.0645161290323%
60% 25 Jul '22

90 Temporary Road - Rain drainage gutter 26 d 03-07-22 31-07-22 34.6153846153846%


40% Temporary Road - Rain drainage gutter 31 Jul '22

91 Labour Camp 70 d 31-05-22 11-08-22 60% 47% 11 Aug '22

92 Labour Camp - Construction 60 d 31-05-22 Labour Camp


01-08-22 70%- Construction
75% 01 Aug '22

93 Labour Camp - Temporary power supply 40 d 30-06-22 11-08-22 30% 35% Labour Camp - Temporary power supply 11 Aug '22

94 Lobour Camp - Temporary water supply 25 d 16-07-22 11-08-22 0% 0% Lobour Camp - Temporary water supply 11 Aug '22

95 M&E Temporary Work 45 d 16-06-22 68% M&E Temporary Work


02-08-22 57.7777777777778% 02 Aug '22

96 M&E Temporary Work - Power Supply 41 d 20-06-22 M&E


53%Temporary Work - Power Supply
02-08-22 53.6585365853659% 02 Aug '22

97 M&E Temporary Work - Power Supply - PEA work 19 d 20-06-22 M&E 100%
08-07-22 Temporary
87%Work - Power Supply - PEA work 08 Jul '22

102 Temp.Power Supply - Connection 22KV Cable by PEA 3d 04-07-22 06-07-22 Temp.Power Supply - Connection 22KV Cable by PEA
100% 60% 06 Jul '22

103 Temp. Power Supply - Electric Power on 2d 07-07-22 08-07-22 100% 0% Temp. Power Supply - Electric Power on 08 Jul '22

104 M&E Temporary Work - Outdoor lighting for construciton site area 20 d 11-07-22 02-08-22 5% M&E Temporary Work - Outdoor lighting for construciton site area
40% 02 Aug '22

105 M&E Temporary Work - Power supply to Office 5d 18-07-22 22-07-22 0% 0% M&E Temporary Work - Power supply to Office 22 Jul '22

106 M&E Temporary Work - Power supply to fabrication yard 4d 10-07-22 14-07-22 50% 20% M&E Temporary Work - Power supply to fabrication yard 14 Jul '22

107 M&E Temporary Work - Power supply to canteen/toilet 4d 14-07-22 17-07-22 0% 10% M&E Temporary Work - Power supply to canteen/toilet 17 Jul '22

108 M&E Temporary Work - CCTV & Install wiring 9d 05-07-22 14-07-22 M&E Temporary Work - CCTV & Install wiring
77.7777777777778%
23% 14 Jul '22

109 M&E Temporary Work - CCTV & Install wiring - Power Supply to camera 6d 05-07-22 M&E 100%
10-07-22 Temporary
35%Work - CCTV & Install wiring - Power Supply to camera 10 Jul '22

110 M&E Temporary Work - CCTV & Install wiring - Testing signal 3d 11-07-22 14-07-22 0% M&E Temporary Work - CCTV & Install wiring - Testing signal
33.3333333333333% 14 Jul '22

115 Project Execution 338 d 08-06-22 01-06-23 6%Project Execution


9.76331360946746%

189 Submission&Approval - Shop Drawing Submission&Approval


210 d 09-06-22 15-01-23 19%- Shop Drawing
15.7142857142857% 15 Jan '23

190 Submission&Approval - Shop Drawing - Structural work Submission&Approval


115 d 09-06-22 05-10-22 - Shop Drawing
35%- Structural work
28.695652173913% 05 Oct '22

191 Submission&Approval - Shop Drawing Str. - Main Factory Submission&Approval


100 d 09-06-22 20-09-22- Shop33%
Drawing
41%Str. - Main Factory 20 Sep '22

192 Submission&Approval - Shop Drawing Str. - Zone A 100 d Submission&Approval


09-06-22 20-09-22 33%- Shop Drawing
40% Str. - Zone A 20 Sep '22

201 Submission&Approval - Shop Drawing Str. - Zone A - Pca. Column 15 d 01-07-22 Submission&Approval
16-07-22 83% - Shop Drawing Str. - Zone A - Pca. Column
73.3333333333333% 16 Jul '22

203 Zone A1 - Pca. Column - 1st Review & Approval by Consultant 2d 09-07-22 10-07-22 Zone A1 - Pca. Column - 1st Review & Approval by Consultant
100% 75% 10 Jul '22

205 Zone A2 - Pca. Column - 1st Review & Approval by Consultant 2d 11-07-22 12-07-22 50% 75% Zone A2 - Pca. Column - 1st Review & Approval by Consultant 12 Jul '22

206 Zone A3 - Pca. Column - 1st Preparation & Submission 7d 07-07-22 14-07-22 75% Zone A3 - Pca. Column - 1st Preparation & Submission
71.4285714285714% 14 Jul '22

207 Zone A3 - Pca. Column - 1st Review & Approval by Consultant 2d 15-07-22 16-07-22 0% 0% Zone A3 - Pca. Column - 1st Review & Approval by Consultant 16 Jul '22

208 Submission&Approval - Shop Drawing Str. - Zone A - Core Wall Details


10 d 04-07-22 Submission&Approval
14-07-22 80% 72% - Shop Drawing Str. - Zone A - Core Wall Details 14 Jul '22

209 Zone A - Core Wall Details - 1st Preparation & Submission 8d 04-07-22 11-07-22 100% Zone
90% A - Core Wall Details - 1st Preparation & Submission 11 Jul '22

210 Zone A - Core Wall Details-1st Review & Approval by Consultant 2d 12-07-22 14-07-22 0% 0% Zone A - Core Wall Details-1st Review & Approval by Consultant 14 Jul '22

211 Submission&Approval - Shop Drawing Str. - Zone A - Roof Steel Structure


14 d 08-07-22 22-07-22Submission&Approval
28.5714285714286%
36% - Shop Drawing Str. - Zone A - Roof Steel Structure 22 Jul '22

212 Zone A - Roof - 1st Preparation & Submission 10 d 08-07-22 18-07-22 40% 50% Zone A - Roof - 1st Preparation & Submission 18 Jul '22

213 Zone A - Roof - 1st Review & Approval by Consultant 4d 19-07-22 22-07-22 0% 0% Zone A - Roof - 1st Review & Approval by Consultant 22 Jul '22

214 Submission&Approval - Shop Drawing Str. - Zone A - Under ground pipe


24 d 30-07-22 23-08-22 0% 0% Submission&Approval - Shop Drawing Str. - Zone A - Under ground pipe 23 Aug '22

215 Zone A - Under ground pipe - 1st Preparation & Submission 6d 30-07-22 04-08-22 0% 0% Zone A - Under ground pipe - 1st Preparation & Submission 04 Aug '22

229 Submission&Approval - Shop Drawing Str. - Zone B 94 d Submission&Approval


09-06-22 - Shop Drawing
41% Str. - Zone B
14-09-22 35.1063829787234% 14 Sep '22

233 Submission&Approval - Shop Drawing Str. - Zone B - FoundationSubmission&Approval


& Ground
23 d beam
16-06-22- Shop08-07-22
Drawing Str.100%
- Zone B - Foundation & Ground beam
97% 08 Jul '22

237 Zone B - Gr. Beam - Review & Approval by Consultant 3d 06-07-22 08-07-22 100% 75% Zone B - Gr. Beam - Review & Approval by Consultant 08 Jul '22

238 Submission&Approval - Shop Drawing Str. - Zone B - Pca. Column 18 d 01-07-22 Submission&Approval
19-07-22 - Shop Drawing Str. - Zone B - Pca. Column
61.1111111111111%
72% 19 Jul '22

240 Zone B1 - Pca. Column - 1st Review & Approval by Consultant 2d 09-07-22 10-07-22 Zone B1 - Pca. Column - 1st Review & Approval by Consultant
100% 75% 10 Jul '22

242 Zone B2 - Pca. Column - 1st Review & Approval by Consultant 2d 11-07-22 12-07-22 50% 75% Zone B2 - Pca. Column - 1st Review & Approval by Consultant 12 Jul '22

243 Zone B3 - Pca. Column - 1st Preparation & Submission 7d 07-07-22 14-07-22 75% Zone B3 - Pca. Column - 1st Preparation & Submission
71.4285714285714% 14 Jul '22

244 Zone B3 - Pca. Column - 1st Review & Approval by Consultant 2d 15-07-22 16-07-22 0% 0% Zone B3 - Pca. Column - 1st Review & Approval by Consultant 16 Jul '22

245 Zone B4 - Pca. Column - 1st Preparation & Submission 7d 10-07-22 17-07-22 Zone B4 - Pca. Column - 1st Preparation & Submission
28.5714285714286%
50% 17 Jul '22

246 Zone B4 - Pca. Column - 1st Review & Approval by Consultant 2d 18-07-22 19-07-22 0% 0% Zone B4 - Pca. Column - 1st Review & Approval by Consultant 19 Jul '22

247 Submission&Approval - Shop Drawing Str. - Zone B - Core Wall Details


10 d 04-07-22 Submission&Approval
14-07-22 80% 60% - Shop Drawing Str. - Zone B - Core Wall Details 14 Jul '22

248 Zone B - Core Wall Details - 1st Preparation & Submission 8d 04-07-22 11-07-22 100% Zone
75% B - Core Wall Details - 1st Preparation & Submission 11 Jul '22

249 Zone B - Core Wall Details - 1st Review & Approval by Consultant 2d 12-07-22 14-07-22 0% 0%Zone B - Core Wall Details - 1st Review & Approval by Consultant 14 Jul '22

250 Submission&Approval - Shop Drawing Str. - Zone B - Roof Steel Structure


14 d 01-07-22 Submission&Approval - Shop Drawing Str. - Zone B - Roof Steel Structure
15-07-22 78.5714285714286%
64% 15 Jul '22

251 Zone B - Roof - 1st Preparation & Submission 10 d 01-07-22 10-07-22 100% 90% Zone B - Roof - 1st Preparation & Submission 10 Jul '22

252 Zone B - Roof - 1st Review & Approval by Consultant 4d 11-07-22 15-07-22 25% 0% Zone B - Roof - 1st Review & Approval by Consultant 15 Jul '22

253 Submission&Approval - Shop Drawing Str. - Zone B - Under ground pipe


28 d 24-07-22 23-08-22 0% 0% Submission&Approval - Shop Drawing Str. - Zone B - Under ground pipe 23 Aug '22

254 Zone B - Under ground pipe - 1st Preparation & Submission 7d 24-07-22 01-08-22 0% 0% Zone B - Under ground pipe - 1st Preparation & Submission 01 Aug '22

268 115Submission&Approval
Submission&Approval - Shop Drawing Str. - Office and Canteen - Shop Drawing
d 09-06-22 05-10-22 Str.22%
- Office and Canteen
28.695652173913% 05 Oct '22

272 Submission&Approval
Submission&Approval - Shop Drawing Str. - Office and Canteen 23 d - &
- Foundation Shop Drawing
Ground
16-06-22 Str.08-07-22
beam - Office and100%
Canteen - Foundation & Ground beam
97% 08 Jul '22

276 Office and Canteen - Gr. Beam - Review & Approval by Consultant 3d 06-07-22 08-07-22 Office75%
100% and Canteen - Gr. Beam - Review & Approval by Consultant 08 Jul '22

1 OF 4
PROJECT : Relief Project
MASTER SCHEDULE (REV0.01) Dated 11Jul22
ID Task Name Duration Start Finish Planned
%
% Complete
Complete June 2022 July 2022 August 2022 September 2022 October 2022 November 2022 December 2022 January 2023 February 2023 March 2023 April 2023 May 2023
30 01 03 05 07 0911 13 15 17 19 21 23 25 27 29 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 02 040608 10 12 14 16 18 20 22 24 26 28 30 01 03 05 07 0911 13 15 17 19 21 23 25 27 29 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 02 040608 10 12 14 16 18 20 22 24 26 28 30 0204060810 12 14 16 18 20 22 242628 30 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 02 04060810 12 14 16 18 20 22 24 26 28 02 04060810 12 141618 20 22 24 26 28 30 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 0
277 10 d 01-07-22Submission&Approval
Submission&Approval - Shop Drawing Str. - Office and Canteen - Pca. Column 10-07-22 100% - Shop
72%Drawing Str. - Office and Canteen - Pca. Column 11 Jul,10 Jul '22
'22

278 Office and Canteen - Pca. Column - 1st Preparation & Submission 8d 01-07-22 Office
08-07-22 and Canteen
100% 90% - Pca. Column - 1st Preparation & Submission 08 Jul '22

279 Office and Canteen - Pca. Column - 1st Review & Approval by Consultant 2 d 09-07-22 10-07-22 Office
100%and0%Canteen - Pca. Column - 1st Review & Approval by Consultant 10 Jul '22

280 Submission&Approval - Shop Drawing Str. - Office and Canteen - Core Wall
5 dDetails
10-07-22 Submission&Approval
15-07-22 40% 42%- Shop Drawing Str. - Office and Canteen - Core Wall Details 15 Jul '22

281 Office and Canteen - Core Wall Details - 1st Preparation & Submission 3d 10-07-22 12-07-22 Office and Canteen - Core Wall Details - 1st Preparation & Submission
66.6666666666667%
70% 12 Jul '22

282 Office and Canteen - Core Wall Details - 1st Review & Approval by Consultant
2d 14-07-22 15-07-22 Office0%
0% and Canteen - Core Wall Details - 1st Review & Approval by Consultant 15 Jul '22

283 Submission&Approval - Shop Drawing Str. - Office and Canteen - Under ground
21 d 07-07-22
pipe Submission&Approval -25%
Shop Drawing Str. - Office and Canteen - Under ground pipe
30-07-22 23.8095238095238% 30 Jul '22

284 Office and Canteen - Under ground pipe - 1st Preparation & Submission 7 d 07-07-22 14-07-22 Office and75%
Canteen - Under ground pipe - 1st Preparation & Submission
71.4285714285714% 14 Jul '22

285 Office and Canteen - Under ground pipe - 1st Review & Approval by Consultant
7d 15-07-22 21-07-22 Office0%
0% and Canteen - Under ground pipe - 1st Review & Approval by Consultant 21 Jul '22

286 Office and Canteen - Under ground pipe - 2nd Preparation & Submission 4 d 22-07-22 25-07-22 0% 0% Office and Canteen - Under ground pipe - 2nd Preparation & Submission 25 Jul '22

287 Office and Canteen - Under ground pipe - 2nd Review & Approval by Consultant
3d 26-07-22 30-07-22 0% 0% Office and Canteen - Under ground pipe - 2nd Review & Approval by Consultant 30 Jul '22

288 Submission&Approval - Shop Drawing Str. - Office and Canteen - Level 114
PTdSlab22-07-22 06-08-22 0% Submission&Approval - Shop Drawing Str. - Office and Canteen - Level 1 PT Slab
0% 06 Aug '22

289 Office and Canteen - Level 1 - 1st Preparation & Submission 7d 22-07-22 30-07-22 0% 0% Office and Canteen - Level 1 - 1st Preparation & Submission 30 Jul '22

290 Office and Canteen - Level 1 - 1st Review & Approval by Consultant 7d 31-07-22 06-08-22 0% 0% Office and Canteen - Level 1 - 1st Review & Approval by Consultant 06 Aug '22

291 Submission&Approval - Shop Drawing Str. - Office and Canteen - Level M28PT
d Slab
21-07-22 20-08-22 0% Submission&Approval
0% - Shop Drawing Str. - Office and Canteen - Level M PT Slab 20 Aug '22

292 Office and Canteen - Level M - 1st Preparation & Submission 7d 21-07-22 27-07-22 0% 0% Office and Canteen - Level M - 1st Preparation & Submission 27 Jul '22

293 Office and Canteen - Level M - 1st Review & Approval by Consultant 7d 30-07-22 05-08-22 0% 0% Office and Canteen - Level M - 1st Review & Approval by Consultant 05 Aug '22

311 68Submission&Approval
Submission&Approval - Shop Drawing Str. - East Utility Building - Shop Drawing
d 09-06-22 19-08-22 Str. 40%
- East Utility Building
48.5294117647059% 19 Aug '22

315 Submission&Approval
Submission&Approval - Shop Drawing Str. - East Utility Building 23 d- Shop
- Foundation Drawingbeam
&16-06-22
Ground Str.08-07-22
- East Utility100%
Building - Foundation & Ground beam
87% 08 Jul '22

319 East Utility Building - Gr. Beam - Review & Approval by Consultant 3d 06-07-22 08-07-22 East Utility
100% 0% Building - Gr. Beam - Review & Approval by Consultant 08 Jul '22

320 10 d 01-07-22Submission&Approval
Submission&Approval - Shop Drawing Str. - East Utility Building - Pca. Column 10-07-22 100% - Shop
72%Drawing Str. - East Utility Building - Pca. Column 10 Jul '22

321 East Utility Building - Pca. Column - 1st Preparation & Submission 8d 01-07-22 East Utility
08-07-22 100% Building
90% - Pca. Column - 1st Preparation & Submission 08 Jul '22

322 East Utility Building - Pca. Column - 1st Review & Approval by Consultant2 d 09-07-22 10-07-22 East
100%Utility
0%Building - Pca. Column - 1st Review & Approval by Consultant 10 Jul '22

323 Submission&Approval - Shop Drawing Str. - East Utility Building - Level 121PT
d Slab
14-07-22 05-08-22Submission&Approval
0% 0% - Shop Drawing Str. - East Utility Building - Level 1 PT Slab 05 Aug '22

324 East Utility Building - Level 1 - 1st Preparation & Submission 7d 14-07-22 20-07-22 0% 0% East Utility Building - Level 1 - 1st Preparation & Submission 20 Jul '22

325 East Utility Building - Level 1 - 1st Review & Approval by Consultant 7d 21-07-22 27-07-22 0% 0% East Utility Building - Level 1 - 1st Review & Approval by Consultant 27 Jul '22

326 East Utility Building - Level 1 - 2nd Preparation & Submission 4d 30-07-22 02-08-22 0% 0% East Utility Building - Level 1 - 2nd Preparation & Submission 02 Aug '22

328 Submission&Approval - Shop Drawing Str. - East Utility Building- Roof PT


28Slab
d 20-07-22 19-08-22 0% Submission&Approval - Shop Drawing Str. - East Utility Building- Roof PT Slab
0% 19 Aug '22

329 East Utility Building - Roof - 1st Preparation & Submission 7d 20-07-22 26-07-22 0% 0% East Utility Building - Roof - 1st Preparation & Submission 26 Jul '22

330 East Utility Building - Roof - 1st Review & Approval by Consultant 7d 27-07-22 04-08-22 0% 0% East Utility Building - Roof - 1st Review & Approval by Consultant 04 Aug '22

333 Submission&Approval
Submission&Approval - Shop Drawing Str. - South Utility Building
101 - Shop Drawing
d 09-06-22 21-09-22 Str. - South
37% Utility Building
32.6732673267327% 21 Sep '22

342 Submission&Approval - Shop Drawing Str. - South Utility Building - Water Submission&Approval
21 Tank
d 21-06-22 - Shop Drawing
11-07-22 100%Str.96%
- South Utility Building - Water Tank 11 Jul '22

344 South Utility Building - Water Tank - 1st Review & Approval by Consultant3 d 09-07-22 11-07-22 South
100% Utility
75%Building - Water Tank - 1st Review & Approval by Consultant 11 Jul '22

345 Submission&Approval - Shop Drawing Str. - South Utility Building - Pca.10


Column Submission&Approval
d 01-07-22 10-07-22 100% - Shop Drawing Str. - South Utility Building - Pca. Column
72% 10 Jul '22

346 South Utility Building - Pca. Column - 1st Preparation & Submission 8d 01-07-22 South Utility
08-07-22 100% Building
90% - Pca. Column - 1st Preparation & Submission 08 Jul '22

347 South Utility Building - Pca. Column - 1st Review & Approval by Consultant
2d 09-07-22 10-07-22 South
100%Utility
0%Building - Pca. Column - 1st Review & Approval by Consultant 10 Jul '22

348 Submission&Approval - Shop Drawing Str. - South Utility Building - Roof14


Steel Submission&Approval
d Structure
01-07-22 15-07-22- Shop Drawing Str. - South Utility Building - Roof Steel Structure
78.5714285714286%
64% 15 Jul '22

349 South Utility Building - Roof - 1st Preparation & Submission 10 d 01-07-22 10-07-22 South Utility
100% 90% Building - Roof - 1st Preparation & Submission 10 Jul '22

350 South Utility Building - Roof - 1st Review & Approval by Consultant 4d 11-07-22 15-07-22 25% South Utility Building - Roof - 1st Review & Approval by Consultant
0% 15 Jul '22

351 Submission&Approval - Shop Drawing Str. - South Utility Building - Level211 dPT Slab
26-07-22 18-08-22 0% 0% Submission&Approval - Shop Drawing Str. - South Utility Building - Level 1 PT Slab 18 Aug '22

352 South Utility Building - Level 1 - 1st Preparation & Submission 7d 26-07-22 03-08-22 0% 0% South Utility Building - Level 1 - 1st Preparation & Submission 03 Aug '22

371 Submission&Approval - Shop Drawing - Architectural work 0% Submission&Approval - Shop Drawing - Architectural work
104 d 11-07-22 28-10-22 0.961538461538462% 28 Oct '22

450 Submission&Approval - Shop Drawing Ar. - East Utility Building


68 d 27-07-22 05-10-22 0% 0% Submission&Approval - Shop Drawing Ar. - East Utility Building 05 Oct '22

451 Submission&Approval - Shop Drawing Ar. - East Utility Building- Roof (Aluminum
22 d 27-07-22
trellis) 20-08-22 0% Submission&Approval - Shop Drawing Ar. - East Utility Building- Roof (Aluminum trellis)
0% 20 Aug '22

452 East Utility Building - Roof - 1st Preparation & Submission 7d 27-07-22 04-08-22 0% 0% East Utility Building - Roof - 1st Preparation & Submission 04 Aug '22

469 Submission&Approval - Shop Drawing Ar. - South Utility Building Submission&Approval - Shop Drawing Ar. - South Utility Building
90 d 11-07-22 12-10-22 1.11111111111111%
2% 12 Oct '22

470 Submission&Approval - Shop Drawing Ar. - South Utility Building - Roof 14


Metal
d Sheet
11-07-22 Submission&Approval
25-07-22 13%- Shop Drawing Ar. - South Utility Building - Roof Metal Sheet
7.14285714285714% 25 Jul '22

471 South Utility Building - Roof - 1st Preparation & Submission 7d 11-07-22 18-07-22 25% South Utility Building - Roof - 1st Preparation & Submission
14.2857142857143% 18 Jul '22

472 South Utility Building - Roof - 1st Review & Approval by Consultant 7d 19-07-22 25-07-22 0% 0% South Utility Building - Roof - 1st Review & Approval by Consultant 25 Jul '22

493 Submission&Approval - Shop Drawing - External work Submission&Approval


196 d 23-06-22 15-01-23 11% - Shop Drawing - External work
9.69387755102041% 15 Jan '23

494 Submission&Approval - Shop Drawing - External work - Retention pond 20 d Submission&Approval


23-06-22 - Shop Drawing
12-07-22 95% 93% - External work - Retention pond 12 Jul '22

496 Retention pond - 1st Review & Approval by Consultant 6d 07-07-22 12-07-22 75% Retention pond - 1st Review & Approval by Consultant
83.3333333333333% 12 Jul '22

497 Submission&Approval - Shop Drawing - External work - Boundary fence 16 d 29-06-22 Submission&Approval
15-07-22 81.25%73% - Shop Drawing - External work - Boundary fence 15 Jul '22

498 Boundary fence - 1st Preparation & Submission 13 d 29-06-22 11-07-22 Boundary fence - 1st Preparation & Submission
100% 90% 11 Jul '22

499 Boundary fence - 1st Review & Approval by Consultant 3d 12-07-22 15-07-22 0% 0% Boundary fence - 1st Review & Approval by Consultant 15 Jul '22

500 Submission&Approval - Shop Drawing - External work - Stormwater drainage


15 d
system
12-07-22 Submission&Approval
27-07-22 0% 0% - Shop Drawing - External work - Stormwater drainage system 27 Jul '22

501 Stormwater drainage system - 1st Preparation & Submission 8d 12-07-22 20-07-22 0% 0% Stormwater drainage system - 1st Preparation & Submission 20 Jul '22

502 Stormwater drainage system - 1st Review & Approval by Consultant 7d 21-07-22 27-07-22 0% 0% Stormwater drainage system - 1st Review & Approval by Consultant 27 Jul '22

543 Submission&Approval - Shop Drawing - External work - Pipe Rack 14 d 01-08-22 15-08-22 0% 0% Submission&Approval - Shop Drawing - External work - Pipe Rack 15 Aug '22

544 Pipe Rack - 1st Preparation & Submission 10 d 01-08-22 10-08-22 0% 0% Pipe Rack - 1st Preparation & Submission 10 Aug '22

546 Submission&Approval - Material Submission&Approval - Material


85 d 19-06-22 15-09-22 27.0588235294118%
25% 15 Sep '22

567 Submission&Approval - Material - Dock leveler 28 d 30-06-22 30-07-22 0% Submission&Approval - Material - Dock leveler
42.8571428571429% 30 Jul '22

568 Dock leveler - 1st Preparation & Submission 7d 30-06-22 06-07-22 100% 0% Dock leveler - 1st Preparation & Submission 06 Jul '22

569 Dock leveler - 1st Review & Approval by Consultant 7d 07-07-22 14-07-22 Dock leveler - 1st Review & Approval by Consultant
71.4285714285714%
0% 14 Jul '22

570 Dock leveler - 2nd Preparation & Submission 7d 15-07-22 21-07-22 0% 0% Dock leveler - 2nd Preparation & Submission 21 Jul '22

571 Dock leveler - 2nd Review & Approval by Consultant 7d 22-07-22 30-07-22 0% 0% Dock leveler - 2nd Review & Approval by Consultant 30 Jul '22

575 Submission&Approval - Material - Formwork for 1M & 2F, posttension slab 16 d 04-07-22 Submission&Approval
20-07-22 50% 50%- Material - Formwork for 1M & 2F, posttension slab 20 Jul '22

576 Formwork for 1M & 2F, posttension slab - 1st Preparation & Submission 9d 04-07-22 Formwork
12-07-22 for 89%
1M & 2F, posttension slab - 1st Preparation & Submission
88.8888888888889% 12 Jul '22

577 Formwork for 1M & 2F, posttension slab - 1st Review & Approval by Consultant 7 d 14-07-22 20-07-22 Formwork
0% 0%for 1M & 2F, posttension slab - 1st Review & Approval by Consultant 20 Jul '22

578 Submission&Approval - Material - Posttension slab 20 d 04-07-22 24-07-22 40% 41% Submission&Approval - Material - Posttension slab 24 Jul '22

579 Posttension slab - 1st Preparation & Submission 15 d 04-07-22 19-07-22 Posttension slab - 1st Preparation & Submission
53.3333333333333%
55% 19 Jul '22

580 Posttension slab - 1st Review & Approval by Consultant 5d 20-07-22 24-07-22 0% 0% Posttension slab - 1st Review & Approval by Consultant 24 Jul '22

581 Submission&Approval - Material - External CHB wall & Plastering cement 28 d 07-07-22 Submission&Approval
06-08-22 17.8571428571429%
19% - Material - External CHB wall & Plastering cement 06 Aug '22

582 External CHB wall & Plastering cement - 1st Preparation & Submission 7d 07-07-22 14-07-22 External CHB wall & Plastering cement - 1st Preparation & Submission
71.4285714285714%
75% 14 Jul '22

583 External CHB wall & Plastering cement - 1st Review & Approval by Consultant 7 d 15-07-22 21-07-22 0%External
0% CHB wall & Plastering cement - 1st Review & Approval by Consultant 21 Jul '22

584 External CHB wall & Plastering cement - 2nd Preparation & Submission 7d 22-07-22 30-07-22 0% 0% External CHB wall & Plastering cement - 2nd Preparation & Submission 30 Jul '22

585 External CHB wall & Plastering cement - 2nd Review & Approval by Consultant 7 d 31-07-22 06-08-22 0% 0% External CHB wall & Plastering cement - 2nd Review & Approval by Consultant 06 Aug '22

586 Submission&Approval - Material - Exterior & Interior paint 28 d 07-07-22 Submission&Approval - Material - Exterior & Interior paint
06-08-22 17.8571428571429%
19% 06 Aug '22

587 Exterior & Interior paint - 1st Preparation & Submission 7d 07-07-22 14-07-22 75% Exterior & Interior paint - 1st Preparation & Submission
71.4285714285714% 14 Jul '22

588 Exterior & Interior paint - 1st Review & Approval by Consultant 7d 15-07-22 21-07-22 0% 0% Exterior & Interior paint - 1st Review & Approval by Consultant 21 Jul '22

589 Exterior & Interior paint - 2nd Preparation & Submission 7d 22-07-22 30-07-22 0% 0% Exterior & Interior paint - 2nd Preparation & Submission 30 Jul '22

590 Exterior & Interior paint - 2nd Review & Approval by Consultant 7d 31-07-22 06-08-22 0% 0% Exterior & Interior paint - 2nd Review & Approval by Consultant 06 Aug '22

591 Submission&Approval - Material - Wall sand wich panel 24 d 10-07-22 Submission&Approval - Material - Wall sand wich panel
05-08-22 8.33333333333333%
9% 05 Aug '22

2 OF 4
PROJECT : Relief Project
MASTER SCHEDULE (REV0.01) Dated 11Jul22
ID Task Name Duration Start Finish Planned
%
% Complete
Complete June 2022 July 2022 August 2022 September 2022 October 2022 November 2022 December 2022 January 2023 February 2023 March 2023 April 2023 May 2023
30 01 03 05 07 0911 13 15 17 19 21 23 25 27 29 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 02 040608 10 12 14 16 18 20 22 24 26 28 30 01 03 05 07 0911 13 15 17 19 21 23 25 27 29 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 02 040608 10 12 14 16 18 20 22 24 26 28 30 0204060810 12 14 16 18 20 22 242628 30 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 02 04060810 12 14 16 18 20 22 24 26 28 02 04060810 12 141618 20 22 24 26 28 30 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 0
592 Wall sand wich panel - 1st Preparation & Submission 15 d 10-07-22 25-07-22 13.3333333333333%
15% Wall sand wich panel - 1st Preparation & Submission11 Jul, '22 25 Jul '22

593 Wall sand wich panel - 1st Review & Approval by Consultant 9d 26-07-22 05-08-22 0% 0% Wall sand wich panel - 1st Review & Approval by Consultant 05 Aug '22

594 Submission&Approval - Material - Sheet shutter (high speed shutter) 28 d 15-07-22 14-08-22 0% 0%Submission&Approval - Material - Sheet shutter (high speed shutter) 14 Aug '22

595 Sheet shutter (high speed shutter) - 1st Preparation & Submission 7d 15-07-22 21-07-22 0% 0% Sheet shutter (high speed shutter) - 1st Preparation & Submission 21 Jul '22

596 Sheet shutter (high speed shutter) - 1st Review & Approval by Consultant 7d 22-07-22 30-07-22 0% 0% Sheet shutter (high speed shutter) - 1st Review & Approval by Consultant 30 Jul '22

597 Sheet shutter (high speed shutter) - 2nd Preparation & Submission 7d 31-07-22 06-08-22 0% 0% Sheet shutter (high speed shutter) - 2nd Preparation & Submission 06 Aug '22

599 Submission&Approval - Material - Shutter,Steel & Aluminum door 28 d 15-07-22 14-08-22 0% 0% Submission&Approval - Material - Shutter,Steel & Aluminum door 14 Aug '22

600 Shutter,Steel & Aluminum door - 1st Preparation & Submission 7d 15-07-22 21-07-22 0% 0% Shutter,Steel & Aluminum door - 1st Preparation & Submission 21 Jul '22

601 Shutter,Steel & Aluminum door - 1st Review & Approval by Consultant 7d 22-07-22 30-07-22 0% 0% Shutter,Steel & Aluminum door - 1st Review & Approval by Consultant 30 Jul '22

602 Shutter,Steel & Aluminum door - 2nd Preparation & Submission 7d 31-07-22 06-08-22 0% 0% Shutter,Steel & Aluminum door - 2nd Preparation & Submission 06 Aug '22

604 Submission&Approval - Material - Roof Insulation & gal.mesh (Rock Wool) 13 d 15-07-22 27-07-22 0% Submission&Approval
0% - Material - Roof Insulation & gal.mesh (Rock Wool) 27 Jul '22

605 Roof Insulation & gal.mesh (Rock Wool) - 1st Preparation & Submission 8d 15-07-22 22-07-22 0% Roof Insulation & gal.mesh (Rock Wool) - 1st Preparation & Submission
0% 22 Jul '22

606 Roof Insulation & gal.mesh (Rock Wool) - 1st Review & Approval by Consultant 5 d 23-07-22 27-07-22 0% 0% Roof Insulation & gal.mesh (Rock Wool) - 1st Review & Approval by Consultant 27 Jul '22

607 Submission&Approval - Material - Siding wall sheet 15 d 20-07-22 05-08-22 0% 0% Submission&Approval - Material - Siding wall sheet 05 Aug '22

608 Siding wall sheet - 1st Preparation & Submission 8d 20-07-22 27-07-22 0% 0% Siding wall sheet - 1st Preparation & Submission 27 Jul '22

609 Siding wall sheet - 1st Review & Approval by Consultant 7d 30-07-22 05-08-22 0% 0% Siding wall sheet - 1st Review & Approval by Consultant 05 Aug '22

610 Submission&Approval - Material - Interior wall & floor finishing,ceramic 28 d 22-07-22 Submission&Approval
21-08-22 0% - Material
0% - Interior wall & floor finishing,ceramic tile,OA floor, epoxy,pcv vinyl sheet 21 Aug '22
tile,OA floor, epoxy,pcv vinyl sheet

611 Interior wall & floor finishing,ceramic tile,OA floor, epoxy,pcv vinyl sheet - 7d 22-07-22 Interior
30-07-22wall &0%
floor finishing,ceramic
0% tile,OA floor, epoxy,pcv vinyl sheet - 1st Preparation & Submission 30 Jul '22
1st Preparation & Submission

612 Interior wall & floor finishing,ceramic tile,OA floor, epoxy,pcv vinyl sheet - 7d 31-07-22 Interior wall
06-08-22 0% & floor
0%finishing,ceramic tile,OA floor, epoxy,pcv vinyl sheet - 1st Review & Approval by Consultant 06 Aug '22
1st Review & Approval by Consultant

615 Submission&Approval - Material - Water proof for water tank,toilet,kitchen,roof


28 dslab 22-07-22 21-08-22 0% Submission&Approval
0% - Material - Water proof for water tank,toilet,kitchen,roof slab 21 Aug '22

616 Water proof for water tank,toilet,kitchen,roof slab - 1st Preparation & Submission
7d 22-07-22 30-07-22 0% Water proof for water tank,toilet,kitchen,roof slab - 1st Preparation & Submission
0% 30 Jul '22

617 Water proof for water tank,toilet,kitchen,roof slab - 1st Review & Approval by Consultant
7d 31-07-22 06-08-22 0% 0% Water proof for water tank,toilet,kitchen,roof slab - 1st Review & Approval by Consultant 06 Aug '22

620 Submission&Approval - Material - Aluminum window,composite cladding & Insulated


10 d 22-07-22 Submission&Approval
glass system02-08-22 0% 0% - Material - Aluminum window,composite cladding & Insulated glass system 02 Aug '22

621 Aluminum window,composite cladding & Insulated glass system - 1st Preparation
5 d & Submission
22-07-22 Aluminum
26-07-22 0% window,composite
0% cladding & Insulated glass system - 1st Preparation & Submission 26 Jul '22

622 Aluminum window,composite cladding & Insulated glass system - 1st 5d 27-07-22 Aluminum
02-08-22 0% window,composite
0% cladding & Insulated glass system - 1st Review & Approval by Consultant 02 Aug '22
Review & Approval by Consultant

623 Submission&Approval - Material - Toilet partition 28 d 31-07-22 28-08-22 0% 0% Submission&Approval - Material - Toilet partition 28 Aug '22

624 Toilet partition - 1st Preparation & Submission 7d 31-07-22 06-08-22 0% 0% Toilet partition - 1st Preparation & Submission 06 Aug '22

628 Submission&Approval - Material - Key & lock set 19 d 01-08-22 20-08-22 0% 0% Submission&Approval - Material - Key & lock set 20 Aug '22

629 Key & lock set - 1st Preparation & Submission 7d 01-08-22 07-08-22 0% 0% Key & lock set - 1st Preparation & Submission 07 Aug '22

641 Procurement 211 d 07-07-22 13-02-23 2.3696682464455%


4% Procurement 13 Feb '23

642 Procurement - Material - Fireproof paint, OP paint for roof/siding wall structure40 d 07-07-22 Procurement
19-08-22 - Material
12.5% 19% - Fireproof paint, OP paint for roof/siding wall structure 19 Aug '22

643 10 d Procurement
Procurement - Fireproof paint, OP paint for roof/siding wall structure - Select Vendor &07-07-22 - Fireproof
Issued P.O. 17-07-22paint,
50%OP paint
75% for roof/siding wall structure - Select Vendor & Issued P.O. 17 Jul '22

644 Procurement - Fireproof paint, OP paint for roof/siding wall structure - Lead time
30 d 18-07-22 19-08-22 0%Procurement
0% - Fireproof paint, OP paint for roof/siding wall structure - Lead time 19 Aug '22

646 Procurement - Material - Polypropylane for process waste 30 d 07-07-22 Procurement - Material - Polypropylane for process waste
08-08-22 16.6666666666667%
33% 08 Aug '22

648 Procurement - Polypropylane for process waste - Lead time 20 d 18-07-22 08-08-22 0% 0% Procurement - Polypropylane for process waste - Lead time 08 Aug '22

650 Procurement - Material - Metal roof sheet 57 d 08-07-22 06-09-22 7.01754385964912%


12% Procurement - Material - Metal roof sheet 06 Sep '22

652 Procurement - Metal roof sheet - Lead time 56 d 09-07-22 06-09-22 5.35714285714286%
10% Procurement - Metal roof sheet - Lead time 06 Sep '22

654 Procurement - Material - Roof Steel Structure 36 d 11-07-22 19-08-22 2.77777777777778%


21% Procurement - Material - Roof Steel Structure 19 Aug '22

655 Procurement - Roof Steel Structure - Select Vendor & Issued P.O. 10 d 11-07-22 21-07-22 10% Procurement - Roof Steel Structure - Select Vendor & Issued P.O.
75% 21 Jul '22

656 Procurement - Roof Steel Structure - Lead time 26 d 22-07-22 19-08-22 0% 0% Procurement - Roof Steel Structure - Lead time 19 Aug '22

658 Procurement - Material - PVC & HDPE for sanitary waste, soil, vent 20 d 15-07-22 05-08-22 0% 25% Procurement - Material - PVC & HDPE for sanitary waste, soil, vent 05 Aug '22

659 Procurement - PVC & HDPE for sanitary waste, soil, vent - Select Vendor & Issued
10 dP.O.15-07-22 Procurement
24-07-22 0% -50%PVC & HDPE for sanitary waste, soil, vent - Select Vendor & Issued P.O. 24 Jul '22

660 Procurement - PVC & HDPE for sanitary waste, soil, vent - Lead time 10 d 25-07-22 05-08-22 0% 0% Procurement - PVC & HDPE for sanitary waste, soil, vent - Lead time 05 Aug '22

662 Procurement - Material - Formwork for 1M & 2F, posttension slab 27 d 21-07-22 19-08-22 0% 0% Procurement - Material - Formwork for 1M & 2F, posttension slab 19 Aug '22

663 Procurement - Formwork for 1M & 2F, posttension slab - Select Vendor & Issued
10P.O.
d 21-07-22 01-08-22 0% Procurement
0% - Formwork for 1M & 2F, posttension slab - Select Vendor & Issued P.O. 01 Aug '22

666 Procurement - Material - Posttension slab 20 d 25-07-22 16-08-22 0% 0% Procurement - Material - Posttension slab 16 Aug '22

667 Procurement - Posttension slab - Select Vendor & Issued P.O. 10 d 25-07-22 05-08-22 0% 0% Procurement - Posttension slab - Select Vendor & Issued P.O. 05 Aug '22

670 Procurement - Material - Roof Insulation & gal.mesh (rock wool) 38 d 30-07-22 06-09-22 0% 20% Procurement - Material - Roof Insulation & gal.mesh (rock wool) 06 Sep '22

671 Procurement - Roof Insulation & gal.mesh (rock wool) - Select Vendor & Issued10
P.O.
d 30-07-22 08-08-22 0% 75% Procurement - Roof Insulation & gal.mesh (rock wool) - Select Vendor & Issued P.O. 08 Aug '22

674 Procurement - Material - Dock leveler 190 d 31-07-22 13-02-23 0% 0% Procurement - Material - Dock leveler 13 Feb '23

675 Procurement - Dock leveler - Select Vendor & Issued P.O. 10 d 31-07-22 09-08-22 0% 0% Procurement - Dock leveler - Select Vendor & Issued P.O. 09 Aug '22

730 Construction Construction


322 d 15-06-22 22-05-23 8.38509316770186%
3% 22 May '23

731 Main Factory 322 d 15-06-22 22-05-23 8.38509316770186%


4% Main Factory 22 May '23

732 Main Factory - Structural Work 241 d 15-06-22 Main


5% Factory - Structural Work
21-02-23 11.2033195020747% 21 Feb '23

733 Main Factory - Structural Work - Zone A 225 d 15-06-22 05-02-23Main


12% Factory
6%- Structural Work - Zone A 05 Feb '23

734 Main Factory - Structural Work - Zone A1 190 d 15-06-22 28-12-22Main Factory - Structural Work - Zone A1
14.2105263157895%
10% 28 Dec '22

735 Main Factory - Substructure- Zone A1 82 d 15-06-22 Main Factory


36% - Substructure- Zone A1
08-09-22 32.9268292682927% 08 Sep '22

740 Zone A1 - Soil backfill under slab 27 d 22-06-22 75% Zone A1 - Soil backfill under slab
19-07-22 74.0740740740741% 19 Jul '22

743 Zone A1.3 - Soil backfill under slab 9d 10-07-22 19-07-22 22.2222222222222%
25% Zone A1.3 - Soil backfill under slab 19 Jul '22

744 Zone A1 - Foundation and Pier 33 d 09-07-22 14-08-22 9.09090909090909%


2% Zone A1 - Foundation and Pier 14 Aug '22

745 Zone A1.2 - Foundation and Pier 11 d 09-07-22 20-07-22 27.2727272727273%


5% Zone A1.2 - Foundation and Pier 20 Jul '22

746 Zone A1.1 - Foundation and Pier 11 d 21-07-22 02-08-22 0% 0% Zone A1.1 - Foundation and Pier 02 Aug '22

781 Main Factory - Structural Work - Zone A2 187 d 29-06-22 Main Factory - Structural Work - Zone A2
12-01-23 6.95187165775401%
5% 12 Jan '23

782 Main Factory - Substructure- Zone A2 82 d 29-06-22 Main Factory - Substructure- Zone A2
22-09-22 15.8536585365854%
17% 22 Sep '22

783 Zone A2 - Pile Cut-off Level 21 d 29-06-22 20-07-22 61.9047619047619%


77% Zone A2 - Pile Cut-off Level 20 Jul '22

786 Zone A2.3 - Pile Cut-off Level 7d 14-07-22 20-07-22 0% 30% Zone A2.3 - Pile Cut-off Level 20 Jul '22

787 Zone A2 - Soil backfill under slab 27 d 06-07-22 04-08-22 22.2222222222222%


22% Zone A2 - Soil backfill under slab 04 Aug '22

788 Zone A2.2 - Soil backfill under slab 9d 06-07-22 15-07-22 66.6666666666667%
67% Zone A2.2 - Soil backfill under slab 15 Jul '22

789 Zone A2.1 - Soil backfill under slab 9d 16-07-22 24-07-22 0% 0% Zone A2.1 - Soil backfill under slab 24 Jul '22

790 Zone A2.3 - Soil backfill under slab 9d 25-07-22 04-08-22 0% 0% Zone A2.3 - Soil backfill under slab 04 Aug '22

791 Zone A2 - Foundation and Pier 45 d 16-07-22 01-09-22 0% 0% Zone A2 - Foundation and Pier 01 Sep '22

792 Zone A2.2 - Foundation and Pier 15 d 16-07-22 01-08-22 0% 0% Zone A2.2 - Foundation and Pier 01 Aug '22

822 Main Factory - Structural Work - Zone A3 197 d 14-07-22 05-02-23 0% 3% Main Factory - Structural Work - Zone A3 05 Feb '23

823 Main Factory - Substructure- Zone A3 81 d 14-07-22 05-10-22 0% 12% Main Factory - Substructure- Zone A3 05 Oct '22

824 Zone A3 - Pile Cut-off Level 21 d 14-07-22 05-08-22 0% 75% Zone A3 - Pile Cut-off Level 05 Aug '22

825 Zone A3.2 - Pile Cut-off Level 7d 14-07-22 20-07-22 0% 75% Zone A3.2 - Pile Cut-off Level 20 Jul '22

826 Zone A3.1 - Pile Cut-off Level 7d 21-07-22 27-07-22 0% 75% Zone A3.1 - Pile Cut-off Level 27 Jul '22

827 Zone A3.3 - Pile Cut-off Level 7d 30-07-22 05-08-22 0% 75% Zone A3.3 - Pile Cut-off Level 05 Aug '22

3 OF 4
PROJECT : Relief Project
MASTER SCHEDULE (REV0.01) Dated 11Jul22
ID Task Name Duration Start Finish Planned
%
% Complete
Complete June 2022 July 2022 August 2022 September 2022 October 2022 November 2022 December 2022 January 2023 February 2023 March 2023 April 2023 May 2023
30 01 03 05 07 0911 13 15 17 19 21 23 25 27 29 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 02 040608 10 12 14 16 18 20 22 24 26 28 30 01 03 05 07 0911 13 15 17 19 21 23 25 27 29 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 02 040608 10 12 14 16 18 20 22 24 26 28 30 0204060810 12 14 16 18 20 22 242628 30 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 02 04060810 12 14 16 18 20 22 24 26 28 02 04060810 12 141618 20 22 24 26 28 30 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 0
828 Zone A3 - Soil backfill under slab 27 d 21-07-22 19-08-22 0% 0% Zone A3 - Soil backfill
11 Jul,under
'22 slab 19 Aug '22

829 Zone A3.2 - Soil backfill under slab 9d 21-07-22 31-07-22 0% 0% Zone A3.2 - Soil backfill under slab 31 Jul '22

830 Zone A3.1 - Soil backfill under slab 9d 01-08-22 09-08-22 0% 0% Zone A3.1 - Soil backfill under slab 09 Aug '22

832 Zone A3 - Foundation and Pier 45 d 01-08-22 15-09-22 0% 0% Zone A3 - Foundation and Pier 15 Sep '22

833 Zone A3.2 - Foundation and Pier 15 d 01-08-22 16-08-22 0% 0% Zone A3.2 - Foundation and Pier 16 Aug '22

869 Main Factory - Structural Work - Zone B 238 d 18-06-22 Main Factory - Structural Work - Zone B
21-02-23 10.0840336134454%
5% 21 Feb '23

870 Main Factory - Structural Work - Zone B1 195 d 18-06-22 Main Factory
9% - Structural Work - Zone B1
09-01-23 12.3076923076923% 09 Jan '23

871 Main Factory - Substructure- Zone B1 82 d 18-06-22 Main Factory - Substructure- Zone B1
11-09-22 29.2682926829268%
29% 11 Sep '22

876 Zone B1 - Soil backfill under slab 27 d 25-06-22 Zone B1 - Soil backfill under slab
22-07-22 62.962962962963%
63% 22 Jul '22

878 Zone B1.2 - Soil backfill under slab 9d 04-07-22 12-07-22 88.8888888888889%
89% Zone B1.2 - Soil backfill under slab 12 Jul '22

879 Zone B1.3 - Soil backfill under slab 9d 14-07-22 22-07-22 0% 0% Zone B1.3 - Soil backfill under slab 22 Jul '22

880 Zone B1 - Foundation and Pier 45 d 04-07-22 21-08-22 17.7777777777778%


0% Zone B1 - Foundation and Pier 21 Aug '22

881 Zone B1.1 - Foundation and Pier 15 d 04-07-22 19-07-22 53.3333333333333%


0% Zone B1.1 - Foundation and Pier 19 Jul '22

882 Zone B1.2 - Foundation and Pier 15 d 20-07-22 05-08-22 0% 0% Zone B1.2 - Foundation and Pier 05 Aug '22

917 Main Factory - Structural Work - Zone B2 189 d 02-07-22 Main Factory - Structural Work - Zone B2
17-01-23 5.29100529100529%
4% 17 Jan '23

918 Main Factory - Substructure- Zone B2 82 d 02-07-22 25-09-22 12.1951219512195%


14% Main Factory - Substructure- Zone B2 25 Sep '22

919 Zone B2 - Pile Cut-off Level 21 d 02-07-22 23-07-22 47.6190476190476%


70% Zone B2 - Pile Cut-off Level 23 Jul '22

921 Zone B2.2 - Pile Cut-off Level 7d 09-07-22 16-07-22 42.8571428571429%


55% Zone B2.2 - Pile Cut-off Level 16 Jul '22

922 Zone B2.3 - Pile Cut-off Level 7d 17-07-22 23-07-22 0% 55% Zone B2.3 - Pile Cut-off Level 23 Jul '22

923 Zone B2 - Soil backfill under slab 27 d 09-07-22 07-08-22 11.1111111111111%


12% Zone B2 - Soil backfill under slab 07 Aug '22

924 Zone B2.1 - Soil backfill under slab 9d 09-07-22 18-07-22 33.3333333333333%
35% Zone B2.1 - Soil backfill under slab 18 Jul '22

925 Zone B2.2 - Soil backfill under slab 9d 19-07-22 27-07-22 0% 0% Zone B2.2 - Soil backfill under slab 27 Jul '22

926 Zone B2.3 - Soil backfill under slab 9d 30-07-22 07-08-22 0% 0% Zone B2.3 - Soil backfill under slab 07 Aug '22

927 Zone B2 - Foundation and Pier 45 d 19-07-22 04-09-22 0% 0% Zone B2 - Foundation and Pier 04 Sep '22

928 Zone B2.1 - Foundation and Pier 15 d 19-07-22 04-08-22 0% 0% Zone B2.1 - Foundation and Pier 04 Aug '22

964 Main Factory - Structural Work - Zone B3 192 d 17-07-22 03-02-23 0% 5% Main Factory - Structural Work - Zone B3 03 Feb '23

965 Main Factory - Substructure- Zone B3 82 d 17-07-22 09-10-22 0% 16% Main Factory - Substructure- Zone B3 09 Oct '22

970 Zone B3 - Soil backfill under slab 27 d 24-07-22 22-08-22 0% 0% Zone B3 - Soil backfill under slab 22 Aug '22

971 Zone B3.1 - Soil backfill under slab 9d 24-07-22 03-08-22 0% 0% Zone B3.1 - Soil backfill under slab 03 Aug '22

1094 Office and Canteen 322 d 15-06-22 22-05-23 Office and Canteen
8.38509316770186%
3% 22 May '23

1095 Office and Canteen - Structural Work 200 d 15-06-22 Office and
11-01-23 13.5% 11%Canteen - Structural Work 11 Jan '23

1096 Office and Canteen - Substructure 82 d 15-06-22 Office and Canteen - Substructure
08-09-22 32.9268292682927%
33% 08 Sep '22

1101 Office and Canteen - Soil backfill under slab 27 d 22-06-22 Office and Canteen - Soil backfill under slab
19-07-22 74.0740740740741%
75% 19 Jul '22

1104 Office and Canteen (O3) - Soil backfill under slab 9d 10-07-22 19-07-22 22.2222222222222%
25% Office and Canteen (O3) - Soil backfill under slab 19 Jul '22

1105 Office and Canteen - Foundation and Pier Office and Canteen - Foundation and Pier
45 d 01-07-22 18-08-22 24.4444444444444%
3% 18 Aug '22

1106 Office and Canteen (O2) - Foundation and Pier 15 d 01-07-22 16-07-22 8% Office and Canteen (O2) - Foundation and Pier
73.3333333333333% 16 Jul '22

1107 Office and Canteen (O1) - Foundation and Pier 15 d 17-07-22 02-08-22 0% 0% Office and Canteen (O1) - Foundation and Pier 02 Aug '22

1192 East Utility Building 150 d 19-06-22 21-11-22 15.3333333333333%


12% East Utility Building 21 Nov '22

1193 East Utility Building - Structural Work 128 d 19-06-22 East


30-10-22 17.96875%
15%Utility Building - Structural Work 30 Oct '22

1194 East Utility Building - Substructure 69 d 19-06-22 East Utility Building - Substructure
30-08-22 33.3333333333333%
26% 30 Aug '22

1199 East Utility Building - Soil backfill under slab 27 d 26-06-22 East Utility Building - Soil backfill under slab
23-07-22 59.2592592592593%
59% 23 Jul '22

1201 East Utility Building (E2) - Soil backfill under slab 9d 05-07-22 14-07-22 East Utility Building (E2) - Soil backfill under slab
77.7777777777778%
78% 14 Jul '22

1202 East Utility Building (E3) - Soil backfill under slab 9d 15-07-22 23-07-22 0% 0% East Utility Building (E3) - Soil backfill under slab 23 Jul '22

1203 East Utility Building - Foundation and Pier 27 d 05-07-22 03-08-22 25.9259259259259%
0% East Utility Building - Foundation and Pier 03 Aug '22

1204 East Utility Building (E1) - Foundation and Pier 9d 05-07-22 14-07-22 77.7777777777778%
0% East Utility Building (E1) - Foundation and Pier 14 Jul '22

1205 East Utility Building (E2) - Foundation and Pier 9d 15-07-22 23-07-22 0% 0% East Utility Building (E2) - Foundation and Pier 23 Jul '22

1206 East Utility Building (E3) - Foundation and Pier 9d 24-07-22 03-08-22 0% 0% East Utility Building (E3) - Foundation and Pier 03 Aug '22

1207 East Utility Building - Gr.Beam 42 d 10-07-22 24-08-22 4.76190476190476%


0% East Utility Building - Gr.Beam 24 Aug '22

1208 East Utility Building (E1) - Gr.Beam 14 d 10-07-22 24-07-22 14.2857142857143%


0% East Utility Building (E1) - Gr.Beam 24 Jul '22

1209 East Utility Building (E2) - Gr.Beam 14 d 25-07-22 09-08-22 0% 0% East Utility Building (E2) - Gr.Beam 09 Aug '22

1235 South Utility Building 206 d 19-06-22 21-01-23 South Utility Building
11.1650485436893%
7% 21 Jan '23

1236 South Utility Building - Structural Work 164 d 19-06-22 South Utility Building - Structural Work
06-12-22 14.0243902439024%
14% 06 Dec '22

1237 South Utility Building - Substructure 79 d 19-06-22 South


25%Utility Building - Substructure
09-09-22 29.1139240506329% 09 Sep '22

1241 South Utility Building - Soil backfill under slab 28 d 26-06-22 South Utility Building - Soil backfill under slab
24-07-22 57.1428571428571%
60% 24 Jul '22

1242 South Utility Building - Foundation and Pier 45 d 03-07-22 20-08-22 20% 3% South Utility Building - Foundation and Pier 20 Aug '22

1243 South Utility Building - Zone A - Foundation and Pier (GL.11-29) 45 d 03-07-22 20-08-22 South
20% Utility
2% Building - Zone A - Foundation and Pier (GL.11-29) 20 Aug '22

1244 South Utility Building - Zone B - Foundation and Pier (GL.1.3-11) 39 d 09-07-22 20-08-22 South Utility Building - Zone B - Foundation and Pier (GL.1.3-11)
7.69230769230769%
5% 20 Aug '22

1245 South Utility Building - Gr.Beam 30 d 31-07-22 30-08-22 0% 0% South Utility Building - Gr.Beam 30 Aug '22

1246 South Utility Building - Zone A - Gr.Beam 21 d 31-07-22 21-08-22 0% 0% South Utility Building - Zone A - Gr.Beam 21 Aug '22

1265 South Utility Building - Water Tank 137 d 20-07-22 09-12-22 0% 0% South Utility Building - Water Tank 09 Dec '22

1266 South Utility Building - WT.Base slab, RC. Slab 35 d 20-07-22 26-08-22 0% 0% South Utility Building - WT.Base slab, RC. Slab 26 Aug '22

1267 South Utility Building - WT.Base slab, RC. Slab (GL.27-Y) 10 d 20-07-22 31-07-22 0% 0% South Utility Building - WT.Base slab, RC. Slab (GL.27-Y) 31 Jul '22

1268 South Utility Building - WT.Base slab, RC. Slab (GL.22-27) 10 d 23-07-22 03-08-22 0% 0% South Utility Building - WT.Base slab, RC. Slab (GL.22-27) 03 Aug '22

1269 South Utility Building - WT.Base slab, RC. Slab (GL.19-22) 10 d 31-07-22 09-08-22 0% 0% South Utility Building - WT.Base slab, RC. Slab (GL.19-22) 09 Aug '22

1301 External Work 294 d 14-07-22 22-05-23 0% 0% External Work 22 May '23

1302 External Work - Retention pond 213 d 14-07-22 21-02-23 0% 0% External Work - Retention pond 21 Feb '23

1303 Retention Pond - Soil Excavation 63 d 14-07-22 17-09-22 0% 0% Retention Pond - Soil Excavation 17 Sep '22

1305 External Work - Boundary fence & Main entrance 292 d 16-07-22 22-05-23 0% 0% External Work - Boundary fence & Main entrance 22 May '23

1306 External Work - Boundary fence 292 d 16-07-22 22-05-23 0% 0% External Work - Boundary fence 22 May '23

1307 Mock up Boundary fence type 2 (West Side) 14 d 16-07-22 31-07-22 0% 0% Mock up Boundary fence type 2 (West Side) 31 Jul '22

1308 Boundary fence Team 1 - At Future Expansion (West Side) 114 d 01-08-22 25-11-22 0% 0% Boundary fence Team 1 - At Future Expansion (West Side) 25 Nov '22

1309 Mock up Boundary fence type 3 (North Side to East Side) 24 d 20-07-22 15-08-22 0% 0% Mock up Boundary fence type 3 (North Side to East Side) 15 Aug '22

1310 Mock up Boundary fence type 1 (North Side to East Side) 22 d 01-08-22 23-08-22 0% 0% Mock up Boundary fence type 1 (North Side to East Side) 23 Aug '22

1315 External Work - Stormwater drainage system 278 d 01-08-22 22-05-23 0% 0% External Work - Stormwater drainage system 22 May '23

1316 Stormwater drainage system Zone 1 - At Retention Pond 132 d 01-08-22 14-12-22 0% 0% Stormwater drainage system Zone 1 - At Retention Pond 14 Dec '22