PROJECT : Relief Project

MASTER SCHEDULE (REV0.01) Dated 11Jul22


ID Task Name Duration Start Finish Planned
% Complete
%
Complete Jun Jul Aug
30-05 06-06 13-06 20-06 27-06 04-07 11-07 18-07 25-07 01-08 08-08 15-08 22-08 29-08
1 RELIEF PROJECT: PROPOSED MASTER SCHEDULE 347 d RELIEF PROJECT:
31-05-22 PROPOSED
01-06-23 MASTER
10%SCHEDULE
12.1037463976945% 11 Jul, '22
2 Project Keydate 347 d Project Keydate
31-05-22 01-06-23 12.1037463976945%
0%
3 General 347 d 0% General
31-05-22 01-06-23 12.1037463976945%
4 LOA, Award Main Contractor 0d LOA,100%
31-05-22 31-05-22 Award 100%
Main Contractor 31 May '22

5 LOA, Award for MEP Package 0d 15-07-22 15-07-22 0% 0% LOA, Award for MEP Package 15 Jul '22

6 Commencement Work On Site 0d 15-06-22 15-06-22 100% 100% Commencement Work On Site 15 Jun '22

7 Contract Completion (Final handover of All area) 0d 01-06-23 01-06-23 0% 0%


8 Key Milestones 124 d 09-01-23 22-05-23 0% 0%
9 M1 - Main Factory Roof Completion 0d 09-01-2309-01-230% 0%
10 M2 - 1st Floor structure completion & Underground Utilities 0d 21-01-2321-01-23 0% 0%
11 M3 - 2nd Floor Structure Completion 0d 21-02-2321-02-230% 0%
12 M4 - Guardhouse & Custrm office 0d 17-03-23 17-03-23 0% 0%
13 M5 - Stormwater Drainage System 0d 22-05-2322-05-230% 0%
14 M6 - Road & Pavement, Loading dock, Truck scale 0d 22-05-23 22-05-23 0% 0%
15 M7 - VIP & Visitor Parking (Northside) 0d 22-05-23 22-05-23 0% 0%
16 M8 - Car & Motorcycle Parking (Southside) 0d 22-05-2322-05-230% 0%
17 M9 - Boundary fence & Main entrance 0d 22-05-2322-05-230% 0%
18 M10 - Green area & Landscape 0d 22-05-23 22-05-23 0% 0%
19 M11 - MEP hookup and ready for Testing & Commissioning 0d 22-05-23 22-05-23 0% 0%
20 Handover Milestones 178 d 21-11-22 01-06-23 0% 0%
21 H.O. - East Utility Building Completion 0d 21-11-22 21-11-22 0% 0%
22 H.O. - South Utility Building Completion 0d 21-01-2321-01-23 0% 0%
23 H.O. - Retention pond Completion 0d 21-02-2321-02-230% 0%
24 H.O. - Building Completion 0d 22-05-23 22-05-23 0% 0%
25 H.O - Final handover all areas 0d 01-06-23 01-06-23 0% 0%
26 Application & Permit 32 d Application
31-05-22 01-07-22 100% 100% & Permit 01 Jul '22

27 Application & Permit- Construction Permit by Owner 0d Application


31-05-22 & Permit- Construction
31-05-22 100% Permit
100% by Owner 31 May '22
28 Application & Permit - Temporary Power 24 d 08-06-22 01-07-22 100% 100%Application & Permit - Temporary Power 01 Jul '22
29 Temporary Power Supply - Submission Application by TKC to PEA 9d 08-06-22 Temporary 100%
16-06-22 Power Supply
100% - Submission Application by TKC to PEA 16 Jun '22
30 Temporary Power Supply - PEA site survey & quotation 14 d 13-06-22 26-06-22 100% 100% Temporary Power Supply - PEA site survey & quotation 26 Jun '22
31 Temporary Power Supply - Issuanace PO to PEA 5d 27-06-22 01-07-22 100% 100% Temporary Power Supply - Issuanace PO to PEA 01 Jul '22
32 Application & Permit - Temporary Water Supply and Drainage Work 13 d 14-06-22 26-06-22 100% 100% Application & Permit - Temporary Water Supply and Drainage Work 26 Jun '22
33 Temp. Water & Drainage - Submission Application CW to WHA 4d 14-06-22 17-06-22 100% 100%Temp. Water & Drainage - Submission Application CW to WHA 17 Jun '22
34 Temp. Water & Drainage - Quotation by WHA 5d 18-06-22 22-06-22 100% 100% Temp. Water & Drainage - Quotation by WHA 22 Jun '22
35 Temp. Water & Drainage - Issuanace PO to WHA 5d 22-06-22 26-06-22 100% 100% Temp. Water & Drainage - Issuanace PO to WHA 26 Jun '22
36 Mobilization & Temporary Work 70 d 31-05-22 Mobilization
11-08-22 60%& Temporary
78% Work 11 Aug '22

37 Submission and Approval - Temporary Work 37 d Submission


01-06-22 07-07-22and 100%
Approval - Temporary Work
100% 07 Jul '22

38 Submission & Approval - Temporary Owner & Consult office 7 d Submission & Approval
01-06-22 - Temporary
07-06-22 100% Owner & Consult office
100% 07 Jun '22
39 Temporary Owner & Consult office - Preparation & Submission Drawings by TKC Temporary Owner
2 d & Consult office - Preparation
01-06-22 02-06-22& Submission
100% 100% Drawings by TKC 02 Jun '22
40 Temporary Owner & Consult office - Review & Approval Drawings by Consultant Temporary
5 d Owner &03-06-22
Consult office - Review100%
07-06-22 & Approval Drawings by Consultant
100% 07 Jun '22
41 Submission & Approval - Temporary Gate No.2 37 d Submission
01-06-22 & Approval
07-07-22 100% - Temporary
100% Gate No.2 07 Jul '22
42 Temporary Gate No.2 - Submission Application by TKC 14 d Temporary
01-06-22Gate No.2 - Submission
14-06-22 100% 100%Application by TKC 14 Jun '22
43 Temporary Gate No.2 - Review & Approval by WHA 23 d 15-06-22 07-07-22 100% 100% Temporary Gate No.2 - Review & Approval by WHA 07 Jul '22
44 Temporary Facilities 70 d Temporary
31-05-22 11-08-22 60% 77% Facilities 11 Aug '22

45 TKC Office & Toilet 34 d 04-06-22 07-07-22 100% 100% TKC Office & Toilet 07 Jul '22

46 TKC Office & Toilets - Installation 9d 04-06-22 12-06-22 100% TKC Office & Toilets - Installation
100% 12 Jun '22
47 TKC Office & Toilets - CW, drain pipe , septic tank connect 9d 13-06-22 21-06-22 100% 100% TKC Office & Toilets - CW, drain pipe , septic tank connect 21 Jun '22
48 TKC Office & Toilets - Roof, walkway and miscellaneous 25 d 13-06-22 07-07-22 100% 100% TKC Office & Toilets - Roof, walkway and miscellaneous 07 Jul '22
49 Owner & Consult office Office 37 d 08-06-22 15-07-22 91.8918918918919%
100% Owner & Consult office Office 15 Jul '22

50 Owner & Consult office Office - Order temporary contaner office 7d 08-06-22 Owner & Consult
14-06-22 office Office - Order temporary contaner office
100% 100% 14 Jun '22
51 Owner & Consult office Office - Installation 4d 19-06-22 22-06-22 100% 100% Owner & Consult office Office - Installation 22 Jun '22
52 TKC Office & Toilets - CW, drain pipe , septic tank connect 8d 23-06-22 30-06-22 100% 100% TKC Office & Toilets - CW, drain pipe , septic tank connect 30 Jun '22
53 TKC Office & Toilets - CCTV 4d 23-06-22 26-06-22 100% 100% TKC Office & Toilets - CCTV 26 Jun '22
54 TKC Office & Toilets - Roof, walkway and miscellaneous 22 d 23-06-22 15-07-22 86.3636363636364%
100% TKC Office & Toilets - Roof, walkway and miscellaneous 15 Jul '22
55 Temporary rest area for worker 27 d 04-06-22 30-06-22 100% 100% Temporary rest area for worker 30 Jun '22

56 Temporary Gate (2 Gates) 26 d 04-07-22 01-08-22 30.7692307692308%


37% Temporary Gate (2 Gates) 01 Aug '22

57 Temporary Gate No.1 (use existing gate) - Additional Wheel cleaning at gate 1 16 d 04-07-22 20-07-22
50% 60% Temporary Gate No.1 (use existing gate) - Additional Wheel cleaning at gate 1 20 Jul '22
58 Temporary Gate No.2 22 d 08-07-22 01-08-22
18.1818181818182%
21% Temporary Gate No.2 01 Aug '22
59 Temporary Gate No.2 - Leveling & concerete connnect to WHA road 10 d 08-07-22 18-07-22
40% 50% Temporary Gate No.2 - Leveling & concerete connnect to WHA road 18 Jul '22
60 Temporary Gate No.2 - Foundation & temporary gate installation 8d 19-07-22 26-07-22
0% 0% Temporary Gate No.2 - Foundation & temporary gate installation 26 Jul '22
61 Temporary Gate No.2 - Wheel cleaning at gate 2 6d 25-07-22 01-08-22
0% 0% Temporary Gate No.2 - Wheel cleaning at gate 2 01 Aug '22
62 Temporary Guardhouse (3 nos) 24 d 07-06-22 30-06-22 100% 100% Temporary Guardhouse (3 nos) 30 Jun '22

63 Temporary worker toilet (45 rooms) 47 d Temporary worker toilet (45 rooms)
06-06-22 23-07-22 76.5957446808511%
95% 23 Jul '22

64 Temporary worker toilet (30 rooms) - Installation 13 d 06-06-22 18-06-22 Temporary


100% 100%worker toilet (30 rooms) - Installation 18 Jun '22
65 Temporary worker toilet (30 rooms) - CW, drain pipe , septic tank connect 22 d 14-06-22 05-07-22 100%Temporary
100% worker toilet (30 rooms) - CW, drain pipe , septic tank connect 05 Jul '22
66 TKC Office & Toilets (30 rooms) - Temporary fence (blind wall) 14 d 01-07-22 15-07-22 78.5714285714286%
80% TKC Office & Toilets (30 rooms) - Temporary fence (blind wall) 15 Jul '22
67 Temporary worker toilet (15 rooms) - Installation 10 d 05-07-22 15-07-22 70% 100% Temporary worker toilet (15 rooms) - Installation 15 Jul '22
68 Temporary worker toilet (15 rooms) - CW, drain pipe , septic tank connect 13 d 10-07-22 23-07-22 15.3846153846154%
100% Temporary worker toilet (15 rooms) - CW, drain pipe , septic tank connect 23 Jul '22
69 TKC Office & Toilets (15 rooms) - Temporary fence (blind wall) 8d 16-07-22 23-07-22 0% 80% TKC Office & Toilets (15 rooms) - Temporary fence (blind wall) 23 Jul '22
70 Temporary moring talk & carpark area 42 d 10-06-22 22-07-22 76.1904761904762%
93% Temporary moring talk & carpark area 22 Jul '22

71 Temporary moring talk 11 d 10-06-22 20-06-22 100% 100% Temporary moring talk 20 Jun '22

72 Temporary carpark 1 with walkway 33 d 10-06-22 12-07-22 96.969696969697%


100% Temporary carpark 1 with walkway 12 Jul '22

73 Temporary carpark 2 with walkway 14 d 08-07-22 22-07-22 28.5714285714286%


70% Temporary carpark 2 with walkway 22 Jul '22

74 Temporary TK storage,checemical store ,garbage house & rebar yard 29 d 12-06-22 10-07-22 Temporary
100% 100% TK storage,checemical store ,garbage house & rebar yard 10 Jul '22

75 Temporary TK storage - Line mark / Soil Adjustment Level / Compaction 7d 12-06-22 18-06-22Temporary TK storage - Line mark / Soil Adjustment Level / Compaction
100% 100% 18 Jun '22
76 Temporary TK storage - Roof wall & door 22 d 19-06-22 10-07-22 100% 100% Temporary TK storage - Roof wall & door 10 Jul '22
77 Temporary formwork,scaffolding yard 44 d 14-06-22 30-07-22 63.6363636363636%
61% Temporary formwork,scaffolding yard 30 Jul '22

78 Temporary formwork,scaffolding yard - Line mark / Soil Adjustment Level / Compaction 5d Temporary 100%
14-06-22 18-06-22 formwork,scaffolding
100% yard - Line mark / Soil Adjustment Level / Compaction 18 Jun '22
79 Temporary formwork,scaffolding yard - Temporary fence 18 d 10-07-22 30-07-22 11.1111111111111%
50% Temporary formwork,scaffolding yard - Temporary fence 30 Jul '22
80 Temporary Road (Blue Color) 37 d 08-06-22 15-07-22 91.8918918918919%
97% Temporary Road (Blue Color) 15 Jul '22

81 Temporary Road - Line mark 4d 08-06-22 11-06-22 100% 100% Temporary Road - Line mark 11 Jun '22
82 Temporary Road - Soil adjustment level 19 d 12-06-22 30-06-22 100% 100% Temporary Road - Soil adjustment level 30 Jun '22
83 Temporary Road - Soil cement & compaction 25 d 16-06-22 10-07-22 100% 100% Temporary Road - Soil cement & compaction 10 Jul '22

1 OF 16
PROJECT : Relief Project
MASTER SCHEDULE (REV0.01) Dated 11Jul22
ID Task Name Duration Start Finish Planned
% Complete
%
Complete Jun Jul Aug
30-05 06-06 13-06 20-06 27-06 04-07 11-07 18-07 25-07 01-08 08-08 15-08 22-08 29-08
84 Temporary Road - Rain drainage gutter 22 d 23-06-22 15-07-22 86.3636363636364%
90% Temporary Road - Rain drainage gutter 11 Jul, '22 15 Jul '22
85 Temporary Internal Road (Orange Color) 49 d Temporary Internal Road (Orange Color)
10-06-22 31-07-22 65.3061224489796%
69% 31 Jul '22

86 Temporary Road - Line mark 4d 10-06-22 13-06-22 100% 100% Temporary Road - Line mark 13 Jun '22
87 Temporary Road - Pile head cut 30 d 15-06-22 15-07-22 90% 95% Temporary Road - Pile head cut 15 Jul '22
88 Temporary Road - Soil adjustment level 30 d 20-06-22 20-07-22 73.3333333333333%
75% Temporary Road - Soil adjustment level 20 Jul '22
89 Temporary Road - Soil cement & compaction 31 d 24-06-22 25-07-22 58.0645161290323%
60% Temporary Road - Soil cement & compaction 25 Jul '22
90 Temporary Road - Rain drainage gutter 26 d 03-07-22 31-07-22 34.6153846153846%
40% Temporary Road - Rain drainage gutter 31 Jul '22
91 Labour Camp 70 d 31-05-22 11-08-22 60% 47% Labour Camp 11 Aug '22

92 Labour Camp - Construction 60 d 31-05-22 01-08-22Labour


70%Camp
75%- Construction 01 Aug '22
93 Labour Camp - Temporary power supply 40 d 30-06-22 11-08-22 30% 35% Labour Camp - Temporary power supply 11 Aug '22
94 Lobour Camp - Temporary water supply 25 d 16-07-22 11-08-22 0% 0% Lobour Camp - Temporary water supply 11 Aug '22
95 M&E Temporary Work 45 d 16-06-22 02-08-22 57.7777777777778%
68% M&E Temporary Work 02 Aug '22

96 M&E Temporary Work - Power Supply 41 d 20-06-22 02-08-22 53.6585365853659%


53% M&E Temporary Work - Power Supply 02 Aug '22
97 M&E Temporary Work - Power Supply - PEA work 19 d 20-06-22 08-07-22 100% 87% M&E Temporary Work - Power Supply - PEA work 08 Jul '22
98 Temp. Power Supply - Transformer 500KVA installation 5d 20-06-22 24-06-22 100% 100% Temp. Power Supply - Transformer 500KVA installation 24 Jun '22
99 Temp. Power Supply - MDB 800AT installation 5d 23-06-22 27-06-22 100% 100% Temp. Power Supply - MDB 800AT installation 27 Jun '22
100 Temp. Power Supply - PEA inspection 5d 27-06-22 01-07-22 100% 100% Temp. Power Supply - PEA inspection 01 Jul '22
101 Temp.Power Supply - PEA Install PT,CT&KWH.meter 5d 30-06-22 04-07-22 100% 100% Temp.Power Supply - PEA Install PT,CT&KWH.meter 04 Jul '22
102 Temp.Power Supply - Connection 22KV Cable by PEA 3d 04-07-22 06-07-22 100% 60% Temp.Power Supply - Connection 22KV Cable by PEA 06 Jul '22
103 Temp. Power Supply - Electric Power on 2d 07-07-22 08-07-22 100% 0% Temp. Power Supply - Electric Power on 08 Jul '22
104 M&E Temporary Work - Outdoor lighting for construciton site area 20 d 11-07-22 02-08-22 5% 40% M&E Temporary Work - Outdoor lighting for construciton site area 02 Aug '22
105 M&E Temporary Work - Power supply to Office 5d 18-07-22 22-07-22 0% 0% M&E Temporary Work - Power supply to Office 22 Jul '22
106 M&E Temporary Work - Power supply to fabrication yard 4d 10-07-22 14-07-22 50% 20% M&E Temporary Work - Power supply to fabrication yard 14 Jul '22
107 M&E Temporary Work - Power supply to canteen/toilet 4d 14-07-22 17-07-22 0% 10% M&E Temporary Work - Power supply to canteen/toilet 17 Jul '22
108 M&E Temporary Work - CCTV & Install wiring 9d 05-07-22 14-07-22 77.7777777777778%
23% M&E Temporary Work - CCTV & Install wiring 14 Jul '22
109 M&E Temporary Work - CCTV & Install wiring - Power Supply to camera 6d 05-07-22 10-07-22 100% 35% M&E Temporary Work - CCTV & Install wiring - Power Supply to camera 10 Jul '22
110 M&E Temporary Work - CCTV & Install wiring - Testing signal 3d 11-07-22 14-07-22 33.3333333333333%
0% M&E Temporary Work - CCTV & Install wiring - Testing signal 14 Jul '22
111 M&E Temporary Work - Lightning protection work 20 d 01-07-22 21-07-22 55% 100% M&E Temporary Work - Lightning protection work 21 Jul '22
112 M&E Temporary Work - Internet & Lan 11 d 16-06-22 26-06-22 100% 100% M&E Temporary Work - Internet & Lan 26 Jun '22
113 M&E Temporary Work - Water supply and Drainage works 7d 28-06-22 04-07-22 100% 100% M&E Temporary Work - Water supply and Drainage works 04 Jul '22
114 Completion of Temporary Work 0d 11-08-22 11-08-22 0% 0% Completion of Temporary Work 11 Aug '22
115 Project Execution 338 d 08-06-22 01-06-23 9.76331360946746%
6% Project Execution

116 Received For Construction Drawing 0d 08-06-22 08-06-22 100% 100% Received For Construction Drawing 08 Jun '22

117 Received For Construction Drawing - Main Factory 0d 08-06-22 08-06-22 100% Received
100% For Construction Drawing - Main Factory 08 Jun '22

118 Received For Construction Drawing - Zone A 0d 08-06-22 08-06-22 100% 100%Received For Construction Drawing - Zone A 08 Jun '22
119 Received For Con. Drawings - Zone A - Structural work 0d 08-06-22 08-06-22 100% Received
100%For Con. Drawings - Zone A - Structural work 08 Jun '22
120 Received For Con. Drawings - Zone A - Str. Work - Foundation 0d 08-06-22 08-06-22Received
100%For100%
Con. Drawings - Zone A - Str. Work - Foundation 08 Jun '22
121 Received For Con. Drawings - Zone A - Str. Work - Under ground pipe 0d 08-06-22 Received For
08-06-22 Con. Drawings
100% 100% - Zone A - Str. Work - Under ground pipe 08 Jun '22
122 Received For Con. Drawings - Zone A - Str. Work - Level 1 PT Slab 0d 08-06-22 Received
08-06-22 For Con.
100% 100%Drawings - Zone A - Str. Work - Level 1 PT Slab 08 Jun '22
123 Received For Con. Drawings - Zone A - Str. Work - Level 2 PT Slab 0d 08-06-22 Received
08-06-22 For Con.
100% 100%Drawings - Zone A - Str. Work - Level 2 PT Slab 08 Jun '22
124 Received For Con. Drawings - Zone A - Str. Work - Roof steel Structure 0d 08-06-22 Received
08-06-22For100%
Con. Drawings
100% - Zone A - Str. Work - Roof steel Structure 08 Jun '22
125 Received For Con. Drawings - Zone A - Architectural work 0d 08-06-22 Received
08-06-22 100% For Con. Drawings - Zone A - Architectural work
100% 08 Jun '22
126 Received For Con. Drawings - Zone A - Ar. Work - Level 1 Plan 0d 08-06-22 08-06-22Received
100%For Con. Drawings - Zone A - Ar. Work - Level 1 Plan
100% 08 Jun '22
127 Received For Con. Drawings - Zone A - Ar. Work - Level 2 Plan 0d 08-06-22 08-06-22Received
100%For100%
Con. Drawings - Zone A - Ar. Work - Level 2 Plan 08 Jun '22
128 Received For Con. Drawings - Zone A - Ar. Work - Roof Metal Sheet 0d 08-06-22 Received 100%
08-06-22 For Con.100%
Drawings - Zone A - Ar. Work - Roof Metal Sheet 08 Jun '22
129 Received For Construction Drawing - Zone B 0d 08-06-22 08-06-22 100% 100%Received For Construction Drawing - Zone B 08 Jun '22
130 Received For Con. Drawings - Zone B - Structural work 0d 08-06-22 08-06-22 100% Received
100%For Con. Drawings - Zone B - Structural work 08 Jun '22
131 Received For Con. Drawings - Zone B - Str. Work - Foundation 0d 08-06-22 08-06-22Received
100%For100%
Con. Drawings - Zone B - Str. Work - Foundation 08 Jun '22
132 Received For Con. Drawings - Zone B - Str. Work - Level 1 PT Slab 0d 08-06-22 Received
08-06-22 For Con.
100% 100%Drawings - Zone B - Str. Work - Level 1 PT Slab 08 Jun '22
133 Received For Con. Drawings - Zone B - Str. Work - Level 2 PT Slab 0d 08-06-22 Received
08-06-22 For Con.
100% 100%Drawings - Zone B - Str. Work - Level 2 PT Slab 08 Jun '22
134 Received For Con. Drawings - Zone B - Str. Work - Roof 0d 08-06-22 08-06-22 100% Received
100% For Con. Drawings - Zone B - Str. Work - Roof 08 Jun '22
135 Received For Con. Drawings - Zone B - Str. Work - Under ground pipe 0d 08-06-22 Received For
08-06-22 Con. Drawings
100% 100% - Zone B - Str. Work - Under ground pipe 08 Jun '22
136 Received For Con. Drawings - Zone B - Architectural work 0d 08-06-22 Received
08-06-22 100% For Con. Drawings - Zone B - Architectural work
100% 08 Jun '22
137 Received For Con. Drawings - Zone B - Ar. Work - Level 1 Plan 0d 08-06-22 08-06-22Received
100%For Con. Drawings - Zone B - Ar. Work - Level 1 Plan
100% 08 Jun '22
138 Received For Con. Drawings - Zone B - Ar. Work - Level 2 Plan 0d 08-06-22 08-06-22Received
100%For Con. Drawings - Zone B - Ar. Work - Level 2 Plan
100% 08 Jun '22
139 Received For Con. Drawings - Zone B - Ar. Work - Roof Metal Sheet 0d 08-06-22 Received100%
08-06-22 For Con.100%
Drawings - Zone B - Ar. Work - Roof Metal Sheet 08 Jun '22
140 Received For Construction Drawing - Office and Canteen 0d 08-06-22 08-06-22 100%Received
100%For Construction Drawing - Office and Canteen 08 Jun '22

141 Received For Con. Drawings - Office and Canteen - Structural work 0d Received100%
08-06-22 08-06-22 For Con. Drawings - Office and Canteen - Structural work
100% 08 Jun '22
142 Received For Con. Drawings - Office and Canteen - Str. Work - Foundation 0d Received
08-06-22 For Con.
08-06-22 Drawings
100% 100% - Office and Canteen - Str. Work - Foundation 08 Jun '22
143 Received For Con. Drawings - Office and Canteen - Str. Work - Level 1 PT Slab 0d Received
08-06-22 For Con. Drawings
08-06-22 100% 100%- Office and Canteen - Str. Work - Level 1 PT Slab 08 Jun '22
144 Received For Con. Drawings - Office and Canteen - Str. Work - Level M PT Slab 0d Received08-06-22
08-06-22 For Con. Drawings - Office and Canteen - Str. Work - Level M PT Slab
100% 100% 08 Jun '22
145 Received For Con. Drawings - Office and Canteen - Str. Work - Level 2 PT Slab 0d Received
08-06-22 For Con. Drawings
08-06-22 100% 100%- Office and Canteen - Str. Work - Level 2 PT Slab 08 Jun '22
146 Received For Con. Drawings - Office and Canteen - Str. Work - Roof PT Slab 0d Received
08-06-22 For Con.100%
08-06-22 Drawings
100%- Office and Canteen - Str. Work - Roof PT Slab 08 Jun '22
147 Received For Con. Drawings - Office and Canteen - Str. Work - Under ground pipe 0d Received For
08-06-22 Con. Drawings
08-06-22 100%- Office
100%and Canteen - Str. Work - Under ground pipe 08 Jun '22
148 Received For Con. Drawings - Office and Canteen - Architectural work 0d Received For
08-06-22 08-06-22 Con. Drawings
100% 100% - Office and Canteen - Architectural work 08 Jun '22
149 Received For Con. Drawings - Office and Canteen - Ar. Work - Level 1 Plan 0d 08-06-22Received For Con.
08-06-22 Drawings
100% 100%- Office and Canteen - Ar. Work - Level 1 Plan 08 Jun '22
150 Received For Con. Drawings - Office and Canteen - Ar. Work - Level M Plan 0d Received
08-06-22 For Con.
08-06-22 Drawings
100% 100% - Office and Canteen - Ar. Work - Level M Plan 08 Jun '22
151 Received For Con. Drawings - Office and Canteen - Ar. Work - Level 2 Plan 0d 08-06-22Received For Con.
08-06-22 Drawings
100% 100% - Office and Canteen - Ar. Work - Level 2 Plan 08 Jun '22
152 Received For Con. Drawings - Office and Canteen - Ar. Work - Roof Plan 0d 08-06-22 Received
08-06-22 For Con.
100%Drawings
100% - Office and Canteen - Ar. Work - Roof Plan 08 Jun '22
153 Received For Con. Drawings - Office and Canteen - Façade work 0d 08-06-22 08-06-22 Received
100%For Con.
100% Drawings - Office and Canteen - Façade work 08 Jun '22
154 Received For Construction Drawing - East Utility Building 0d 08-06-22 08-06-22 100% Received For Construction Drawing - East Utility Building
100% 08 Jun '22

155 Received For Con. Drawings - East Utility Building - Structural work 0d Received 100%
08-06-22 08-06-22 For Con.100%
Drawings - East Utility Building - Structural work 08 Jun '22
156 Received For Con. Drawings - East Utility Building - Str. Work - Foundation 0d Received
08-06-22 For Con.
08-06-22 Drawings
100% 100% - East Utility Building - Str. Work - Foundation 08 Jun '22
157 Received For Con. Drawings - East Utility Building - Str. Work - Level 1 PT Slab 0d Received
08-06-22 For Con. Drawings
08-06-22 100% 100%- East Utility Building - Str. Work - Level 1 PT Slab 08 Jun '22
158 Received For Con. Drawings - East Utility Building - Str. Work - Roof PT Slab 0d Received
08-06-22 For Con.100%
08-06-22 Drawings - East Utility Building - Str. Work - Roof PT Slab
100% 08 Jun '22
159 Received For Con. Drawings - East Utility Building - Architectural work 0d 08-06-22 Received
08-06-22For100%
Con. Drawings
100% - East Utility Building - Architectural work 08 Jun '22
160 Received For Con. Drawings - East Utility Building - Ar. Work - Level 1 Plan 0d 08-06-22Received For Con.
08-06-22 Drawings
100% 100% - East Utility Building - Ar. Work - Level 1 Plan 08 Jun '22
161 Received For Con. Drawings - East Utility Building - Ar. Work - Roof (Aluminum trellis) 0d Received For Con.
08-06-22 Drawings100%
08-06-22 - East Utility
100%Building - Ar. Work - Roof (Aluminum trellis) 08 Jun '22
162 Received For Construction Drawing - South Utility Building 0d 08-06-22 08-06-22 Received
100% 100% For Construction Drawing - South Utility Building 08 Jun '22

163 Received For Con. Drawings - South Utility Building - Structural work 0d Received For
08-06-22 08-06-22 Con. Drawings
100% 100% - South Utility Building - Structural work 08 Jun '22
164 Received For Con. Drawings - South Utility Building - Str. Work - Foundation 0d Received
08-06-22 For Con. 100%
08-06-22 Drawings - South Utility Building - Str. Work - Foundation
100% 08 Jun '22
165 Received For Con. Drawings - South Utility Building - Str. Work - Level 1 PT Slab 0d Received 08-06-22
08-06-22 For Con. Drawings
100% - 100%
South Utility Building - Str. Work - Level 1 PT Slab 08 Jun '22
166 Received For Con. Drawings - South Utility Building - Str. Work - Level 2 PT Slab 0d Received For
08-06-22 Con. Drawings
08-06-22 100%- South
100%Utility Building - Str. Work - Level 2 PT Slab 08 Jun '22
167 Received For Con. Drawings - South Utility Building - Str. Work - Roof Steel Structure 0d Received For Con.
08-06-22 Drawings100%
08-06-22 - South100%
Utility Building - Str. Work - Roof Steel Structure 08 Jun '22
168 Received For Con. Drawings - South Utility Building - Str. Work - Water Tank 0d Received
08-06-22 For Con. Drawings
08-06-22 100% 100% - South Utility Building - Str. Work - Water Tank 08 Jun '22
169 Received For Con. Drawings - South Utility Building - Str. - RC.Stair, Link Bridge 0d Received For
08-06-22 Con. Drawings
08-06-22 100% - South
100%Utility Building - Str. - RC.Stair, Link Bridge 08 Jun '22
170 Received For Con. Drawings - South Utility Building - Str. Work - External Stl. Staircase 0d Received For Con.08-06-22
08-06-22 Drawings -100%
South Utility
100%Building - Str. Work - External Stl. Staircase 08 Jun '22
171 Received For Con. Drawings - South Utility Building - Architectural work 0d 08-06-22Received
08-06-22 For Con.
100% Drawings
100% - South Utility Building - Architectural work 08 Jun '22
172 Received For Con. Drawings - South Utility Building - Ar. Work - Level 1 Plan 0d Received
08-06-22 For Con.100%
08-06-22 Drawings - South Utility Building - Ar. Work - Level 1 Plan
100% 08 Jun '22

2 OF 16
PROJECT : Relief Project
MASTER SCHEDULE (REV0.01) Dated 11Jul22
ID Task Name Duration Start Finish Planned
% Complete
%
Complete Jun Jul Aug
30-05 06-06 13-06 20-06 27-06 04-07 11-07 18-07 25-07 01-08 08-08 15-08 22-08 29-08
173 Received For Con. Drawings - South Utility Building - Ar. Work - Level 2 Plan 0d Received
08-06-22 For Con. 100%
08-06-22 Drawings - South Utility Building - Ar. Work - Level 2 Plan
100% 08 Jun '22 11 Jul, '22
174 Received For Con. Drawings - South Utility Building - Ar. Work - Roof Metal Sheet 0d Received For
08-06-22 Con. Drawings
08-06-22 100%- South
100% Utility Building - Ar. Work - Roof Metal Sheet 08 Jun '22
175 Received For Construction Drawing - External Work 0d 08-06-22 08-06-22 100%Received 100% For Construction Drawing - External Work 08 Jun '22

176 Received For Construction Drawing - External Work - Retention pond 0d Received For
08-06-22 08-06-22 Construction
100% 100% Drawing - External Work - Retention pond 08 Jun '22

177 Received For Construction Drawing - External Work - Boundary fence & Main entrance 0d Received For Construction
08-06-22 08-06-22 Drawing
100% -100%
External Work - Boundary fence & Main entrance 08 Jun '22

178 Received For Construction Drawing - External Work - Stormwater drainage system 0d Received
08-06-22For08-06-22
Construction Drawing
100% 100%- External Work - Stormwater drainage system 08 Jun '22

179 Received For Construction Drawing - External Work - Guardhouse & Custrm office 0d Received For
08-06-22 Construction
08-06-22 Drawing
100% 100%- External Work - Guardhouse & Custrm office 08 Jun '22
180 Received For Construction Drawing - External Work - Road & Pavement, Loading dock, Truck Received
0 d For Construction
08-06-22 Drawing
08-06-22- External
100%Work - Road & Pavement, Loading dock, Truck scale
100% 08 Jun '22
scale
181 Received For Construction Drawing - External Work - Car & Motorcycle parking (Southside) 0 d Received08-06-22
For Construction Drawing
08-06-22 - External
100% 100%Work - Car & Motorcycle parking (Southside) 08 Jun '22
182 Received For Construction Drawing - External Work - VIP & Visitor parking (Northside) 0d Received For Construction
08-06-22 08-06-22 Drawing
100% -100%External Work - VIP & Visitor parking (Northside) 08 Jun '22
183 Received For Construction Drawing - External Work - Green area & Landscape 0d Received
08-06-22 For Construction
08-06-22 100% Drawing
100% - External Work - Green area & Landscape 08 Jun '22
184 Received For Construction Drawing - External Work - Truck Scale 0d 08-06-22 08-06-22Received For Construction
100% 100% Drawing - External Work - Truck Scale 08 Jun '22
185 Received For Construction Drawing - External Work - Link Bridge 0d 08-06-22 08-06-22Received For Construction
100% 100% Drawing - External Work - Link Bridge 08 Jun '22
186 Received For Construction Drawing - External Work - Walk Way 0d 08-06-22 08-06-22 Received
100% For 100%
Construction Drawing - External Work - Walk Way 08 Jun '22
187 Received For Construction Drawing - External Work - Pipe Rack 0d 08-06-22 08-06-22 Received
100% For 100%
Construction Drawing - External Work - Pipe Rack 08 Jun '22
188 Received For Construction Drawing - External Work - Main entrance 0d Received For
08-06-22 08-06-22 100%Construction
100% Drawing - External Work - Main entrance 08 Jun '22
189 Submission&Approval - Shop Drawing 210 d 19% Submission&Approval - Shop Drawing
09-06-2215-01-2315.7142857142857%
190 Submission&Approval - Shop Drawing - Structural work 115 d Submission&Approval
09-06-2205-10-2228.695652173913%
35% - Shop Drawing - Structural work

191 Submission&Approval - Shop Drawing Str. - Main Factory 100 d Submission&Approval


09-06-2220-09-2233% 41% - Shop Drawing Str. - Main Factory

192 Submission&Approval - Shop Drawing Str. - Zone A 100 d 09-06-22 20-09-22 33% Submission&Approval
40% - Shop Drawing Str. - Zone A
193 Submission&Approval - Shop Drawing Str. - Zone A - Pile Cut Off 6d 09-06-22 Submission&Approval
14-06-22 100% 100% - Shop Drawing Str. - Zone A - Pile Cut Off 14 Jun '22
194 Zone A - Pile Cut Off - Preparation & Submission 3d 09-06-22 11-06-22 100% 100% Zone A - Pile Cut Off - Preparation & Submission 11 Jun '22
195 Zone A - Pile Cut Off - Review & Approval by Consultant 3d 12-06-22 14-06-22 100% 100%Zone A - Pile Cut Off - Review & Approval by Consultant 14 Jun '22
196 Submission&Approval - Shop Drawing Str. - Zone A - Foundation & Ground beam 23 d 16-06-22 Submission&Approval
08-07-22 100% 100% - Shop Drawing Str. - Zone A - Foundation & Ground beam 08 Jul '22
197 Zone A - Foundation - 1st Preparation & Submission 7d 16-06-22 22-06-22 100% 100% Zone A - Foundation - 1st Preparation & Submission 22 Jun '22
198 Zone A - Foundation - 1st Review & Approval by Consultant 3d 23-06-22 25-06-22 100% 100% Zone A - Foundation - 1st Review & Approval by Consultant 25 Jun '22
199 Zone A - Gr. beam - 1st Preparation & Submission 10 d 26-06-22 05-07-22 100% 100% Zone A - Gr. beam - 1st Preparation & Submission 05 Jul '22
200 Zone A - Gr. Beam - 1st Review & Approval by Consultant 3d 06-07-22 08-07-22 100% 100% Zone A - Gr. Beam - 1st Review & Approval by Consultant 08 Jul '22
201 Submission&Approval - Shop Drawing Str. - Zone A - Pca. Column 15 d 01-07-22 16-07-22 73.3333333333333%
83% Submission&Approval - Shop Drawing Str. - Zone A - Pca. Column 16 Jul '22
202 Zone A1 - Pca. Column - 1st Preparation & Submission 8d 01-07-22 08-07-22 100% 100% Zone A1 - Pca. Column - 1st Preparation & Submission 08 Jul '22
203 Zone A1 - Pca. Column - 1st Review & Approval by Consultant 2d 09-07-22 10-07-22 100% 75% Zone A1 - Pca. Column - 1st Review & Approval by Consultant 10 Jul '22
204 Zone A2 - Pca. Column - 1st Preparation & Submission 7d 04-07-22 10-07-22 100% 100% Zone A2 - Pca. Column - 1st Preparation & Submission 10 Jul '22
205 Zone A2 - Pca. Column - 1st Review & Approval by Consultant 2d 11-07-22 12-07-22 50% 75% Zone A2 - Pca. Column - 1st Review & Approval by Consultant 12 Jul '22
206 Zone A3 - Pca. Column - 1st Preparation & Submission 7d 07-07-22 14-07-22 71.4285714285714%
75% Zone A3 - Pca. Column - 1st Preparation & Submission 14 Jul '22
207 Zone A3 - Pca. Column - 1st Review & Approval by Consultant 2d 15-07-22 16-07-22 0% 0% Zone A3 - Pca. Column - 1st Review & Approval by Consultant 16 Jul '22
208 Submission&Approval - Shop Drawing Str. - Zone A - Core Wall Details 10 d 04-07-22 14-07-22 80% 72% Submission&Approval - Shop Drawing Str. - Zone A - Core Wall Details 14 Jul '22
209 Zone A - Core Wall Details - 1st Preparation & Submission 8d 04-07-22 11-07-22 100% 90% Zone A - Core Wall Details - 1st Preparation & Submission 11 Jul '22
210 Zone A - Core Wall Details-1st Review & Approval by Consultant 2d 12-07-22 14-07-22 0% 0% Zone A - Core Wall Details-1st Review & Approval by Consultant 14 Jul '22
211 Submission&Approval - Shop Drawing Str. - Zone A - Roof Steel Structure 14 d 08-07-22 22-07-22 28.5714285714286%
36% Submission&Approval - Shop Drawing Str. - Zone A - Roof Steel Structure 22 Jul '22
212 Zone A - Roof - 1st Preparation & Submission 10 d 08-07-22 18-07-22 40% 50% Zone A - Roof - 1st Preparation & Submission 18 Jul '22
213 Zone A - Roof - 1st Review & Approval by Consultant 4d 19-07-22 22-07-22 0% 0% Zone A - Roof - 1st Review & Approval by Consultant 22 Jul '22
214 Submission&Approval - Shop Drawing Str. - Zone A - Under ground pipe 24 d 30-07-22 23-08-22 0% 0% Submission&Approval - Shop Drawing Str. - Zone A - Under ground pipe 23 Aug '22
215 Zone A - Under ground pipe - 1st Preparation & Submission 6d 30-07-22 04-08-22 0% 0% Zone A - Under ground pipe - 1st Preparation & Submission 04 Aug '22
216 Zone A - Under ground pipe - 1st Review & Approval by Consultant 6d 05-08-22 10-08-22 0% 0% Zone A - Under ground pipe - 1st Review & Approval by Consultant 10 Aug '22
217 Zone A - Under ground pipe - 2nd Preparation & Submission 6d 11-08-22 17-08-22 0% 0% Zone A - Under ground pipe - 2nd Preparation & Submission 17 Aug '22
218 Zone A - Under ground pipe - 2nd Review & Approval by Consultant 6d 18-08-22 23-08-22 0% 0% Zone A - Under ground pipe - 2nd Review & Approval by Consultant 23 Aug '22
219 Submission&Approval - Shop Drawing Str. - Zone A - Level 1 PT Slab 28 d 10-08-22 07-09-22 0% 0% Submission&Approval - Shop Drawing Str. - Zone A - Level 1 PT Slab
220 Zone A - Level 1 - 1st Preparation & Submission 7d 10-08-22 17-08-22 0% 0% Zone A - Level 1 - 1st Preparation & Submission 17 Aug '22
221 Zone A - Level 1 - 1st Review & Approval by Consultant 7d 18-08-22 24-08-22 0% 0% Zone A - Level 1 - 1st Review & Approval by Consultant 24 Aug '22
222 Zone A - Level 1 - 2nd Preparation & Submission 7d 25-08-22 31-08-22 0% 0% Zone A - Level 1 - 2nd Preparation & Submission 31 Aug '22
223 Zone A - Level 1 - 2nd Review & Approval by Consultant 7d 01-09-22 07-09-22 0% 0% Zone A - Level 1 - 2nd Review & Approval by Consultant
224 Submission&Approval - Shop Drawing Str. - Zone A - Level 2 PT Slab 28 d 24-08-22 20-09-22 0% 0% Submission&Approval - Shop Drawing Str. - Zone A - Level 2 PT Slab
225 Zone A - Level 2 - 1st Preparation & Submission 7d 24-08-22 30-08-22 0% 0% Zone A - Level 2 - 1st Preparation & Submission 30 Aug '22
226 Zone A - Level 2 - 1st Review & Approval by Consultant 7d 31-08-22 06-09-22 0% 0% Zone A - Level 2 - 1st Review & Approval by Consultant
227 Zone A - Level 2 - 2nd Preparation & Submission 7d 07-09-22 13-09-22 0% 0% Zone A - Level 2 - 2nd Preparation & Submi
228 Zone A - Level 2 - 2nd Review & Approval by Consultant 7d 14-09-22 20-09-22 0% 0% Zone A - Level 2 - 2nd Re
229 Submission&Approval - Shop Drawing Str. - Zone B 94 d 09-06-22 Submission&Approval
14-09-22 35.1063829787234%
41% - Shop Drawing Str. - Zone B
230 Submission&Approval - Shop Drawing Str. - Zone B - Pile Cut off 9d 09-06-22 Submission&Approval
17-06-22 100% 100% - Shop Drawing Str. - Zone B - Pile Cut off 17 Jun '22
231 Zone B - Pile Cut Off - Preparation & Submission 4d 09-06-22 12-06-22 100% 100% Zone B - Pile Cut Off - Preparation & Submission 12 Jun '22
232 Zone B - Pile Cut Off - Review & Approval by Consultant 5d 13-06-22 17-06-22 100% 100% Zone B - Pile Cut Off - Review & Approval by Consultant 17 Jun '22
233 Submission&Approval - Shop Drawing Str. - Zone B - Foundation & Ground beam 23 d 16-06-22 08-07-22 100%Submission&Approval
97% - Shop Drawing Str. - Zone B - Foundation & Ground beam 08 Jul '22
234 Zone B - Foundation - Preparation & Submission 7d 16-06-22 22-06-22 100% 100% Zone B - Foundation - Preparation & Submission 22 Jun '22
235 Zone B - Foundation - Review & Approval by Consultant 3d 23-06-22 25-06-22 100% 100% Zone B - Foundation - Review & Approval by Consultant 25 Jun '22
236 Zone B - Gr. Beam - Preparation & Submission 10 d 26-06-22 05-07-22 100% 100% Zone B - Gr. Beam - Preparation & Submission 05 Jul '22
237 Zone B - Gr. Beam - Review & Approval by Consultant 3d 06-07-22 08-07-22 100% 75% Zone B - Gr. Beam - Review & Approval by Consultant 08 Jul '22
238 Submission&Approval - Shop Drawing Str. - Zone B - Pca. Column 18 d 01-07-22 19-07-22 61.1111111111111%
72% Submission&Approval - Shop Drawing Str. - Zone B - Pca. Column 19 Jul '22
239 Zone B1 - Pca. Column - 1st Preparation & Submission 8d 01-07-22 08-07-22 100% 100% Zone B1 - Pca. Column - 1st Preparation & Submission 08 Jul '22
240 Zone B1 - Pca. Column - 1st Review & Approval by Consultant 2d 09-07-22 10-07-22 100% 75% Zone B1 - Pca. Column - 1st Review & Approval by Consultant 10 Jul '22
241 Zone B2 - Pca. Column - 1st Preparation & Submission 7d 04-07-22 10-07-22 100% 100% Zone B2 - Pca. Column - 1st Preparation & Submission 10 Jul '22
242 Zone B2 - Pca. Column - 1st Review & Approval by Consultant 2d 11-07-22 12-07-22 50% 75% Zone B2 - Pca. Column - 1st Review & Approval by Consultant 12 Jul '22
243 Zone B3 - Pca. Column - 1st Preparation & Submission 7d 07-07-22 14-07-22 71.4285714285714%
75% Zone B3 - Pca. Column - 1st Preparation & Submission 14 Jul '22
244 Zone B3 - Pca. Column - 1st Review & Approval by Consultant 2d 15-07-22 16-07-22 0% 0% Zone B3 - Pca. Column - 1st Review & Approval by Consultant 16 Jul '22
245 Zone B4 - Pca. Column - 1st Preparation & Submission 7d 10-07-22 17-07-22 28.5714285714286%
50% Zone B4 - Pca. Column - 1st Preparation & Submission 17 Jul '22
246 Zone B4 - Pca. Column - 1st Review & Approval by Consultant 2d 18-07-22 19-07-22 0% 0% Zone B4 - Pca. Column - 1st Review & Approval by Consultant 19 Jul '22
247 Submission&Approval - Shop Drawing Str. - Zone B - Core Wall Details 10 d 04-07-22 14-07-22 80% 60% Submission&Approval - Shop Drawing Str. - Zone B - Core Wall Details 14 Jul '22
248 Zone B - Core Wall Details - 1st Preparation & Submission 8d 04-07-22 11-07-22 100% 75% Zone B - Core Wall Details - 1st Preparation & Submission 11 Jul '22
249 Zone B - Core Wall Details - 1st Review & Approval by Consultant 2d 12-07-22 14-07-22 0% 0% Zone B - Core Wall Details - 1st Review & Approval by Consultant 14 Jul '22
250 Submission&Approval - Shop Drawing Str. - Zone B - Roof Steel Structure 14 d 01-07-22 15-07-22 78.5714285714286%
64% Submission&Approval - Shop Drawing Str. - Zone B - Roof Steel Structure 15 Jul '22
251 Zone B - Roof - 1st Preparation & Submission 10 d 01-07-22 10-07-22 100% 90% Zone B - Roof - 1st Preparation & Submission 10 Jul '22
252 Zone B - Roof - 1st Review & Approval by Consultant 4d 11-07-22 15-07-22 25% 0% Zone B - Roof - 1st Review & Approval by Consultant 15 Jul '22
253 Submission&Approval - Shop Drawing Str. - Zone B - Under ground pipe 28 d 24-07-22 23-08-22 0% 0% Submission&Approval - Shop Drawing Str. - Zone B - Under ground pipe 23 Aug '22
254 Zone B - Under ground pipe - 1st Preparation & Submission 7d 24-07-22 01-08-22 0% 0% Zone B - Under ground pipe - 1st Preparation & Submission 01 Aug '22
255 Zone B - Under ground pipe - 1st Review & Approval by Consultant 7d 02-08-22 08-08-22 0% 0% Zone B - Under ground pipe - 1st Review & Approval by Consultant 08 Aug '22

256 Zone B - Under ground pipe - 2nd Preparation & Submission 7d 09-08-22 16-08-22 0% 0% Zone B - Under ground pipe - 2nd Preparation & Submission 16 Aug '22
257 Zone B - Under ground pipe - 2nd Review & Approval by Consultant 7d 17-08-22 23-08-22 0% 0% Zone B - Under ground pipe - 2nd Review & Approval by Consultant 23 Aug '22
258 Submission&Approval - Shop Drawing Str. - Zone B - Level 1 PT Slab 28 d 04-08-22 01-09-22 0% 0% Submission&Approval - Shop Drawing Str. - Zone B - Level 1 PT Slab 01 Sep '22
259 Zone B - Level 1 - 1st Preparation & Submission 7d 04-08-22 10-08-22 0% 0% Zone B - Level 1 - 1st Preparation & Submission 10 Aug '22
260 Zone B - Level 1 - 1st Review & Approval by Consultant 7d 11-08-22 18-08-22 0% 0% Zone B - Level 1 - 1st Review & Approval by Consultant 18 Aug '22
261 Zone B - Level 1 - 2nd Preparation & Submission 7d 19-08-22 25-08-22 0% 0% Zone B - Level 1 - 2nd Preparation & Submission 25 Aug '22

3 OF 16
PROJECT : Relief Project
MASTER SCHEDULE (REV0.01) Dated 11Jul22
ID Task Name Duration Start Finish Planned
% Complete
%
Complete Jun Jul Aug
30-05 06-06 13-06 20-06 27-06 04-07 11-07 18-07 25-07 01-08 08-08 15-08 22-08 29-08
262 Zone B - Level 1 - 2nd Review & Approval by Consultant 7d 26-08-22 01-09-22
0% 0% 11 Jul, '22 Zone B - Level 1 - 2nd Review & Approval by Consultant 01 Sep '22
263 Submission&Approval - Shop Drawing Str. - Zone B - Level 2 PT Slab 28 d 18-08-22 14-09-22
0% 0% Submission&Approval - Shop Drawing Str. - Zone B - Level 2 PT Slab
264 Zone B - Level 2 - 1st Preparation & Submission 7d 18-08-22 24-08-22
0% 0% Zone B - Level 2 - 1st Preparation & Submission 24 Aug '22
265 Zone B - Level 2 - 1st Review & Approval by Consultant 7d 25-08-22 31-08-22
0% 0% Zone B - Level 2 - 1st Review & Approval by Consultant 31 Aug '22
266 Zone B - Level 2 - 2nd Preparation & Submission 7d 01-09-22 07-09-22
0% 0% Zone B - Level 2 - 2nd Preparation & Submission
267 Zone B - Level 2 - 2nd Review & Approval by Consultant 7d 08-09-22 14-09-22
0% 0% Zone B - Level 2 - 2nd Review & Approval by Co
268 Submission&Approval - Shop Drawing Str. - Office and Canteen 115 d Submission&Approval
09-06-2205-10-22 22% - Shop Drawing Str. - Office and Canteen
28.695652173913%
269 Submission&Approval - Shop Drawing Str. - Office and Canteen - Pile Cut Off 6d Submission&Approval
09-06-22 14-06-22 100% - Shop Drawing Str. - Office and Canteen - Pile Cut Off
100% 14 Jun '22
270 Office and Canteen - Pile Cut Off - Preparation & Submission 3d 09-06-22 11-06-22 Office
100%and100%
Canteen - Pile Cut Off - Preparation & Submission 11 Jun '22
271 Office and Canteen - Pile Cut Off - Review & Approval by Consultant 3d 12-06-22 14-06-22 100%Office100%
and Canteen - Pile Cut Off - Review & Approval by Consultant 14 Jun '22
272 Submission&Approval - Shop Drawing Str. - Office and Canteen - Foundation & Ground beam
23 d Submission&Approval
16-06-22 08-07-22 100% 97% - Shop Drawing Str. - Office and Canteen - Foundation & Ground beam 08 Jul '22
273 Office and Canteen - Foundation - Preparation & Submission 7d 16-06-22 22-06-22 100% 100% Office and Canteen - Foundation - Preparation & Submission 22 Jun '22
274 Office and Canteen - Foundation - Review & Approval by Consultant 3d 23-06-22 25-06-22 100% 100% Office and Canteen - Foundation - Review & Approval by Consultant 25 Jun '22
275 Office and Canteen - Gr. Beam - Preparation & Submission 10 d 26-06-22 05-07-22 100% 100% Office and Canteen - Gr. Beam - Preparation & Submission 05 Jul '22
276 Office and Canteen - Gr. Beam - Review & Approval by Consultant 3d 06-07-22 08-07-22 100% 75% Office and Canteen - Gr. Beam - Review & Approval by Consultant 08 Jul '22
277 Submission&Approval - Shop Drawing Str. - Office and Canteen - Pca. Column 10 d 01-07-22 10-07-22 100% 72% Submission&Approval - Shop Drawing Str. - Office and Canteen - Pca. Column 10 Jul '22
278 Office and Canteen - Pca. Column - 1st Preparation & Submission 8d 01-07-22 08-07-22 100% 90% Office and Canteen - Pca. Column - 1st Preparation & Submission 08 Jul '22
279 Office and Canteen - Pca. Column - 1st Review & Approval by Consultant 2d 09-07-22 10-07-22 100% 0% Office and Canteen - Pca. Column - 1st Review & Approval by Consultant 10 Jul '22
280 Submission&Approval - Shop Drawing Str. - Office and Canteen - Core Wall Details 5d 10-07-22 15-07-22 40% 42% Submission&Approval - Shop Drawing Str. - Office and Canteen - Core Wall Details 15 Jul '22
281 Office and Canteen - Core Wall Details - 1st Preparation & Submission 3d 10-07-22 12-07-22 66.6666666666667%
70% Office and Canteen - Core Wall Details - 1st Preparation & Submission 12 Jul '22
282 Office and Canteen - Core Wall Details - 1st Review & Approval by Consultant 2d 14-07-22 15-07-22 0% 0% Office and Canteen - Core Wall Details - 1st Review & Approval by Consultant 15 Jul '22
283 Submission&Approval - Shop Drawing Str. - Office and Canteen - Under ground pipe 21 d 07-07-22 30-07-22 23.8095238095238%
25% Submission&Approval - Shop Drawing Str. - Office and Canteen - Under ground pipe 30 Jul '22
284 Office and Canteen - Under ground pipe - 1st Preparation & Submission 7d 07-07-22 14-07-22 71.4285714285714%
75% Office and Canteen - Under ground pipe - 1st Preparation & Submission 14 Jul '22
285 Office and Canteen - Under ground pipe - 1st Review & Approval by Consultant 7d 15-07-22 21-07-22 0% 0% Office and Canteen - Under ground pipe - 1st Review & Approval by Consultant 21 Jul '22
286 Office and Canteen - Under ground pipe - 2nd Preparation & Submission 4d 22-07-22 25-07-22 0% 0% Office and Canteen - Under ground pipe - 2nd Preparation & Submission 25 Jul '22
287 Office and Canteen - Under ground pipe - 2nd Review & Approval by Consultant 3d 26-07-22 30-07-22 0% 0% Office and Canteen - Under ground pipe - 2nd Review & Approval by Consultant 30 Jul '22
288 Submission&Approval - Shop Drawing Str. - Office and Canteen - Level 1 PT Slab 14 d 22-07-22 06-08-22 0% 0% Submission&Approval - Shop Drawing Str. - Office and Canteen - Level 1 PT Slab 06 Aug '22
289 Office and Canteen - Level 1 - 1st Preparation & Submission 7d 22-07-22 30-07-22 0% 0% Office and Canteen - Level 1 - 1st Preparation & Submission 30 Jul '22
290 Office and Canteen - Level 1 - 1st Review & Approval by Consultant 7d 31-07-22 06-08-22 0% 0% Office and Canteen - Level 1 - 1st Review & Approval by Consultant 06 Aug '22
291 Submission&Approval - Shop Drawing Str. - Office and Canteen - Level M PT Slab 28 d 21-07-22 20-08-22 0% 0% Submission&Approval - Shop Drawing Str. - Office and Canteen - Level M PT Slab 20 Aug '22
292 Office and Canteen - Level M - 1st Preparation & Submission 7d 21-07-22 27-07-22 0% 0% Office and Canteen - Level M - 1st Preparation & Submission 27 Jul '22
293 Office and Canteen - Level M - 1st Review & Approval by Consultant 7d 30-07-22 05-08-22 0% 0% Office and Canteen - Level M - 1st Review & Approval by Consultant 05 Aug '22
294 Office and Canteen - Level M - 2nd Preparation & Submission 7d 06-08-22 13-08-22 0% 0% Office and Canteen - Level M - 2nd Preparation & Submission 13 Aug '22
295 Office and Canteen - Level M - 2nd Review & Approval by Consultant 7d 14-08-22 20-08-22 0% 0% Office and Canteen - Level M - 2nd Review & Approval by Consultant 20 Aug '22
296 Submission&Approval - Shop Drawing Str. - Office and Canteen - Level 2 PT Slab 28 d 04-08-22 01-09-22 0% 0% Submission&Approval - Shop Drawing Str. - Office and Canteen - Level 2 PT Slab 01 Sep '22
297 Office and Canteen - Level 2 - 1st Preparation & Submission 7d 04-08-22 10-08-22 0% 0% Office and Canteen - Level 2 - 1st Preparation & Submission 10 Aug '22
298 Office and Canteen - Level 2 - 1st Review & Approval by Consultant 7d 11-08-22 18-08-22 0% 0% Office and Canteen - Level 2 - 1st Review & Approval by Consultant 18 Aug '22

299 Office and Canteen - Level 2 - 2nd Preparation & Submission 7d 19-08-22 25-08-22
0% 0% Office and Canteen - Level 2 - 2nd Preparation & Submission 25 Aug '22
300 Office and Canteen - Level 2 - 2nd Review & Approval by Consultant 7d 26-08-22 01-09-22
0% 0% Office and Canteen - Level 2 - 2nd Review & Approval by Consultant 01 Sep '22
301 Submission&Approval - Shop Drawing Str. - Office and Canteen - Roof PT slab 28 d 18-08-22 14-09-22
0% 0% Submission&Approval - Shop Drawing Str. - Office and Canteen - Roof PT slab
302 Office and Canteen - Roof - 1st Preparation & Submission 7d 18-08-22 24-08-22
0% 0% Office and Canteen - Roof - 1st Preparation & Submission 24 Aug '22
303 Office and Canteen - Roof - 1st Review & Approval by Consultant 7d 25-08-22 31-08-22
0% 0% Office and Canteen - Roof - 1st Review & Approval by Consultant 31 Aug '22
304 Office and Canteen - Roof - 2nd Preparation & Submission 7d 01-09-22 07-09-22
0% 0% Office and Canteen - Roof - 2nd Preparation & Submission
305 Office and Canteen - Roof - 2nd Review & Approval by Consultant 7d 08-09-22 14-09-22
0% 0% Office and Canteen - Roof - 2nd Review & Approval by Co
306 Submission&Approval - Shop Drawing Str. - Office and Canteen - Top Roof PT Slab 28 d 08-09-22 05-10-22
0% 0% Submission&Approval - Shop Drawing Str. - Office and Canteen - Top Roof
307 Office and Canteen - Top Roof - 1st Preparation & Submission 7d 08-09-22 14-09-22
0% 0% Office and Canteen - Top Roof - 1st Preparation & Sub
308 Office and Canteen - Top Roof - 1st Review & Approval by Consultant 7d 15-09-22 21-09-22
0% 0% Office and Canteen - Top Roof - 1s
309 Office and Canteen - Top Roof- 2nd Preparation & Submission 7d 22-09-22 28-09-22
0% 0% O
310 Office and Canteen - Top Roof- 2nd Review & Approval by Consultant 7d 29-09-22 05-10-22
0% 0%
311 Submission&Approval - Shop Drawing Str. - East Utility Building 68 d Submission&Approval
09-06-2219-08-22 40% - Shop Drawing Str. - East Utility Building
48.5294117647059% 19 Aug '22

312 Submission&Approval - Shop Drawing Str. - East Utility Building - Pile Cut Off 10 d Submission&Approval
09-06-22 18-06-22 100% - Shop Drawing Str. - East Utility Building - Pile Cut Off
100% 18 Jun '22
313 East Utility Building - Pile Cut Off - Preparation & Submission 5d 09-06-22 13-06-22East Utility100%
100% Building - Pile Cut Off - Preparation & Submission 13 Jun '22
314 East Utility Building - Pile Cut Off - Review & Approval by Consultant 5d 14-06-22 18-06-22 100% 100% East Utility Building - Pile Cut Off - Review & Approval by Consultant 18 Jun '22
315 Submission&Approval - Shop Drawing Str. - East Utility Building - Foundation & Ground 23 d Submission&Approval
16-06-22 08-07-22 100% 87%- Shop Drawing Str. - East Utility Building - Foundation & Ground beam 08 Jul '22
beam
316 East Utility Building - Foundation - Preparation & Submission 7d 16-06-22 22-06-22 100% 100% East Utility Building - Foundation - Preparation & Submission 22 Jun '22
317 East Utility Building - Foundation - Review & Approval by Consultant 3d 23-06-22 25-06-22 100% 100% East Utility Building - Foundation - Review & Approval by Consultant 25 Jun '22
318 East Utility Building - Gr. Beam - Preparation & Submission 10 d 26-06-22 05-07-22 100% 100% East Utility Building - Gr. Beam - Preparation & Submission 05 Jul '22
319 East Utility Building - Gr. Beam - Review & Approval by Consultant 3d 06-07-22 08-07-22 100% 0% East Utility Building - Gr. Beam - Review & Approval by Consultant 08 Jul '22
320 Submission&Approval - Shop Drawing Str. - East Utility Building - Pca. Column 10 d 01-07-22 10-07-22 100% 72% Submission&Approval - Shop Drawing Str. - East Utility Building - Pca. Column 10 Jul '22

321 East Utility Building - Pca. Column - 1st Preparation & Submission 8d 01-07-22 08-07-22
100% 90% East Utility Building - Pca. Column - 1st Preparation & Submission 08 Jul '22
322 East Utility Building - Pca. Column - 1st Review & Approval by Consultant 2d 09-07-22 10-07-22
100% 0% East Utility Building - Pca. Column - 1st Review & Approval by Consultant 10 Jul '22
323 Submission&Approval - Shop Drawing Str. - East Utility Building - Level 1 PT Slab 21 d 14-07-22 05-08-22
0% 0% Submission&Approval - Shop Drawing Str. - East Utility Building - Level 1 PT Slab 05 Aug '22
324 East Utility Building - Level 1 - 1st Preparation & Submission 7d 14-07-22 20-07-22
0% 0% East Utility Building - Level 1 - 1st Preparation & Submission 20 Jul '22
325 East Utility Building - Level 1 - 1st Review & Approval by Consultant 7d 21-07-22 27-07-22
0% 0% East Utility Building - Level 1 - 1st Review & Approval by Consultant 27 Jul '22
326 East Utility Building - Level 1 - 2nd Preparation & Submission 4d 30-07-22 02-08-22
0% 0% East Utility Building - Level 1 - 2nd Preparation & Submission 02 Aug '22
327 East Utility Building - Level 1 - 2nd Review & Approval by Consultant 3d 03-08-22 05-08-22
0% 0% East Utility Building - Level 1 - 2nd Review & Approval by Consultant 05 Aug '22
328 Submission&Approval - Shop Drawing Str. - East Utility Building- Roof PT Slab 28 d 20-07-22 19-08-22
0% 0% Submission&Approval - Shop Drawing Str. - East Utility Building- Roof PT Slab 19 Aug '22
329 East Utility Building - Roof - 1st Preparation & Submission 7d 20-07-22 26-07-22
0% 0% East Utility Building - Roof - 1st Preparation & Submission 26 Jul '22
330 East Utility Building - Roof - 1st Review & Approval by Consultant 7d 27-07-22 04-08-22
0% 0% East Utility Building - Roof - 1st Review & Approval by Consultant 04 Aug '22
331 East Utility Building - Roof - 2nd Preparation & Submission 7d 05-08-22 11-08-22
0% 0% East Utility Building - Roof - 2nd Preparation & Submission 11 Aug '22
332 East Utility Building - Roof - 2nd Review & Approval by Consultant 7d 13-08-22 19-08-22
0% 0% East Utility Building - Roof - 2nd Review & Approval by Consultant 19 Aug '22
333 Submission&Approval - Shop Drawing Str. - South Utility Building 101 d Submission&Approval
09-06-2221-09-22 37% - Shop Drawing Str. - South Utility Building
32.6732673267327%
334 Submission&Approval - Shop Drawing Str. - South Utility Building - Pile Cut Off 10 d Submission&Approval
09-06-22 - Shop100%
18-06-22 100% Drawing Str. - South Utility Building - Pile Cut Off 18 Jun '22
335 South Utility Building - Pile Cut Off - Preparation & Submission 5d South
09-06-22 13-06-22 Utility100%
100% Building - Pile Cut Off - Preparation & Submission 13 Jun '22
336 South Utility Building - Pile Cut Off - Review & Approval by Consultant 5d 14-06-22 18-06-22 100% South 100%Utility Building - Pile Cut Off - Review & Approval by Consultant 18 Jun '22
337 Submission&Approval - Shop Drawing Str. - South Utility Building - Foundation & 24 d Submission&Approval
16-06-22 09-07-22 100% 100% - Shop Drawing Str. - South Utility Building - Foundation & Ground beam 09 Jul '22
Ground beam
338 South Utility Building - Foundation - Preparation & Submission 7d 16-06-22 22-06-22 100% 100% South Utility Building - Foundation - Preparation & Submission 22 Jun '22
339 South Utility Building - Foundation - Review & Approval by Consultant 3d 23-06-22 25-06-22 100% 100% South Utility Building - Foundation - Review & Approval by Consultant 25 Jun '22
340 South Utility Building - Gr. beam - Preparation & Submission 7d 30-06-22 06-07-22 100% 100% South Utility Building - Gr. beam - Preparation & Submission 06 Jul '22
341 South Utility Building - Gr. Beam - Review & Approval by Consultant 3d 07-07-22 09-07-22 100% 100% South Utility Building - Gr. Beam - Review & Approval by Consultant 09 Jul '22
342 Submission&Approval - Shop Drawing Str. - South Utility Building - Water Tank 21 d 21-06-22 11-07-22 100% 96% Submission&Approval - Shop Drawing Str. - South Utility Building - Water Tank 11 Jul '22
343 South Utility Building - Water Tank- 1st Preparation & Submission 18 d 21-06-22 08-07-22 100% 100% South Utility Building - Water Tank- 1st Preparation & Submission 08 Jul '22
344 South Utility Building - Water Tank - 1st Review & Approval by Consultant 3d 09-07-22 11-07-22 100% 75% South Utility Building - Water Tank - 1st Review & Approval by Consultant 11 Jul '22
345 Submission&Approval - Shop Drawing Str. - South Utility Building - Pca. Column 10 d 01-07-22 10-07-22 100% 72% Submission&Approval - Shop Drawing Str. - South Utility Building - Pca. Column 10 Jul '22
346 South Utility Building - Pca. Column - 1st Preparation & Submission 8d 01-07-22 08-07-22 100% 90% South Utility Building - Pca. Column - 1st Preparation & Submission 08 Jul '22
347 South Utility Building - Pca. Column - 1st Review & Approval by Consultant 2d 09-07-22 10-07-22 100% 0% South Utility Building - Pca. Column - 1st Review & Approval by Consultant 10 Jul '22
348 Submission&Approval - Shop Drawing Str. - South Utility Building - Roof Steel Structure 14 d 01-07-22 15-07-22 78.5714285714286%
64% Submission&Approval - Shop Drawing Str. - South Utility Building - Roof Steel Structure 15 Jul '22
349 South Utility Building - Roof - 1st Preparation & Submission 10 d 01-07-22 10-07-22 100% 90% South Utility Building - Roof - 1st Preparation & Submission 10 Jul '22

4 OF 16
PROJECT : Relief Project
MASTER SCHEDULE (REV0.01) Dated 11Jul22
ID Task Name Duration Start Finish Planned
% Complete
%
Complete Jun Jul Aug
30-05 06-06 13-06 20-06 27-06 04-07 11-07 18-07 25-07 01-08 08-08 15-08 22-08 29-08
350 South Utility Building - Roof - 1st Review & Approval by Consultant 4d 11-07-22 15-07-22 25% 0% South Utility Building - Roof - 1st Review & Approval by Consultant11 Jul, '22 15 Jul '22
351 Submission&Approval - Shop Drawing Str. - South Utility Building - Level 1 PT Slab 21 d 26-07-22 18-08-22 0% 0% Submission&Approval - Shop Drawing Str. - South Utility Building - Level 1 PT Slab 18 Aug '22
352 South Utility Building - Level 1 - 1st Preparation & Submission 7d 26-07-22 03-08-22 0% 0% South Utility Building - Level 1 - 1st Preparation & Submission 03 Aug '22
353 South Utility Building - Level 1 - 1st Review & Approval by Consultant 7d 04-08-22 10-08-22 0% 0% South Utility Building - Level 1 - 1st Review & Approval by Consultant 10 Aug '22
354 South Utility Building - Level 1 - 2nd Preparation & Submission 4d 11-08-22 15-08-22 0% 0% South Utility Building - Level 1 - 2nd Preparation & Submission 15 Aug '22
355 South Utility Building - Level 1 - 2nd Review & Approval by Consultant 3d 16-08-22 18-08-22 0% 0% South Utility Building - Level 1 - 2nd Review & Approval by Consultant 18 Aug '22
356 Submission&Approval - Shop Drawing Str. -South Utility Building - Level 2 PT Slab 28 d 10-08-22 07-09-22 0% 0% Submission&Approval - Shop Drawing Str. -South Utility Building - Level 2 PT Slab
357 South Utility Building - Level 2 - 1st Preparation & Submission 7d 10-08-22 17-08-22 0% 0% South Utility Building - Level 2 - 1st Preparation & Submission 17 Aug '22
358 South Utility Building - Level 2 - 1st Review & Approval by Consultant 7d 18-08-22 24-08-22 0% 0% South Utility Building - Level 2 - 1st Review & Approval by Consultant 24 Aug '22

359 South Utility Building - Level 2 - 2nd Preparation & Submission 7d 25-08-22 31-08-22 0% 0% South Utility Building - Level 2 - 2nd Preparation & Submission 31 Aug '22

360 South Utility Building - Level 2 - 2nd Review & Approval by Consultant 7d 01-09-22 07-09-22 0% 0% South Utility Building - Level 2 - 2nd Review & Approval by Consultant
361 Submission&Approval - Shop Drawing Str. - South Utility Building - RC.Stair, Link Bridge 28 d 25-08-22 21-09-22 0% 0% Submission&Approval - Shop Drawing Str. - South Utility Building - RC.Stair, Link Bridge
362 South Utility Building - RC.Stair, Link Bridge- 1st Preparation & Submission 7d 25-08-22 31-08-22 0% 0% South Utility Building - RC.Stair, Link Bridge- 1st Preparation & Submission 31 Aug '22
363 South Utility Building - RC.Stair, Link Bridge - 1st Review & Approval by Consultant 7d 01-09-22 07-09-22 0% 0% South Utility Building - RC.Stair, Link Bridge - 1st Review & Approval by Consultant
364 South Utility Building - RC.Stair, Link Bridge - 2nd Preparation & Submission 7d 08-09-22 14-09-22 0% 0% South Utility Building - RC.Stair, Link Bridge - 2nd Preparation & Sub
365 South Utility Building - RC.Stair, Link Bridge- 2nd Review & Approval by Consultant 7d 15-09-22 21-09-22 0% 0% South Utility Building - RC.Stair, Link Bridge- 2nd
366 Submission&Approval - Shop Drawing Str. - South Utility Building - External Stl. Staircase28 d 25-08-22 21-09-22 0% 0% Submission&Approval - Shop Drawing Str. - South Utility Building - External Stl. Staircase
367 South Utility Building - External Stl. Staircase- 1st Preparation & Submission 7d 25-08-22 31-08-22 0% 0% South Utility Building - External Stl. Staircase- 1st Preparation & Submission 31 Aug '22
368 South Utility Building - External Stl. Staircase - 1st Review & Approval by Consultant 7d 01-09-22 07-09-22 0% 0% South Utility Building - External Stl. Staircase - 1st Review & Approval by Consultant
369 South Utility Building - External Stl. Staircase - 2nd Preparation & Submission 7d 08-09-22 14-09-22 0% 0% South Utility Building - External Stl. Staircase - 2nd Preparation & Sub
370 South Utility Building - External Stl. Staircase- 2nd Review & Approval by Consultant 7d 15-09-22 21-09-22 0% 0% South Utility Building - External Stl. Staircase- 2nd
371 Submission&Approval - Shop Drawing - Architectural work 104 d 11-07-2228-10-220.961538461538462%
0% Submission&Approval - Shop Drawing - Architectural work

372 Submission&Approval - Shop Drawing Ar. - Main Factory 82 d 04-08-2227-10-220% 0% Submission&Approval - Shop Drawing Ar. - Main Factory

373 Submission&Approval - Shop Drawing Ar. - Zone A 76 d 10-08-22 27-10-22 0% 0% Submission&Approval - Shop Drawing Ar. - Zone A
374 Submission&Approval - Shop Drawing Ar. - Zone A - Roof Metal Sheet 14 d 10-08-22 24-08-22 0% 0% Submission&Approval - Shop Drawing Ar. - Zone A - Roof Metal Sheet 24 Aug '22
375 Zone A - Roof - 1st Preparation & Submission 7d 10-08-22 17-08-22 0% 0% Zone A - Roof - 1st Preparation & Submission 17 Aug '22
376 Zone A - Roof - 1st Review & Approval by Consultant 7d 18-08-22 24-08-22 0% 0% Zone A - Roof - 1st Review & Approval by Consultant 24 Aug '22
377 Submission&Approval - Shop Drawing Ar. - Zone A - Aluminium Door, Window 28 d 01-09-22 28-09-22 0% 0% Submission&Approval - Shop Drawing Ar. - Zone A - Aluminium Door, Window
378 Zone A - Aluminium Door, Window - 1st Preparation & Submission 7d 01-09-22 07-09-22 0% 0% Zone A - Aluminium Door, Window - 1st Preparation & Submission
379 Zone A - Aluminium Door, Window - 1st Review & Approval by Consultant 7d 08-09-22 14-09-22 0% 0% Zone A - Aluminium Door, Window - 1st Review & Approval by Co
380 Zone A - Aluminium Door, Window - 2nd Preparation & Submission 7d 15-09-22 21-09-22 0% 0% Zone A - Aluminium Door, Windo
381 Zone A - Aluminium Door, Window - 2nd Review & Approval by Consultant 7d 22-09-22 28-09-22 0% 0% Zone A - Alum
382 Submission&Approval - Shop Drawing Ar. - Zone A - PC. Wall 28 d 21-09-22 19-10-22 0% 0% Subm
383 Zone A - PC. Wall - 1st Preparation & Submission 7d 21-09-22 27-09-22 0% 0%
384 Zone A - PC. Wall - 1st Review & Approval by Consultant 7d 28-09-22 04-10-22 0% 0%
385 Zone A - PC. Wall - 2nd Preparation & Submission 7d 05-10-22 11-10-22 0% 0%
386 Zone A - PC. Wall - 2nd Review & Approval by Consultant 7d 12-10-22 19-10-22 0% 0%
387 Submission&Approval - Shop Drawing Ar. - Zone A - Level 1 Plan 28 d 28-09-22 27-10-22 0% 0%
388 Zone A - Level 1 - 1st Preparation & Submission 7d 28-09-22 04-10-22 0% 0%
389 Zone A - Level 1 - 1st Review & Approval by Consultant 7d 05-10-22 11-10-22 0% 0%
390 Zone A - Level 1 - 2nd Preparation & Submission 7d 12-10-22 19-10-22 0% 0%
391 Zone A - Level 1 - 2nd Review & Approval by Consultant 7d 20-10-22 27-10-22 0% 0%
392 Submission&Approval - Shop Drawing Ar. - Zone A - Level 2 Plan 28 d 28-09-22 27-10-22 0% 0%
393 Zone A - Level 2 - 1st Preparation & Submission 7d 28-09-22 04-10-22 0% 0%
394 Zone A - Level 2 - 1st Review & Approval by Consultant 7d 05-10-22 11-10-22 0% 0%
395 Zone A - Level 2 - 2nd Preparation & Submission 7d 12-10-22 19-10-22 0% 0%
396 Zone A - Level 2 - 2nd Review & Approval by Consultant 7d 20-10-22 27-10-22 0% 0%
397 Submission&Approval - Shop Drawing Ar. - Zone B 76 d 04-08-22 20-10-22 0% 0% Submission&Approval - Shop Drawing Ar. - Zone B
398 Submission&Approval - Shop Drawing Ar. - Zone B - Roof Metal Sheet 14 d 04-08-22 18-08-22 0% 0% Submission&Approval - Shop Drawing Ar. - Zone B - Roof Metal Sheet 18 Aug '22
399 Zone B - Roof - 1st Preparation & Submission 7d 04-08-22 10-08-22 0% 0% Zone B - Roof - 1st Preparation & Submission 10 Aug '22
400 Zone B - Roof - 1st Review & Approval by Consultant 7d 11-08-22 18-08-22 0% 0% Zone B - Roof - 1st Review & Approval by Consultant 18 Aug '22
401 Submission&Approval - Shop Drawing Ar. - Zone B - Aluminium Door, Window 28 d 01-09-22 28-09-22 0% 0% Submission&Approval - Shop Drawing Ar. - Zone B - Aluminium Door, Window
402 Zone B - Aluminium Door, Window - 1st Preparation & Submission 7d 01-09-22 07-09-22 0% 0% Zone B - Aluminium Door, Window - 1st Preparation & Submission
403 Zone B - Aluminium Door, Window - 1st Review & Approval by Consultant 7d 08-09-22 14-09-22 0% 0% Zone B - Aluminium Door, Window - 1st Review & Approval by Co
404 Zone B - Aluminium Door, Window - 2nd Preparation & Submission 7d 15-09-22 21-09-22 0% 0% Zone B - Aluminium Door, Windo
405 Zone B - Aluminium Door, Window - 2nd Review & Approval by Consultant 7d 22-09-22 28-09-22 0% 0% Zone B - Alum
406 Submission&Approval - Shop Drawing Ar. - Zone B - PC. Wall 28 d 15-09-22 12-10-22 0% 0% Submission&Approval - Sh
407 Zone B - PC. Wall - 1st Preparation & Submission 7d 15-09-22 21-09-22 0% 0% Zone B - PC. W
408 Zone B - PC. Wall - 1st Review & Approval by Consultant 7d 22-09-22 28-09-22 0% 0%
409 Zone B - PC. Wall - 2nd Preparation & Submission 7d 29-09-22 05-10-22
0% 0%
410 Zone B - PC. Wall - 2nd Review & Approval by Consultant 7d 06-10-22 12-10-22
0% 0%
411 Submission&Approval - Shop Drawing Ar. - Zone B - Level 1 Plan 28 d 22-09-22 20-10-22
0% 0% Subm
412 Zone B - Level 1 - 1st Preparation & Submission 7d 22-09-22 28-09-22
0% 0%
413 Zone B - Level 1 - 1st Review & Approval by Consultant 7d 29-09-22 05-10-22
0% 0%
414 Zone B - Level 1 - 2nd Preparation & Submission 7d 06-10-22 12-10-22
0% 0%
415 Zone B - Level 1 - 2nd Review & Approval by Consultant 7d 14-10-22 20-10-22
0% 0%
416 Submission&Approval - Shop Drawing Ar. - Zone B - Level 2 Plan 28 d 22-09-22 20-10-22
0% 0% Subm
417 Zone B - Level 2 - 1st Preparation & Submission 7d 22-09-22 28-09-22
0% 0%
418 Zone B - Level 2 - 1st Review & Approval by Consultant 7d 29-09-22 05-10-22
0% 0%
419 Zone B - Level 2 - 2nd Preparation & Submission 7d 06-10-22 12-10-22
0% 0%
420 Zone B - Level 2 - 2nd Review & Approval by Consultant 7d 14-10-22 20-10-22
0% 0%
421 Submission&Approval - Shop Drawing Ar. - Office and Canteen 69 d 19-08-2228-10-220% 0% Submission&Approval - Shop Drawing Ar. - Office and Canteen

422 Submission&Approval - Shop Drawing Ar. - Office and Canteen - Façade work & Curtain wall
14 d 19-08-22 01-09-22 0% 0% Submission&Approval - Shop Drawing Ar. - Office and Canteen - Façade work & Curtain wall 01 Sep '22
423 Office and Canteen - Façade work - 1st Preparation & Submission 7d 19-08-22 25-08-22 0% 0% Office and Canteen - Façade work - 1st Preparation & Submission 25 Aug '22
424 Office and Canteen - Façade work - 1st Review & Approval by Consultant 7d 26-08-22 01-09-22 0% 0% Office and Canteen - Façade work - 1st Review & Approval by Consultant 01 Sep '22
425 Submission&Approval - Shop Drawing Ar. - Office and Canteen - Level 1 Plan 28 d 30-08-22 26-09-22 0% 0% Submission&Approval - Shop Drawing Ar. - Office and Canteen - Level 1 Plan
426 Office and Canteen - Level 1 - 1st Preparation & Submission 7d 30-08-22 05-09-22 0% 0% Office and Canteen - Level 1 - 1st Preparation & Submission
427 Office and Canteen - Level 1 - 1st Review & Approval by Consultant 7d 06-09-22 12-09-22 0% 0% Office and Canteen - Level 1 - 1st Review & Approval by Consultan
428 Office and Canteen - Level 1 - 2nd Preparation & Submission 7d 13-09-22 19-09-22 0% 0% Office and Canteen - Level 1 - 2nd
429 Office and Canteen - Level 1 - 2nd Review & Approval by Consultant 7d 20-09-22 26-09-22 0% 0% Office and Can
430 Submission&Approval - Shop Drawing Ar. - Office and Canteen - Level M Plan 28 d 15-09-22 12-10-22 0% 0% Submission&Approval - Shop Drawing Ar. -
431 Office and Canteen - Level M - 1st Preparation & Submission 7d 15-09-22 21-09-22 0% 0% Office and Canteen - Leve
432 Office and Canteen - Level M - 1st Review & Approval by Consultant 7d 22-09-22 28-09-22 0% 0% Office a
433 Office and Canteen - Level M - 2nd Preparation & Submission 7d 29-09-22 05-10-22 0% 0%
434 Office and Canteen - Level M - 2nd Review & Approval by Consultant 7d 06-10-22 12-10-22 0% 0%
435 Submission&Approval - Shop Drawing Ar. - Office and Canteen - Level 2 Plan 28 d 22-09-22 20-10-22 0% 0% Submission&App
436 Office and Canteen - Level 2 - 1st Preparation & Submission 7d 22-09-22 28-09-22 0% 0%
437 Office and Canteen - Level 2 - 1st Review & Approval by Consultant 7d 29-09-22 05-10-22 0% 0%
438 Office and Canteen - Level 2 - 2nd Preparation & Submission 7d 06-10-22 12-10-22 0% 0%
439 Office and Canteen - Level 2 - 2nd Review & Approval by Consultant 7d 14-10-22 20-10-22 0% 0%

5 OF 16
PROJECT : Relief Project
MASTER SCHEDULE (REV0.01) Dated 11Jul22
ID Task Name Duration Start Finish Planned
% Complete
%
Complete Jun Jul Aug
30-05 06-06 13-06 20-06 27-06 04-07 11-07 18-07 25-07 01-08 08-08 15-08 22-08 29-08
440 Submission&Approval - Shop Drawing Ar. - Office and Canteen - Roof Plan 28 d 29-09-22 28-10-22
0% 0% 11 Jul, '22
441 Office and Canteen - Roof - 1st Preparation & Submission 7d 29-09-22 05-10-22
0% 0%
442 Office and Canteen - Roof - 1st Review & Approval by Consultant 7d 06-10-22 12-10-22
0% 0%
443 Office and Canteen - Roof - 2nd Preparation & Submission 7d 14-10-22 20-10-22
0% 0%
444 Office and Canteen - Roof - 2nd Review & Approval by Consultant 7d 21-10-22 28-10-22
0% 0%
445 Submission&Approval - Shop Drawing Ar. - Office and Canteen - Top Roof Plan 28 d 29-09-22 28-10-22
0% 0%
446 Office and Canteen - Top Roof - 1st Preparation & Submission 7d 29-09-22 05-10-22
0% 0%
447 Office and Canteen - Top Roof - 1st Review & Approval by Consultant 7d 06-10-22 12-10-22
0% 0%
448 Office and Canteen - Top Roof - 2nd Preparation & Submission 7d 14-10-22 20-10-22
0% 0%
449 Office and Canteen - Top Roof - 2nd Review & Approval by Consultant 7d 21-10-22 28-10-22
0% 0%
450 Submission&Approval - Shop Drawing Ar. - East Utility Building 68 d 27-07-2205-10-220% 0% Submission&Approval - Shop Drawing Ar. - East Utility Building

451 Submission&Approval - Shop Drawing Ar. - East Utility Building- Roof (Aluminum trellis) 22 d 27-07-22 20-08-22 0% 0% Submission&Approval - Shop Drawing Ar. - East Utility Building- Roof (Aluminum trellis) 20 Aug '22
452 East Utility Building - Roof - 1st Preparation & Submission 7d 27-07-22 04-08-22 0% 0% East Utility Building - Roof - 1st Preparation & Submission 04 Aug '22
453 East Utility Building - Roof - 1st Review & Approval by Consultant 7d 05-08-22 11-08-22 0% 0% East Utility Building - Roof - 1st Review & Approval by Consultant 11 Aug '22
454 East Utility Building - Roof - 2nd Preparation & Submission 4d 13-08-22 16-08-22 0% 0% East Utility Building - Roof - 2nd Preparation & Submission 16 Aug '22
455 East Utility Building - Roof - 2nd Review & Approval by Consultant 4d 17-08-22 20-08-22 0% 0% East Utility Building - Roof - 2nd Review & Approval by Consultant 20 Aug '22
456 Submission&Approval - Shop Drawing Ar. - East Utility Building - Level 1 Plan 14 d 24-08-22 06-09-22 0% 0% Submission&Approval - Shop Drawing Ar. - East Utility Building - Level 1 Plan

457 East Utility Building - Level 1 - 1st Preparation & Submission 7d 24-08-22 30-08-22
0% 0% East Utility Building - Level 1 - 1st Preparation & Submission 30 Aug '22
458 East Utility Building - Level 1 - 1st Review & Approval by Consultant 7d 31-08-22 06-09-22
0% 0% East Utility Building - Level 1 - 1st Review & Approval by Consultant
459 Submission&Approval - Shop Drawing Ar. - East Utility Building - Aluminium Door, Window28 d 26-08-22 22-09-22
0% 0% Submission&Approval - Shop Drawing Ar. - East Utility Building - Aluminium Door, Window
460 East Utility Building - Aluminium Door, Window - 1st Preparation & Submission 7d 26-08-22 01-09-22
0% 0% East Utility Building - Aluminium Door, Window - 1st Preparation & Submission 01 Sep '22
461 East Utility Building - Aluminium Door, Window - 1st Review & Approval by Consultant 7d 02-09-22 08-09-22
0% 0% East Utility Building - Aluminium Door, Window - 1st Review & Approval by Consultant
462 East Utility Building - Aluminium Door, Window - 2nd Preparation & Submission 7d 09-09-22 15-09-22
0% 0% East Utility Building - Aluminium Door, Window - 2nd Preparation &
463 East Utility Building - Aluminium Door, Window - 2nd Review & Approval by Consultant 7 d 16-09-22 22-09-22
0% 0% East Utility Building - Aluminium Door, Window -
464 Submission&Approval - Shop Drawing Ar. - East Utility Building - PC. Wall 21 d 15-09-22 05-10-22
0% 0% Submission&Approval - Shop Drawing A
465 East Utility Building - PC. Wall - 1st Preparation & Submission 7d 15-09-22 21-09-22
0% 0% East Utility Building - PC. W
466 East Utility Building - PC. Wall - 1st Review & Approval by Consultant 7d 22-09-22 28-09-22
0% 0% East Util
467 East Utility Building - PC. Wall - 2nd Preparation & Submission 4d 29-09-22 02-10-22
0% 0%
468 East Utility Building - PC. Wall - 2nd Review & Approval by Consultant 3d 03-10-22 05-10-22
0% 0%
469 Submission&Approval - Shop Drawing Ar. - South Utility Building 90 d 11-07-2212-10-221.11111111111111%
2% Submission&Approval - Shop Drawing Ar. - South Utility Building

470 Submission&Approval - Shop Drawing Ar. - South Utility Building - Roof Metal Sheet 14 d 11-07-22 25-07-22 7.14285714285714%
13% Submission&Approval - Shop Drawing Ar. - South Utility Building - Roof Metal Sheet 25 Jul '22
471 South Utility Building - Roof - 1st Preparation & Submission 7d 11-07-22 18-07-22 14.2857142857143%
25% South Utility Building - Roof - 1st Preparation & Submission 18 Jul '22
472 South Utility Building - Roof - 1st Review & Approval by Consultant 7d 19-07-22 25-07-22 0% 0% South Utility Building - Roof - 1st Review & Approval by Consultant 25 Jul '22
473 Submission&Approval - Shop Drawing Ar. - South Utility Building - Level 1 Plan 28 d 25-08-22 21-09-22 0% 0% Submission&Approval - Shop Drawing Ar. - South Utility Building - Level 1 Plan
474 South Utility Building - Level 1 - 1st Preparation & Submission 7d 25-08-22 31-08-22 0% 0% South Utility Building - Level 1 - 1st Preparation & Submission 31 Aug '22
475 South Utility Building - Level 1 - 1st Review & Approval by Consultant 7d 01-09-22 07-09-22 0% 0% South Utility Building - Level 1 - 1st Review & Approval by Consultant
476 South Utility Building - Level 1 - 2nd Preparation & Submission 7d 08-09-22 14-09-22 0% 0% South Utility Building - Level 1 - 2nd Preparation & Sub
477 South Utility Building - Level 1 - 2nd Review & Approval by Consultant 7d 15-09-22 21-09-22 0% 0% South Utility Building - Level 1 - 2nd
478 Submission&Approval - Shop Drawing Ar. - South Utility Building - Aluminium Door, 28 d 26-08-22 22-09-22 0% 0% Submission&Approval - Shop Drawing Ar. - South Utility Building - Aluminium Door, Window
Window
479 South Utility Building - Aluminium Door, Window - 1st Preparation & Submission 7d 26-08-22 01-09-22 0% 0% South Utility Building - Aluminium Door, Window - 1st Preparation & Submission 01 Sep '22
480 South Utility Building - Aluminium Door, Window - 1st Review & Approval by Consultant 7d 02-09-22 08-09-22 0% 0% South Utility Building - Aluminium Door, Window - 1st Review & Approval by Consultant

481 South Utility Building - Aluminium Door, Window - 2nd Preparation & Submission 7d 09-09-22 15-09-22 0% 0% South Utility Building - Aluminium Door, Window - 2nd Preparation &
482 South Utility Building - Aluminium Door, Window - 2nd Review & Approval by Consultant 7d 16-09-22 22-09-22 0% 0% South Utility Building - Aluminium Door, Window -
483 Submission&Approval - Shop Drawing Ar. - South Utility Building - PC. Wall 28 d 15-09-22 12-10-22 0% 0% Submission&Approval - Shop Drawing Ar
484 South Utility Building - PC. Wall - 1st Preparation & Submission 7d 15-09-22 21-09-22 0% 0% South Utility Building - PC. W
485 South Utility Building - PC. Wall - 1st Review & Approval by Consultant 7d 22-09-22 28-09-22 0% 0% South Util
486 South Utility Building - PC. Wall - 2nd Preparation & Submission 7d 29-09-22 05-10-22 0% 0%
487 South Utility Building - PC. Wall - 2nd Review & Approval by Consultant 7d 06-10-22 12-10-22 0% 0%
488 Submission&Approval - Shop Drawing Ar. -South Utility Building - Level 2 Plan 14 d 17-09-22 30-09-22 0% 0% Submission&Approval - Shop Drawin
489 South Utility Building - Level 2 - 1st Preparation & Submission 4d 17-09-22 20-09-22 0% 0% South Utility Buildin
490 South Utility Building - Level 2 - 1st Review & Approval by Consultant 3d 21-09-22 23-09-22 0% 0% South Utility
491 South Utility Building - Level 2 - 2nd Preparation & Submission 4d 24-09-22 27-09-22 0% 0%
492 South Utility Building - Level 2 - 2nd Review & Approval by Consultant 3d 28-09-22 30-09-22 0% 0%
493 Submission&Approval - Shop Drawing - External work 196 d 23-06-2215-01-239.69387755102041%
11% Submission&Approval - Shop Drawing - External work

494 Submission&Approval - Shop Drawing - External work - Retention pond 20 d 23-06-22 12-07-22 95% 93% Submission&Approval - Shop Drawing - External work - Retention pond 12 Jul '22
495 Retention pond - 1st Preparation & Submission 14 d 23-06-22 06-07-22 100% 100% Retention pond - 1st Preparation & Submission 06 Jul '22
496 Retention pond - 1st Review & Approval by Consultant 6d 07-07-22 12-07-22 83.3333333333333%
75% Retention pond - 1st Review & Approval by Consultant 12 Jul '22
497 Submission&Approval - Shop Drawing - External work - Boundary fence 16 d 29-06-22 15-07-22 81.25%73% Submission&Approval - Shop Drawing - External work - Boundary fence 15 Jul '22
498 Boundary fence - 1st Preparation & Submission 13 d 29-06-22 11-07-22 100% 90% Boundary fence - 1st Preparation & Submission 11 Jul '22
499 Boundary fence - 1st Review & Approval by Consultant 3d 12-07-22 15-07-22 0% 0% Boundary fence - 1st Review & Approval by Consultant 15 Jul '22
500 Submission&Approval - Shop Drawing - External work - Stormwater drainage system 15 d 12-07-22 27-07-22 0% 0% Submission&Approval - Shop Drawing - External work - Stormwater drainage system 27 Jul '22
501 Stormwater drainage system - 1st Preparation & Submission 8d 12-07-22 20-07-22 0% 0% Stormwater drainage system - 1st Preparation & Submission 20 Jul '22
502 Stormwater drainage system - 1st Review & Approval by Consultant 7d 21-07-22 27-07-22 0% 0% Stormwater drainage system - 1st Review & Approval by Consultant 27 Jul '22
503 Submission&Approval - Shop Drawing - External work - Guardhouse & Custrm office 20 d 04-08-22 24-08-22 0% 0% Submission&Approval - Shop Drawing - External work - Guardhouse & Custrm office 24 Aug '22
504 Guardhouse & Custrm office - 1st Preparation & Submission 5d 04-08-22 08-08-22 0% 0% Guardhouse & Custrm office - 1st Preparation & Submission 08 Aug '22
505 Guardhouse & Custrm office - 1st Review & Approval by Consultant 5d 09-08-22 14-08-22 0% 0% Guardhouse & Custrm office - 1st Review & Approval by Consultant 14 Aug '22
506 Guardhouse & Custrm office - 2nd Preparation & Submission 5d 15-08-22 19-08-22 0% 0% Guardhouse & Custrm office - 2nd Preparation & Submission 19 Aug '22
507 Guardhouse & Custrm office - 2nd Review & Approval by Consultant 5d 20-08-22 24-08-22 0% 0% Guardhouse & Custrm office - 2nd Review & Approval by Consultant 24 Aug '22
508 Submission&Approval - Shop Drawing - External work - Road & Pavement, Loading dock, 21 d 25-08-22 14-09-22 0% 0% Submission&Approval - Shop Drawing - External work - Road & Pavement, Loading dock, Truck scale
Truck scale
509 Road & Pavement, Loading dock, Truck scale - 1st Preparation & Submission 7d 25-08-22 31-08-22 0% 0% Road & Pavement, Loading dock, Truck scale - 1st Preparation & Submission 31 Aug '22
510 Road & Pavement, Loading dock, Truck scale - 1st Review & Approval by Consultant 7d 01-09-22 07-09-22 0% 0% Road & Pavement, Loading dock, Truck scale - 1st Review & Approval by Consultant
511 Road & Pavement, Loading dock, Truck scale - 2nd Preparation & Submission 4d 08-09-22 11-09-22 0% 0% Road & Pavement, Loading dock, Truck scale - 2nd Preparation & Sub
512 Road & Pavement, Loading dock, Truck scale - 2nd Review & Approval by Consultant 3d 12-09-22 14-09-22 0% 0% Road & Pavement, Loading dock, Truck scale - 2nd Review &
513 Submission&Approval - Shop Drawing - External work - Car & Motorcycle parking (Southside)28 d 25-08-22 21-09-22 0% 0% Submission&Approval - Shop Drawing - External work - Car & Motorcycle parking (Southside)
514 Car & Motorcycle parking (Southside) - 1st Preparation & Submission 7d 25-08-22 31-08-22 0% 0% Car & Motorcycle parking (Southside) - 1st Preparation & Submission 31 Aug '22
515 Car & Motorcycle parking (Southside) - 1st Review & Approval by Consultant 7d 01-09-22 07-09-22 0% 0% Car & Motorcycle parking (Southside) - 1st Review & Approval by Consultant
516 Car & Motorcycle parking (Southside) - 2nd Preparation & Submission 7d 08-09-22 14-09-22 0% 0% Car & Motorcycle parking (Southside) - 2nd Preparation & Sub
517 Car & Motorcycle parking (Southside) - 2nd Review & Approval by Consultant 7d 15-09-22 21-09-22 0% 0% Car & Motorcycle parking (Southside) - 2nd
518 Submission&Approval - Shop Drawing - External work - VIP & Visitor parking (Northside) 28 d 25-08-22 21-09-22 0% 0% Submission&Approval - Shop Drawing - External work - VIP & Visitor parking (Northside)
519 VIP & Visitor parking (Northside) - 1st Preparation & Submission 7d 25-08-22 31-08-22 0% 0% VIP & Visitor parking (Northside) - 1st Preparation & Submission 31 Aug '22
520 VIP & Visitor parking (Northside) - 1st Review & Approval by Consultant 7d 01-09-22 07-09-22 0% 0% VIP & Visitor parking (Northside) - 1st Review & Approval by Consultant
521 VIP & Visitor parking (Northside) - 2nd Preparation & Submission 7d 08-09-22 14-09-22 0% 0% VIP & Visitor parking (Northside) - 2nd Preparation & Sub
522 VIP & Visitor parking (Northside) - 2nd Review & Approval by Consultant 7d 15-09-22 21-09-22 0% 0% VIP & Visitor parking (Northside) - 2nd
523 Submission&Approval - Shop Drawing - External work - Green area & Landscape 28 d 15-12-22 15-01-23 0% 0%
524 Green area & Landscape - 1st Preparation & Submission 7d 15-12-22 21-12-22 0% 0%
525 Green area & Landscape - 1st Review & Approval by Consultant 7d 22-12-22 28-12-22 0% 0%
526 Green area & Landscape - 2nd Preparation & Submission 7d 29-12-22 08-01-23 0% 0%
527 Green area & Landscape - 2nd Review & Approval by Consultant 7d 09-01-23 15-01-23 0% 0%

6 OF 16
PROJECT : Relief Project
MASTER SCHEDULE (REV0.01) Dated 11Jul22
ID Task Name Duration Start Finish Planned
% Complete
%
Complete Jun Jul Aug
30-05 06-06 13-06 20-06 27-06 04-07 11-07 18-07 25-07 01-08 08-08 15-08 22-08 29-08
528 Submission&Approval - Shop Drawing - External work - Main entrance 28 d 15-12-22 15-01-23 0% 0% 11 Jul, '22
529 Main entrance - 1st Preparation & Submission 7d 15-12-22 21-12-22 0% 0%
530 Main entrance - 1st Review & Approval by Consultant 7d 22-12-22 28-12-22 0% 0%
531 Main entrance - 2nd Preparation & Submission 7d 29-12-22 08-01-23 0% 0%
532 Main entrance - 2nd Review & Approval by Consultant 7d 09-01-23 15-01-23 0% 0%
533 Submission&Approval - Shop Drawing - External work - Truck Scale 28 d 01-09-22 28-09-22 0% 0% Submission&Approval - Shop Drawing - External work - Truck Scale

534 Truck Scale - 1st Preparation & Submission 7d 01-09-22 07-09-22 0% 0% Truck Scale - 1st Preparation & Submission
535 Truck Scale - 1st Review & Approval by Consultant 7d 08-09-22 14-09-22 0% 0% Truck Scale - 1st Review & Approval by Co
536 Truck Scale - 2nd Preparation & Submission 7d 15-09-22 21-09-22 0% 0% Truck Sca
537 Truck Scale - 2nd Review & Approval by Consultant 7d 22-09-22 28-09-22 0% 0%
538 Submission&Approval - Shop Drawing - External work - Walk Way 28 d 04-08-22 01-09-22 0% 0% Submission&Approval - Shop Drawing - External work - Walk Way 01 Sep '22
539 Walk Way - 1st Preparation & Submission 7d 04-08-22 10-08-22 0% 0% Walk Way - 1st Preparation & Submission 10 Aug '22
540 Walk Way - 1st Review & Approval by Consultant 7d 11-08-22 18-08-22 0% 0% Walk Way - 1st Review & Approval by Consultant 18 Aug '22
541 Walk Way - 2nd Preparation & Submission 7d 19-08-22 25-08-22 0% 0% Walk Way - 2nd Preparation & Submission 25 Aug '22
542 Walk Way - 2nd Review & Approval by Consultant 7d 26-08-22 01-09-22 0% 0% Walk Way - 2nd Review & Approval by Consultant 01 Sep '22
543 Submission&Approval - Shop Drawing - External work - Pipe Rack 14 d 01-08-22 15-08-22 0% 0% Submission&Approval - Shop Drawing - External work - Pipe Rack 15 Aug '22
544 Pipe Rack - 1st Preparation & Submission 10 d 01-08-22 10-08-22 0% 0% Pipe Rack - 1st Preparation & Submission 10 Aug '22
545 Pipe Rack - 1st Review & Approval by Consultant 4d 11-08-22 15-08-22 0% 0% Pipe Rack - 1st Review & Approval by Consultant 15 Aug '22
546 Submission&Approval - Material 85 d 19-06-2215-09-2227.0588235294118%
25% Submission&Approval - Material

547 Submission&Approval - Material - Re-Bar 10 d 19-06-22 28-06-22 100% 100% Submission&Approval - Material - Re-Bar 28 Jun '22
548 Re-Bar - 1st Preparation & Submission 7d 19-06-22 25-06-22 100% 100% Re-Bar - 1st Preparation & Submission 25 Jun '22
549 Re-Bar - 1st Review & Approval by Consultant 3d 26-06-22 28-06-22 100% 100% Re-Bar - 1st Review & Approval by Consultant 28 Jun '22
550 Submission&Approval - Material - Concrete 10 d 19-06-22 28-06-22 100% 100% Submission&Approval - Material - Concrete 28 Jun '22
551 Concrete - 1st Preparation & Submission 7d 19-06-22 25-06-22 100% 100% Concrete - 1st Preparation & Submission 25 Jun '22
552 Concrete - 1st Review & Approval by Consultant 3d 26-06-22 28-06-22 100% 100% Concrete - 1st Review & Approval by Consultant 28 Jun '22
553 Submission&Approval - Material - Fireproof paint, OP paint for roof/siding wall str 21 d 23-06-22 14-07-22 90.4761904761905%
100% Submission&Approval - Material - Fireproof paint, OP paint for roof/siding wall str 14 Jul '22
554 Fireproof paint - 1st Preparation & Submission 7d 23-06-22 29-06-22 100% 100% Fireproof paint - 1st Preparation & Submission 29 Jun '22
555 Fireproof paint - 1st Review & Approval by Consultant 7d 30-06-22 06-07-22 100% 100% Fireproof paint - 1st Review & Approval by Consultant 06 Jul '22
556 OP paint for roof/siding wall str - 1st Preparation & Submission 5d 04-07-22 08-07-22 100% 100% OP paint for roof/siding wall str - 1st Preparation & Submission 08 Jul '22
557 OP paint for roof/siding wall str - 1st Review & Approval by Consultant 5d 09-07-22 14-07-22 60% 100% OP paint for roof/siding wall str - 1st Review & Approval by Consultant 14 Jul '22
558 Submission&Approval - Material - Metal roof sheet 14 d 23-06-22 06-07-22 100% 100% Submission&Approval - Material - Metal roof sheet 06 Jul '22
559 Metal roof sheet - 1st Preparation & Submission 7d 23-06-22 29-06-22 100% 100% Metal roof sheet - 1st Preparation & Submission 29 Jun '22
560 Metal roof sheet - 1st Review & Approval by Consultant 7d 30-06-22 06-07-22 100% 100% Metal roof sheet - 1st Review & Approval by Consultant 06 Jul '22
561 Submission&Approval - Material - Polypropylane for process waste 14 d 23-06-22 06-07-22 100% 100% Submission&Approval - Material - Polypropylane for process waste 06 Jul '22
562 Polypropylane for process waste - 1st Preparation & Submission 7d 23-06-22 29-06-22 100% 100% Polypropylane for process waste - 1st Preparation & Submission 29 Jun '22
563 Polypropylane for process waste - 1st Review & Approval by Consultant 7d 30-06-22 06-07-22 100% 100% Polypropylane for process waste - 1st Review & Approval by Consultant 06 Jul '22
564 Submission&Approval - Material - PVC & HDPE for sanitary waste, soil, vent 14 d 30-06-22 14-07-22 85.7142857142857%
100% Submission&Approval - Material - PVC & HDPE for sanitary waste, soil, vent 14 Jul '22
565 PVC & HDPE for sanitary waste, soil, vent - 1st Preparation & Submission 7d 30-06-22 06-07-22 100% 100% PVC & HDPE for sanitary waste, soil, vent - 1st Preparation & Submission 06 Jul '22
566 PVC & HDPE for sanitary waste, soil, vent - 1st Review & Approval by Consultant 7d 07-07-22 14-07-22 71.4285714285714%
100% PVC & HDPE for sanitary waste, soil, vent - 1st Review & Approval by Consultant 14 Jul '22
567 Submission&Approval - Material - Dock leveler 28 d 30-06-22 30-07-22 42.8571428571429%
0% Submission&Approval - Material - Dock leveler 30 Jul '22
568 Dock leveler - 1st Preparation & Submission 7d 30-06-22 06-07-22 100% 0% Dock leveler - 1st Preparation & Submission 06 Jul '22
569 Dock leveler - 1st Review & Approval by Consultant 7d 07-07-22 14-07-22 71.4285714285714%
0% Dock leveler - 1st Review & Approval by Consultant 14 Jul '22
570 Dock leveler - 2nd Preparation & Submission 7d 15-07-22 21-07-22 0% 0% Dock leveler - 2nd Preparation & Submission 21 Jul '22
571 Dock leveler - 2nd Review & Approval by Consultant 7d 22-07-22 30-07-22 0% 0% Dock leveler - 2nd Review & Approval by Consultant 30 Jul '22
572 Submission&Approval - Material - Roof Steel Structure 10 d 01-07-22 10-07-22 100% 100% Submission&Approval - Material - Roof Steel Structure 10 Jul '22
573 Roof Steel Structure - 1st Preparation & Submission 7d 01-07-22 07-07-22 100% 100% Roof Steel Structure - 1st Preparation & Submission 07 Jul '22
574 Roof Steel Structure - 1st Review & Approval by Consultant 3d 08-07-22 10-07-22 100% 100% Roof Steel Structure - 1st Review & Approval by Consultant 10 Jul '22
575 Submission&Approval - Material - Formwork for 1M & 2F, posttension slab 16 d 04-07-22 20-07-22 50% 50% Submission&Approval - Material - Formwork for 1M & 2F, posttension slab 20 Jul '22
576 Formwork for 1M & 2F, posttension slab - 1st Preparation & Submission 9d 04-07-22 12-07-22 88.8888888888889%
89% Formwork for 1M & 2F, posttension slab - 1st Preparation & Submission 12 Jul '22
577 Formwork for 1M & 2F, posttension slab - 1st Review & Approval by Consultant 7d 14-07-22 20-07-22 0% 0% Formwork for 1M & 2F, posttension slab - 1st Review & Approval by Consultant 20 Jul '22
578 Submission&Approval - Material - Posttension slab 20 d 04-07-22 24-07-22 40% 41% Submission&Approval - Material - Posttension slab 24 Jul '22
579 Posttension slab - 1st Preparation & Submission 15 d 04-07-22 19-07-22 53.3333333333333%
55% Posttension slab - 1st Preparation & Submission 19 Jul '22
580 Posttension slab - 1st Review & Approval by Consultant 5d 20-07-22 24-07-22 0% 0% Posttension slab - 1st Review & Approval by Consultant 24 Jul '22
581 Submission&Approval - Material - External CHB wall & Plastering cement 28 d 07-07-22 06-08-22 17.8571428571429%
19% Submission&Approval - Material - External CHB wall & Plastering cement 06 Aug '22
582 External CHB wall & Plastering cement - 1st Preparation & Submission 7d 07-07-22 14-07-22 71.4285714285714%
75% External CHB wall & Plastering cement - 1st Preparation & Submission 14 Jul '22
583 External CHB wall & Plastering cement - 1st Review & Approval by Consultant 7d 15-07-22 21-07-22 0% 0% External CHB wall & Plastering cement - 1st Review & Approval by Consultant 21 Jul '22
584 External CHB wall & Plastering cement - 2nd Preparation & Submission 7d 22-07-22 30-07-22 0% 0% External CHB wall & Plastering cement - 2nd Preparation & Submission 30 Jul '22
585 External CHB wall & Plastering cement - 2nd Review & Approval by Consultant 7d 31-07-22 06-08-22 0% 0% External CHB wall & Plastering cement - 2nd Review & Approval by Consultant 06 Aug '22
586 Submission&Approval - Material - Exterior & Interior paint 28 d 07-07-22 06-08-22 17.8571428571429%
19% Submission&Approval - Material - Exterior & Interior paint 06 Aug '22
587 Exterior & Interior paint - 1st Preparation & Submission 7d 07-07-22 14-07-22 71.4285714285714%
75% Exterior & Interior paint - 1st Preparation & Submission 14 Jul '22
588 Exterior & Interior paint - 1st Review & Approval by Consultant 7d 15-07-22 21-07-22 0% 0% Exterior & Interior paint - 1st Review & Approval by Consultant 21 Jul '22
589 Exterior & Interior paint - 2nd Preparation & Submission 7d 22-07-22 30-07-22 0% 0% Exterior & Interior paint - 2nd Preparation & Submission 30 Jul '22
590 Exterior & Interior paint - 2nd Review & Approval by Consultant 7d 31-07-22 06-08-22 0% 0% Exterior & Interior paint - 2nd Review & Approval by Consultant 06 Aug '22
591 Submission&Approval - Material - Wall sand wich panel 24 d 10-07-22 05-08-22 8.33333333333333%
9% Submission&Approval - Material - Wall sand wich panel 05 Aug '22
592 Wall sand wich panel - 1st Preparation & Submission 15 d 10-07-22 25-07-22 13.3333333333333%
15% Wall sand wich panel - 1st Preparation & Submission 25 Jul '22
593 Wall sand wich panel - 1st Review & Approval by Consultant 9d 26-07-22 05-08-22 0% 0% Wall sand wich panel - 1st Review & Approval by Consultant 05 Aug '22
594 Submission&Approval - Material - Sheet shutter (high speed shutter) 28 d 15-07-22 14-08-22 0% 0% Submission&Approval - Material - Sheet shutter (high speed shutter) 14 Aug '22
595 Sheet shutter (high speed shutter) - 1st Preparation & Submission 7d 15-07-22 21-07-22 0% 0% Sheet shutter (high speed shutter) - 1st Preparation & Submission 21 Jul '22
596 Sheet shutter (high speed shutter) - 1st Review & Approval by Consultant 7d 22-07-22 30-07-22 0% 0% Sheet shutter (high speed shutter) - 1st Review & Approval by Consultant 30 Jul '22
597 Sheet shutter (high speed shutter) - 2nd Preparation & Submission 7d 31-07-22 06-08-22 0% 0% Sheet shutter (high speed shutter) - 2nd Preparation & Submission 06 Aug '22
598 Sheet shutter (high speed shutter) - 2nd Review & Approval by Consultant 7d 07-08-22 14-08-22 0% 0% Sheet shutter (high speed shutter) - 2nd Review & Approval by Consultant 14 Aug '22
599 Submission&Approval - Material - Shutter,Steel & Aluminum door 28 d 15-07-22 14-08-22 0% 0% Submission&Approval - Material - Shutter,Steel & Aluminum door 14 Aug '22
600 Shutter,Steel & Aluminum door - 1st Preparation & Submission 7d 15-07-22 21-07-22 0% 0% Shutter,Steel & Aluminum door - 1st Preparation & Submission 21 Jul '22
601 Shutter,Steel & Aluminum door - 1st Review & Approval by Consultant 7d 22-07-22 30-07-22 0% 0% Shutter,Steel & Aluminum door - 1st Review & Approval by Consultant 30 Jul '22
602 Shutter,Steel & Aluminum door - 2nd Preparation & Submission 7d 31-07-22 06-08-22 0% 0% Shutter,Steel & Aluminum door - 2nd Preparation & Submission 06 Aug '22
603 Shutter,Steel & Aluminum door - 2nd Review & Approval by Consultant 7d 07-08-22 14-08-22 0% 0% Shutter,Steel & Aluminum door - 2nd Review & Approval by Consultant 14 Aug '22
604 Submission&Approval - Material - Roof Insulation & gal.mesh (Rock Wool) 13 d 15-07-22 27-07-22 0% 0% Submission&Approval - Material - Roof Insulation & gal.mesh (Rock Wool) 27 Jul '22
605 Roof Insulation & gal.mesh (Rock Wool) - 1st Preparation & Submission 8d 15-07-22 22-07-22 0% 0% Roof Insulation & gal.mesh (Rock Wool) - 1st Preparation & Submission 22 Jul '22
606 Roof Insulation & gal.mesh (Rock Wool) - 1st Review & Approval by Consultant 5d 23-07-22 27-07-22 0% 0% Roof Insulation & gal.mesh (Rock Wool) - 1st Review & Approval by Consultant 27 Jul '22
607 Submission&Approval - Material - Siding wall sheet 15 d 20-07-22 05-08-22 0% 0% Submission&Approval - Material - Siding wall sheet 05 Aug '22
608 Siding wall sheet - 1st Preparation & Submission 8d 20-07-22 27-07-22 0% 0% Siding wall sheet - 1st Preparation & Submission 27 Jul '22
609 Siding wall sheet - 1st Review & Approval by Consultant 7d 30-07-22 05-08-22 0% 0% Siding wall sheet - 1st Review & Approval by Consultant 05 Aug '22
610 Submission&Approval - Material - Interior wall & floor finishing,ceramic tile,OA floor, 28 d 22-07-22 21-08-22 0% 0% Submission&Approval - Material - Interior wall & floor finishing,ceramic tile,OA floor, epoxy,pcv vinyl sheet 21 Aug '22
epoxy,pcv vinyl sheet
611 Interior wall & floor finishing,ceramic tile,OA floor, epoxy,pcv vinyl sheet - 1st Preparation & 7d 22-07-22 30-07-22 0% 0% Interior wall & floor finishing,ceramic tile,OA floor, epoxy,pcv vinyl sheet - 1st Preparation & Submission 30 Jul '22
Submission
612 Interior wall & floor finishing,ceramic tile,OA floor, epoxy,pcv vinyl sheet - 1st Review & 7d 31-07-22 06-08-22 0% 0% Interior wall & floor finishing,ceramic tile,OA floor, epoxy,pcv vinyl sheet - 1st Review & Approval by Consultant 06 Aug '22
Approval by Consultant
613 Interior wall & floor finishing,ceramic tile,OA floor, epoxy,pcv vinyl sheet - 2nd Preparation & 7d 07-08-22 14-08-22 0% 0% Interior wall & floor finishing,ceramic tile,OA floor, epoxy,pcv vinyl sheet - 2nd Preparation & Submission 14 Aug '22
Submission

7 OF 16
PROJECT : Relief Project
MASTER SCHEDULE (REV0.01) Dated 11Jul22
ID Task Name Duration Start Finish Planned
% Complete
%
Complete Jun Jul Aug
30-05 06-06 13-06 20-06 27-06 04-07 11-07 18-07 25-07 01-08 08-08 15-08 22-08 29-08
614 Interior wall & floor finishing,ceramic tile,OA floor, epoxy,pcv vinyl sheet - 2nd Review & 7d 15-08-22 21-08-22 0% 0% 11 Jul, '22 Interior wall & floor finishing,ceramic tile,OA floor, epoxy,pcv vinyl sheet - 2nd Review & Approval by Consultant 21 Aug '22
Approval by Consultant
615 Submission&Approval - Material - Water proof for water tank,toilet,kitchen,roof slab 28 d 22-07-22 21-08-22 0% 0% Submission&Approval - Material - Water proof for water tank,toilet,kitchen,roof slab 21 Aug '22
616 Water proof for water tank,toilet,kitchen,roof slab - 1st Preparation & Submission 7d 22-07-22 30-07-22 0% 0% Water proof for water tank,toilet,kitchen,roof slab - 1st Preparation & Submission 30 Jul '22
617 Water proof for water tank,toilet,kitchen,roof slab - 1st Review & Approval by Consultant 7d 31-07-22 06-08-22 0% 0% Water proof for water tank,toilet,kitchen,roof slab - 1st Review & Approval by Consultant 06 Aug '22
618 Water proof for water tank,toilet,kitchen,roof slab - 2nd Preparation & Submission 7d 07-08-22 14-08-22 0% 0% Water proof for water tank,toilet,kitchen,roof slab - 2nd Preparation & Submission 14 Aug '22
619 Water proof for water tank,toilet,kitchen,roof slab - 2nd Review & Approval by Consultant 7d 15-08-22 21-08-22 0% 0% Water proof for water tank,toilet,kitchen,roof slab - 2nd Review & Approval by Consultant 21 Aug '22
620 Submission&Approval - Material - Aluminum window,composite cladding & Insulated glass 10 d 22-07-22 02-08-22 0% 0% Submission&Approval - Material - Aluminum window,composite cladding & Insulated glass system 02 Aug '22
system
621 Aluminum window,composite cladding & Insulated glass system - 1st Preparation & Submission 5d 22-07-22 26-07-22 0% 0% Aluminum window,composite cladding & Insulated glass system - 1st Preparation & Submission 26 Jul '22
622 Aluminum window,composite cladding & Insulated glass system - 1st Review & Approval by 5d 27-07-22 02-08-22 0% 0% Aluminum window,composite cladding & Insulated glass system - 1st Review & Approval by Consultant 02 Aug '22
Consultant
623 Submission&Approval - Material - Toilet partition 28 d 31-07-22 28-08-22 0% 0% Submission&Approval - Material - Toilet partition 28 Aug '22
624 Toilet partition - 1st Preparation & Submission 7d 31-07-22 06-08-22 0% 0% Toilet partition - 1st Preparation & Submission 06 Aug '22
625 Toilet partition - 1st Review & Approval by Consultant 7d 07-08-22 14-08-22 0% 0% Toilet partition - 1st Review & Approval by Consultant 14 Aug '22
626 Toilet partition - 2nd Preparation & Submission 7d 15-08-22 21-08-22 0% 0% Toilet partition - 2nd Preparation & Submission 21 Aug '22
627 Toilet partition - 2nd Review & Approval by Consultant 7d 22-08-22 28-08-22 0% 0% Toilet partition - 2nd Review & Approval by Consultant 28 Aug '22
628 Submission&Approval - Material - Key & lock set 19 d 01-08-22 20-08-22 0% 0% Submission&Approval - Material - Key & lock set 20 Aug '22

629 Key & lock set - 1st Preparation & Submission 7d 01-08-22 07-08-22 0% 0% Key & lock set - 1st Preparation & Submission 07 Aug '22
630 Key & lock set - 1st Review & Approval by Consultant 12 d 08-08-22 20-08-22 0% 0% Key & lock set - 1st Review & Approval by Consultant 20 Aug '22
631 Submission&Approval - Material - Dry wall & Ceiling 28 d 07-08-22 04-09-22 0% 0% Submission&Approval - Material - Dry wall & Ceiling
632 Dry wall & Ceiling - 1st Preparation & Submission 7d 07-08-22 14-08-22 0% 0% Dry wall & Ceiling - 1st Preparation & Submission 14 Aug '22
633 Dry wall & Ceiling - 1st Review & Approval by Consultant 7d 15-08-22 21-08-22 0% 0% Dry wall & Ceiling - 1st Review & Approval by Consultant 21 Aug '22
634 Dry wall & Ceiling - 2nd Preparation & Submission 7d 22-08-22 28-08-22 0% 0% Dry wall & Ceiling - 2nd Preparation & Submission 28 Aug '22
635 Dry wall & Ceiling - 2nd Review & Approval by Consultant 7d 29-08-22 04-09-22 0% 0% Dry wall & Ceiling - 2nd Review & Approval by Consultant
636 Submission&Approval - Material - Floor hardener 28 d 19-08-22 15-09-22 0% 0% Submission&Approval - Material - Floor hardener
637 Floor hardener - 1st Preparation & Submission 7d 19-08-22 25-08-22 0% 0% Floor hardener - 1st Preparation & Submission 25 Aug '22
638 Floor hardener - 1st Review & Approval by Consultant 7d 26-08-22 01-09-22 0% 0% Floor hardener - 1st Review & Approval by Consultant 01 Sep '22
639 Floor hardener - 2nd Preparation & Submission 7d 02-09-22 08-09-22 0% 0% Floor hardener - 2nd Preparation & Submission
640 Floor hardener - 2nd Review & Approval by Consultant 7d 09-09-22 15-09-22 0% 0% Floor hardener - 2nd Review & Approval b
641 Procurement 211 d 07-07-2213-02-232.3696682464455%
4% Procurement

642 Procurement - Material - Fireproof paint, OP paint for roof/siding wall structure 40 d 07-07-22 19-08-22 12.5% 19% Procurement - Material - Fireproof paint, OP paint for roof/siding wall structure 19 Aug '22
643 Procurement - Fireproof paint, OP paint for roof/siding wall structure - Select Vendor & Issued 10 d 07-07-22 17-07-22 50% 75% Procurement - Fireproof paint, OP paint for roof/siding wall structure - Select Vendor & Issued P.O. 17 Jul '22
P.O.
644 Procurement - Fireproof paint, OP paint for roof/siding wall structure - Lead time 30 d 18-07-22 19-08-22 0% 0% Procurement - Fireproof paint, OP paint for roof/siding wall structure - Lead time 19 Aug '22
645 Procurement - Fireproof paint, OP paint for roof/siding wall structure - Mat on site 0d 19-08-22 19-08-22 0% 0% Procurement - Fireproof paint, OP paint for roof/siding wall structure - Mat on site 19 Aug '22
646 Procurement - Material - Polypropylane for process waste 30 d 07-07-22 08-08-22 16.6666666666667%
33% Procurement - Material - Polypropylane for process waste 08 Aug '22
647 Procurement - Polypropylane for process waste - Select Vendor & Issued P.O. 10 d 07-07-22 17-07-22 50% 100% Procurement - Polypropylane for process waste - Select Vendor & Issued P.O. 17 Jul '22
648 Procurement - Polypropylane for process waste - Lead time 20 d 18-07-22 08-08-22 0% 0% Procurement - Polypropylane for process waste - Lead time 08 Aug '22
649 Procurement - Polypropylane for process waste - Mat on site 0d 08-08-22 08-08-22 0% 0% Procurement - Polypropylane for process waste - Mat on site 08 Aug '22
650 Procurement - Material - Metal roof sheet 57 d 08-07-22 06-09-22 7.01754385964912%
12% Procurement - Material - Metal roof sheet
651 Procurement - Metal roof sheet - Select Vendor & Issued P.O. 1d 08-07-22 08-07-22 100% 100% Procurement - Metal roof sheet - Select Vendor & Issued P.O. 08 Jul '22
652 Procurement - Metal roof sheet - Lead time 56 d 09-07-22 06-09-22 5.35714285714286%
10% Procurement - Metal roof sheet - Lead time
653 Procurement - Metal roof sheet - Mat on site 0d 06-09-22 06-09-22 0% 0% Procurement - Metal roof sheet - Mat on
654 Procurement - Material - Roof Steel Structure 36 d 11-07-22 19-08-22 2.77777777777778%
21% Procurement - Material - Roof Steel Structure 19 Aug '22
655 Procurement - Roof Steel Structure - Select Vendor & Issued P.O. 10 d 11-07-22 21-07-22 10% 75% Procurement - Roof Steel Structure - Select Vendor & Issued P.O. 21 Jul '22
656 Procurement - Roof Steel Structure - Lead time 26 d 22-07-22 19-08-22 0% 0% Procurement - Roof Steel Structure - Lead time 19 Aug '22
657 Procurement - Roof Steel Structure - Mat on site 0d 19-08-22 19-08-22 0% 0% Procurement - Roof Steel Structure - Mat on site 19 Aug '22
658 Procurement - Material - PVC & HDPE for sanitary waste, soil, vent 20 d 15-07-22 05-08-22 0% 25% Procurement - Material - PVC & HDPE for sanitary waste, soil, vent 05 Aug '22
659 Procurement - PVC & HDPE for sanitary waste, soil, vent - Select Vendor & Issued P.O. 10 d 15-07-22 24-07-22 0% 50% Procurement - PVC & HDPE for sanitary waste, soil, vent - Select Vendor & Issued P.O. 24 Jul '22
660 Procurement - PVC & HDPE for sanitary waste, soil, vent - Lead time 10 d 25-07-22 05-08-22 0% 0% Procurement - PVC & HDPE for sanitary waste, soil, vent - Lead time 05 Aug '22
661 Procurement - PVC & HDPE for sanitary waste, soil, vent - Mat on site 0d 05-08-22 05-08-22 0% 0% Procurement - PVC & HDPE for sanitary waste, soil, vent - Mat on site 05 Aug '22
662 Procurement - Material - Formwork for 1M & 2F, posttension slab 27 d 21-07-22 19-08-22 0% 0% Procurement - Material - Formwork for 1M & 2F, posttension slab 19 Aug '22
663 Procurement - Formwork for 1M & 2F, posttension slab - Select Vendor & Issued P.O. 10 d 21-07-22 01-08-22 0% 0% Procurement - Formwork for 1M & 2F, posttension slab - Select Vendor & Issued P.O. 01 Aug '22
664 Procurement - Formwork for 1M & 2F, posttension slab - Lead time 17 d 02-08-22 19-08-22 0% 0% Procurement - Formwork for 1M & 2F, posttension slab - Lead time 19 Aug '22
665 Procurement - Formwork for 1M & 2F, posttension slab - Mat on site 0d 19-08-22 19-08-22 0% 0% Procurement - Formwork for 1M & 2F, posttension slab - Mat on site 19 Aug '22
666 Procurement - Material - Posttension slab 20 d 25-07-22 16-08-22 0% 0% Procurement - Material - Posttension slab 16 Aug '22
667 Procurement - Posttension slab - Select Vendor & Issued P.O. 10 d 25-07-22 05-08-22 0% 0% Procurement - Posttension slab - Select Vendor & Issued P.O. 05 Aug '22
668 Procurement - Posttension slab - Lead time 10 d 06-08-22 16-08-22 0% 0% Procurement - Posttension slab - Lead time 16 Aug '22
669 Procurement - Posttension slab - Mat on site 0d 16-08-22 16-08-22 0% 0% Procurement - Posttension slab - Mat on site 16 Aug '22
670 Procurement - Material - Roof Insulation & gal.mesh (rock wool) 38 d 30-07-22 06-09-22 0% 20% Procurement - Material - Roof Insulation & gal.mesh (rock wool)
671 Procurement - Roof Insulation & gal.mesh (rock wool) - Select Vendor & Issued P.O. 10 d 30-07-22 08-08-22 0% 75% Procurement - Roof Insulation & gal.mesh (rock wool) - Select Vendor & Issued P.O. 08 Aug '22
672 Procurement - Roof Insulation & gal.mesh (rock wool) - Lead time 28 d 09-08-22 06-09-22 0% 0% Procurement - Roof Insulation & gal.mesh (rock wool) - Lead time
673 Procurement - Roof Insulation & gal.mesh (rock wool) - Mat on site 0d 06-09-22 06-09-22 0% 0% Procurement - Roof Insulation & gal.mesh (rock wool) - Mat on
674 Procurement - Material - Dock leveler 190 d 31-07-22 13-02-23 0% 0% Procurement - Material - Dock leveler
675 Procurement - Dock leveler - Select Vendor & Issued P.O. 10 d 31-07-22 09-08-22 0% 0% Procurement - Dock leveler - Select Vendor & Issued P.O. 09 Aug '22
676 Procurement - Dock leveler - Lead time 180 d 10-08-22 13-02-23 0% 0% Procurement - Dock leveler - Lead time
677 Procurement - Dock leveler - Mat on site 0d 13-02-23 13-02-23 0% 0%
678 Procurement - Material - Aluminum window,composite cladding & Insulated glass system 106 d 03-08-22 19-11-22 0% 1% Procurement - Material - Aluminum window,composite cladding & Insulated glass system
679 Procurement - Aluminum window,composite cladding & Insulated glass system - Select Vendor 5d 03-08-22 07-08-22 0% 25% Procurement - Aluminum window,composite cladding & Insulated glass system - Select Vendor & Issued P.O. 07 Aug '22
& Issued P.O.
680 Procurement - Aluminum window,composite cladding & Insulated glass system - Lead time 101 d 08-08-22 19-11-22 0% 0% Procurement - Aluminum window,composite cladding & Insulated glass system - Lead time
681 Procurement - Aluminum window,composite cladding & Insulated glass system - Mat on site 0d 19-11-22 19-11-22 0% 0%
682 Procurement - Material - Siding wall sheet 57 d 06-08-22 02-10-22 0% 0% Procurement - Material - Siding wall sheet
683 Procurement - Siding wall sheet - Select Vendor & Issued P.O. 10 d 06-08-22 16-08-22 0% 0% Procurement - Siding wall sheet - Select Vendor & Issued P.O. 16 Aug '22
684 Procurement - Siding wall sheet - Lead time 47 d 17-08-22 02-10-22 0% 0% Procurement - Siding wall sheet - Lead time
685 Procurement - Siding wall sheet - Mat on site 0d 02-10-22 02-10-22 0% 0%
686 Procurement - Material - Wall sand wich panel 82 d 06-08-22 29-10-22 0% 0% Procurement - Material - Wall sand wich panel
687 Procurement - Wall sand wich panel - Select Vendor & Issued P.O. 10 d 06-08-22 16-08-22 0% 0% Procurement - Wall sand wich panel - Select Vendor & Issued P.O. 16 Aug '22
688 Procurement - Wall sand wich panel - Lead time 72 d 17-08-22 29-10-22 0% 0% Procurement - Wall sand wich panel - Lead time
689 Procurement - Wall sand wich panel - Mat on site 0d 29-10-22 29-10-22 0% 0%
690 Procurement - Material - External CHB wall & plastering cement 55 d 07-08-22 01-10-22 0% 0% Procurement - Material - External CHB wall & plastering cement
691 Procurement - External CHB wall & plastering cement - Select Vendor & Issued P.O. 10 d 07-08-22 17-08-22 0% 0% Procurement - External CHB wall & plastering cement - Select Vendor & Issued P.O. 17 Aug '22
692 Procurement - External CHB wall & plastering cement - Lead time 45 d 18-08-22 01-10-22 0% 0% Procurement - External CHB wall & plastering cement - Lead time
693 Procurement - External CHB wall & plastering cement - Mat on site 0d 01-10-22 01-10-22 0% 0%
694 Procurement - Material - Exterior & Interior paint - Select Vendor & Issued P.O. 55 d 07-08-22 01-10-22 0% 0% Procurement - Material - Exterior & Interior paint - Select Vendor & Issued P.O.
695 Procurement - Exterior & Interior paint - Select Vendor & Issued P.O. 10 d 07-08-22 17-08-22 0% 0% Procurement - Exterior & Interior paint - Select Vendor & Issued P.O. 17 Aug '22
696 Procurement - Exterior & Interior paint - Lead time 45 d 18-08-22 01-10-22 0% 0% Procurement - Exterior & Interior paint - Lead time
697 Procurement - Exterior & Interior paint - Mat on site 0d 01-10-22 01-10-22 0% 0%
698 Procurement - Material - Sheet shutter (high speed shutter) 130 d 15-08-22 25-12-22 0% 0% Procurement - Material - Sheet shutter (high speed shutter)
699 Procurement - Sheet shutter (high speed shutter) - Select Vendor & Issued P.O. 10 d 15-08-22 24-08-22 0% 0% Procurement - Sheet shutter (high speed shutter) - Select Vendor & Issued P.O. 24 Aug '22

8 OF 16
PROJECT : Relief Project
MASTER SCHEDULE (REV0.01) Dated 11Jul22
ID Task Name Duration Start Finish Planned
% Complete
%
Complete Jun Jul Aug
30-05 06-06 13-06 20-06 27-06 04-07 11-07 18-07 25-07 01-08 08-08 15-08 22-08 29-08
700 Procurement - Sheet shutter (high speed shutter) - Lead time 120 d 25-08-22 25-12-22 0% 0% 11 Jul, '22 Procurement - Sheet shutter (high speed shutter) - Lead time
701 Procurement - Sheet shutter (high speed shutter) - Mat on site 0d 25-12-22 25-12-22 0% 0%
702 Procurement - Material - Shutter,Steel & Aluminum door 60 d 15-08-22 14-10-22 0% 0% Procurement - Material - Shutter,Steel & Aluminum door
703 Procurement - Shutter,Steel & Aluminum door - Select Vendor & Issued P.O. 10 d 15-08-22 24-08-22 0% 0% Procurement - Shutter,Steel & Aluminum door - Select Vendor & Issued P.O. 24 Aug '22
704 Procurement - Shutter,Steel & Aluminum door - Lead time 50 d 25-08-22 14-10-22 0% 0% Procurement - Shutter,Steel & Aluminum door - Lead time
705 Procurement - Shutter,Steel & Aluminum door - Mat on site 0d 14-10-22 14-10-22 0% 0%
706 Procurement - Material - Key & lock set 59 d 21-08-22 19-10-22 0% 0% Procurement - Material - Key & lock set
707 Procurement - Key & lock set - Select Vendor & Issued P.O. 10 d 21-08-22 30-08-22 0% 0% Procurement - Key & lock set - Select Vendor & Issued P.O. 30 Aug '22
708 Procurement - Key & lock set - Lead time 49 d 31-08-22 19-10-22 0% 0% Procurement - Key & lock set - Lead time
709 Procurement - Key & lock set - Mat on site 0d 19-10-22 19-10-22 0% 0%
710 Procurement - Material - Interior wall & floor finishing ceramic tile,OA floor, epoxy,pcv vinyl 70 d 22-08-22 01-11-22 0% 0% Procurement - Material - Interior wall & floor finishing ceramic tile,OA floor, epoxy,pcv vinyl sheet
sheet
711 Procurement - Interior wall & floor finishing ceramic tile,OA floor, epoxy,pcv vinyl sheet - Select 10 d 22-08-22 31-08-22 0% 0% Procurement - Interior wall & floor finishing ceramic tile,OA floor, epoxy,pcv vinyl sheet - Select Vendor & Issued P.O. 31 Aug '22
Vendor & Issued P.O.
712 Procurement - Interior wall & floor finishing ceramic tile,OA floor, epoxy,pcv vinyl sheet - Lead 60 d 01-09-22 01-11-22 0% 0% Procurement - Interior wall & floor finishing ceramic tile,OA floor, epoxy,pcv vinyl sheet - Lead time
time
713 Procurement - Interior wall & floor finishing ceramic tile,OA floor, epoxy,pcv vinyl sheet - Mat on 0 d 01-11-22 01-11-22 0% 0%
site
714 Procurement - Material - Water proof for water tank,toilet,kitchen,roof slab 40 d 22-08-22 30-09-22 0% 13% Procurement - Material - Water proof for water tank,toilet,kitchen,roof slab
715 Procurement - Water proof for water tank,toilet,kitchen,roof slab - Select Vendor & Issued P.O. 10 d 22-08-22 31-08-22 0% 50% Procurement - Water proof for water tank,toilet,kitchen,roof slab - Select Vendor & Issued P.O. 31 Aug '22
716 Procurement - Water proof for water tank,toilet,kitchen,roof slab - Lead time 30 d 01-09-22 30-09-22 0% 0% Procurement - Water proof for water tank,toilet,kitchen,roof slab - Lead time
717 Procurement - Water proof for water tank,toilet,kitchen,roof slab - Mat on site 0d 30-09-22 30-09-22 0% 0%
718 Procurement - Material - Toilet partition 70 d 29-08-22 08-11-22 0% 0% Procurement - Material - Toilet partition
719 Procurement - Toilet partition - Select Vendor & Issued P.O. 10 d 29-08-22 07-09-22 0% 0% Procurement - Toilet partition - Select Vendor & Issued P.O.
720 Procurement - Toilet partition - Lead time 60 d 08-09-22 08-11-22 0% 0% Procurement - Toilet partition - Le
721 Procurement - Toilet partition - Mat on site 0d 08-11-22 08-11-22 0% 0%
722 Procurement - Material - Dry wall & Ceiling 50 d 05-09-22 26-10-22 0% 0% Procurement - Material - Dry wall & Ceiling
723 Procurement - Dry wall & Ceiling - Select Vendor & Issued P.O. 10 d 05-09-22 14-09-22 0% 0% Procurement - Dry wall & Ceiling - Select Vendor & Issued P.O.
724 Procurement - Dry wall & Ceiling - Lead time 40 d 15-09-22 26-10-22 0% 0% Procureme
725 Procurement - Dry wall & Ceiling - Mat on site 0d 26-10-22 26-10-22 0% 0%
726 Procurement - Material - Floor hardener 20 d 16-09-22 05-10-22 0% 0% Pr
727 Procurement - Floor hardener - Select Vendor & Issued P.O. 10 d 16-09-22 25-09-22 0% 0% Procurement - Floor h
728 Procurement - Floor hardener - Lead time 10 d 26-09-22 05-10-22 0% 0%
729 Procurement - Floor hardener - Mat on site 0d 05-10-22 05-10-22 0% 0%
730 Construction 322 d 15-06-2222-05-238.38509316770186%
3% Construction

731 Main Factory 322 d 15-06-22 22-05-23 8.38509316770186%


4% Main Factory

732 Main Factory - Structural Work 241 d 15-06-22 21-02-23 11.2033195020747%


5% Main Factory - Structural Work

733 Main Factory - Structural Work - Zone A 225 d 15-06-22 05-02-23 12% 6% Main Factory - Structural Work - Zone A

734 Main Factory - Structural Work - Zone A1 190 d 15-06-22 28-12-22 14.2105263157895%
10% Main Factory - Structural Work - Zone A1

735 Main Factory - Substructure- Zone A1 82 d 15-06-22 08-09-22 32.9268292682927%


36% Main Factory - Substructure- Zone A1

736 Zone A1 - Pile Cut-off Level 21 d 15-06-22 05-07-22 100% 100% Zone A1 - Pile Cut-off Level 05 Jul '22

737 Zone A1.2 - Pile Cut-off Level 7d 15-06-22 21-06-22 100% 100% Zone A1.2 - Pile Cut-off Level 21 Jun '22
738 Zone A1.1 - Pile Cut-off Level 7d 22-06-22 28-06-22 100% 100% Zone A1.1 - Pile Cut-off Level 28 Jun '22
739 Zone A1.3 - Pile Cut-off Level 7d 29-06-22 05-07-22 100% 100% Zone A1.3 - Pile Cut-off Level 05 Jul '22
740 Zone A1 - Soil backfill under slab 27 d 22-06-22 19-07-22 74.0740740740741%
75% Zone A1 - Soil backfill under slab 19 Jul '22

741 Zone A1.2 - Soil backfill under slab 9d 22-06-22 30-06-22 100% 100% Zone A1.2 - Soil backfill under slab 30 Jun '22
742 Zone A1.1 - Soil backfill under slab 9d 01-07-22 09-07-22 100% 100% Zone A1.1 - Soil backfill under slab 09 Jul '22
743 Zone A1.3 - Soil backfill under slab 9d 10-07-22 19-07-22 22.2222222222222%
25% Zone A1.3 - Soil backfill under slab 19 Jul '22
744 Zone A1 - Foundation and Pier 33 d 09-07-2214-08-229.09090909090909%
2% Zone A1 - Foundation and Pier 14 Aug '22

745 Zone A1.2 - Foundation and Pier 11 d 09-07-22 20-07-22 27.2727272727273%


5% Zone A1.2 - Foundation and Pier 20 Jul '22
746 Zone A1.1 - Foundation and Pier 11 d 21-07-22 02-08-22 0% 0% Zone A1.1 - Foundation and Pier 02 Aug '22
747 Zone A1.3 - Foundation and Pier 11 d 03-08-22 14-08-22 0% 0% Zone A1.3 - Foundation and Pier 14 Aug '22
748 Zone A1 - Pca.Column, Core wall, Gr.Beam 36 d 03-08-22 08-09-22 0% 0% Zone A1 - Pca.Column, Core wall, Gr.Beam

749 Zone A1.2 - Pca.Column, Core wall, Gr.Beam 12 d 03-08-22 15-08-22 0% 0% Zone A1.2 - Pca.Column, Core wall, Gr.Beam 15 Aug '22
750 Zone A1.1 - Pca.Column, Core wall, Gr.Beam 12 d 16-08-22 27-08-22 0% 0% Zone A1.1 - Pca.Column, Core wall, Gr.Beam 27 Aug '22
751 Zone A1.3 - Pca.Column, Core wall, Gr.Beam 12 d 28-08-22 08-09-22 0% 0% Zone A1.3 - Pca.Column, Core wall, Gr.Beam
752 Main Factory - Underground Piping Work - Zone A1 32 d 24-08-2224-09-220% 0% Main Factory - Underground Piping Work - Zone A1

753 Zone A1 - U/G Toilet x 3 Rm. 32 d 24-08-22 24-09-22 0% 0% Zone A1 - U/G Toilet x 3 Rm.
754 Zone A1 - U/G Toilet x 3 Rm. - Excavation 6d 24-08-22 29-08-22 0% 0% Zone A1 - U/G Toilet x 3 Rm. - Excavation 29 Aug '22
755 Zone A1 - U/G Toilet x 3 Rm. - Sand Compacted 6d 26-08-22 31-08-22 0% 0% Zone A1 - U/G Toilet x 3 Rm. - Sand Compacted 31 Aug '22
756 Zone A1 - U/G Toilet x 3 Rm. - Install Pipes 20 d 28-08-22 16-09-22 0% 0% Zone A1 - U/G Toilet x 3 Rm. - Install Pipes
757 Zone A1 - U/G Toilet x 3 Rm. - Pressure Test 6d 17-09-22 22-09-22 0% 0% Z
758 Zone A1 - U/G Toilet x 3 Rm. - Inspection (Kajima & CM) 2d 23-09-22 24-09-22 0% 0%
759 Zone A1 - U/G Pipe 16 d 30-08-22 14-09-22 0% 0% Zone A1 - U/G Pipe
760 Zone A1 - U/G Pipe - Excavation 7d 30-08-22 05-09-22
0% 0% Zone A1 - U/G Pipe - Excavation
761 Zone A1 - U/G Pipe - Sand Compacted 7d 31-08-22 06-09-22
0% 0% Zone A1 - U/G Pipe - Sand Compacted
762 Zone A1 - U/G Pipe - Install Pipes 10 d 01-09-22 10-09-22
0% 0% Zone A1 - U/G Pipe - Install Pipes
763 Zone A1 - U/G Pipe - Pressure Test 10 d 03-09-22 12-09-22
0% 0% Zone A1 - U/G Pipe - Pressure Test
764 Zone A1 - U/G Pipe - Inspection (Kajima & CM) 2d 13-09-22 14-09-22
0% 0% Zone A1 - U/G Pipe
765 Main Factory - Roof Work - Zone A1 88 d 20-08-22 17-11-22 0% 0% Main Factory - Roof Work - Zone A1

766 Zone A1 - Roof Steel Structure 34 d 20-08-22 22-09-22 0% 0% Zone A1 - Roof Steel Structure

767 Zone A1.1&1.2 - Roof Steel Structure 17 d 20-08-22 05-09-22 0% 0% Zone A1.1&1.2 - Roof Steel Structure
768 Zone A1.2&1.3 - Roof Steel Structure 17 d 06-09-22 22-09-22 0% 0% Zone A1.2&1.3 - Roof Steel Structur
769 Zone A1 - Roof Matel Sheet 70 d 07-09-22 17-11-22 0% 0% Zone A1 - Roof Matel S

770 Zone A1.1&1.2 - Roof Matel Sheet 35 d 07-09-22 11-10-22 0% 0% Zone A1.1&1.2 - Roof Matel S
771 Zone A1.2&1.3 - Roof Matel Sheet 35 d 12-10-22 17-11-22 0% 0%
772 Main Factory - Post Tension Slab - Zone A1 92 d 25-09-22 28-12-22 0% 0%
773 Zone A1 - PT Slab Floor 1 69 d 25-09-22 04-12-22 0% 0%
774 Zone A1.2 - PT Slab Floor 1 23 d 25-09-22 18-10-22 0% 0%
775 Zone A1.1 - PT Slab Floor 1 23 d 19-10-22 11-11-22 0% 0%
776 Zone A1.3 - PT Slab Floor 1 23 d 12-11-22 04-12-22 0% 0%
777 Zone A1 - PT Slab Floor 2 69 d 19-10-22 28-12-22 0% 0%
778 Zone A1.2 - PT Slab Floor 2 23 d 19-10-22 11-11-22 0% 0%
779 Zone A1.1 - PT Slab Floor 2 23 d 12-11-22 04-12-22 0% 0%
780 Zone A1.3 - PT Slab Floor 2 23 d 06-12-22 28-12-22 0% 0%
781 Main Factory - Structural Work - Zone A2 187 d 29-06-22 12-01-23 6.95187165775401%
5% Main Factory - Structural Work - Zone A2

782 Main Factory - Substructure- Zone A2 82 d 29-06-22 22-09-22 15.8536585365854%


17% Main Factory - Substructure- Zone A2

9 OF 16
PROJECT : Relief Project
MASTER SCHEDULE (REV0.01) Dated 11Jul22
ID Task Name Duration Start Finish Planned
% Complete
%
Complete Jun Jul Aug
30-05 06-06 13-06 20-06 27-06 04-07 11-07 18-07 25-07 01-08 08-08 15-08 22-08 29-08
783 Zone A2 - Pile Cut-off Level 21 d 29-06-22 20-07-22 61.9047619047619%
77% Zone A2 - Pile Cut-off Level 11 Jul, '22 20 Jul '22

784 Zone A2.2 - Pile Cut-off Level 7d 29-06-22 05-07-22 100% 100% Zone A2.2 - Pile Cut-off Level 05 Jul '22
785 Zone A2.1 - Pile Cut-off Level 7d 06-07-22 12-07-22 85.7142857142857%
100% Zone A2.1 - Pile Cut-off Level 12 Jul '22
786 Zone A2.3 - Pile Cut-off Level 7d 14-07-22 20-07-22 0% 30% Zone A2.3 - Pile Cut-off Level 20 Jul '22
787 Zone A2 - Soil backfill under slab 27 d 06-07-22 04-08-22 22.2222222222222%
22% Zone A2 - Soil backfill under slab 04 Aug '22

788 Zone A2.2 - Soil backfill under slab 9d 06-07-22 15-07-22 66.6666666666667%
67% Zone A2.2 - Soil backfill under slab 15 Jul '22
789 Zone A2.1 - Soil backfill under slab 9d 16-07-22 24-07-22 0% 0% Zone A2.1 - Soil backfill under slab 24 Jul '22
790 Zone A2.3 - Soil backfill under slab 9d 25-07-22 04-08-22 0% 0% Zone A2.3 - Soil backfill under slab 04 Aug '22
791 Zone A2 - Foundation and Pier 45 d 16-07-2201-09-220% 0% Zone A2 - Foundation and Pier 01 Sep '22

792 Zone A2.2 - Foundation and Pier 15 d 16-07-22 01-08-22 0% 0% Zone A2.2 - Foundation and Pier 01 Aug '22
793 Zone A2.1 - Foundation and Pier 15 d 02-08-22 17-08-22 0% 0% Zone A2.1 - Foundation and Pier 17 Aug '22
794 Zone A2.3 - Foundation and Pier 15 d 18-08-22 01-09-22 0% 0% Zone A2.3 - Foundation and Pier 01 Sep '22
795 Zone A2 - PCa.Column, Core wall, Gr.Beam 36 d 18-08-22 22-09-22 0% 0% Zone A2 - PCa.Column, Core wall, Gr.Beam

796 Zone A2.2 - Pca.Column, Core wall, Gr.Beam 12 d 18-08-22 29-08-22 0% 0% Zone A2.2 - Pca.Column, Core wall, Gr.Beam 29 Aug '22
797 Zone A2.1 - Pca.Column, Core wall, Gr.Beam 12 d 30-08-22 10-09-22 0% 0% Zone A2.1 - Pca.Column, Core wall, Gr.Beam
798 Zone A2.3 - Pca.Column, Core wall, Gr.Beam 12 d 11-09-22 22-09-22 0% 0% Zone A2.3 - Pca.Column,
799 Main Factory - Underground Piping Work - Zone A2 16 d 22-09-2207-10-220% 0%
800 Zone A2 - U/G Pipe 16 d 22-09-22 07-10-22 0% 0%
801 Zone A2 - U/G Pipe - Excavation 7d 22-09-22 28-09-22
0% 0%
802 Zone A2 - U/G Pipe - Sand Compacted 7d 23-09-22 29-09-22
0% 0%
803 Zone A2 - U/G Pipe - Install Pipes 10 d 24-09-22 03-10-22
0% 0%
804 Zone A2 - U/G Pipe - Pressure Test 10 d 26-09-22 05-10-22
0% 0%
805 Zone A2 - U/G Pipe - Inspection (Kajima & CM) 2d 06-10-22 07-10-22
0% 0%
806 Main Factory - Roof Work - Zone A2 87 d 02-09-22 29-11-22 0% 0% Main Factory - Roof Work - Zone A2

807 Zone A2 - Roof Steel Structure 34 d 02-09-22 05-10-22 0% 0% Zone A2 - Roof Steel Structure

808 Zone A2.1&2.2 - Roof Steel Structure 17 d 02-09-22 18-09-22 0% 0% Zone A2.1&2.2 - Roof Steel Structure
809 Zone A2.2&2.3 - Roof Steel Structure 17 d 19-09-22 05-10-22 0% 0%
810 Zone A2 - Roof Matel Sheet 70 d 19-09-22 29-11-22 0% 0%
811 Zone A2.1&2.2 - Roof Matel Sheet 35 d 19-09-22 25-10-22 0% 0%
812 Zone A2.2&2.3 - Roof Matel Sheet 35 d 26-10-22 29-11-22 0% 0%
813 Main Factory - Post Tension Slab - Zone A2 90 d 08-10-22 12-01-23 0% 0%
814 Zone A2 - PT Slab Floor 1 69 d 08-10-22 18-12-22 0% 0%
815 Zone A2.2 - PT Slab Floor 1 23 d 08-10-22 01-11-22 0% 0%
816 Zone A2.1 - PT Slab Floor 1 23 d 02-11-22 24-11-22 0% 0%
817 Zone A2.3 - PT Slab Floor 1 23 d 25-11-22 18-12-22 0% 0%
818 Zone A2 - PT Slab Floor 2 69 d 31-10-22 12-01-23 0% 0%
819 Zone A2.2 - PT Slab Floor 2 23 d 31-10-22 22-11-22 0% 0%
820 Zone A2.1 - PT Slab Floor 2 23 d 23-11-22 16-12-22 0% 0%
821 Zone A2.3 - PT Slab Floor 2 23 d 17-12-22 12-01-23 0% 0%
822 Main Factory - Structural Work - Zone A3 197 d 14-07-22 05-02-23 0% 3% Main Factory - Structural Work - Zone A3

823 Main Factory - Substructure- Zone A3 81 d 14-07-22 05-10-22 0% 12% Main Factory - Substructure- Zone A3

824 Zone A3 - Pile Cut-off Level 21 d 14-07-22 05-08-22 0% 75% Zone A3 - Pile Cut-off Level 05 Aug '22

825 Zone A3.2 - Pile Cut-off Level 7d 14-07-22 20-07-22 0% 75% Zone A3.2 - Pile Cut-off Level 20 Jul '22
826 Zone A3.1 - Pile Cut-off Level 7d 21-07-22 27-07-22 0% 75% Zone A3.1 - Pile Cut-off Level 27 Jul '22
827 Zone A3.3 - Pile Cut-off Level 7d 30-07-22 05-08-22 0% 75% Zone A3.3 - Pile Cut-off Level 05 Aug '22
828 Zone A3 - Soil backfill under slab 27 d 21-07-22 19-08-22 0% 0% Zone A3 - Soil backfill under slab 19 Aug '22

829 Zone A3.2 - Soil backfill under slab 9d 21-07-22 31-07-22 0% 0% Zone A3.2 - Soil backfill under slab 31 Jul '22
830 Zone A3.1 - Soil backfill under slab 9d 01-08-22 09-08-22 0% 0% Zone A3.1 - Soil backfill under slab 09 Aug '22
831 Zone A3.3 - Soil backfill under slab 9d 10-08-22 19-08-22 0% 0% Zone A3.3 - Soil backfill under slab 19 Aug '22
832 Zone A3 - Foundation and Pier 45 d 01-08-2215-09-220% 0% Zone A3 - Foundation and Pier

833 Zone A3.2 - Foundation and Pier 15 d 01-08-22 16-08-22 0% 0% Zone A3.2 - Foundation and Pier 16 Aug '22
834 Zone A3.1 - Foundation and Pier 15 d 17-08-22 31-08-22 0% 0% Zone A3.1 - Foundation and Pier 31 Aug '22
835 Zone A3.3 - Foundation and Pier 15 d 01-09-22 15-09-22 0% 0% Zone A3.3 - Foundation and Pier
836 Zone A3 - PCa.Column, Core wall, Gr.Beam 36 d 31-08-22 05-10-22 0% 0% Zone A3 - PCa.Column, Core wall, Gr.Beam

837 Zone A3.2 - Pca.Column, Core wall, Gr.Beam 12 d 31-08-22 11-09-22 0% 0% Zone A3.2 - Pca.Column, Core wall, Gr.Beam
838 Zone A3.1 - Pca.Column, Core wall, Gr.Beam 12 d 12-09-22 23-09-22 0% 0% Zone A3.1 - Pca.Colum
839 Zone A3.3 - Pca.Column, Core wall, Gr.Beam 12 d 24-09-22 05-10-22 0% 0%
840 Main Factory - Underground Piping Work - Zone A3 32 d 18-09-2220-10-220% 0% Main F

841 Zone A3 - U/G Toilet x 3 Rm. 32 d 18-09-22 20-10-22 0% 0%


842 Zone A3 - U/G Toilet x 3 Rm. - Excavation 6d 18-09-22 23-09-22 0% 0%
843 Zone A3 - U/G Toilet x 3 Rm. - Sand Compacted 6d 20-09-22 25-09-22 0% 0%
844 Zone A3 - U/G Toilet x 3 Rm. - Install Pipes 20 d 22-09-22 11-10-22 0% 0%
845 Zone A3 - U/G Toilet x 3 Rm. - Pressure Test 6d 12-10-22 18-10-22 0% 0%
846 Zone A3 - U/G Toilet x 3 Rm. - Inspection (Kajima & CM) 2d 19-10-22 20-10-22 0% 0%
847 Zone A3 - U/G Pipe 16 d 24-09-22 09-10-22 0% 0%
848 Zone A3 - U/G Pipe - Excavation 7d 24-09-22 30-09-22
0% 0%
849 Zone A3 - U/G Pipe - Sand Compacted 7d 25-09-22 01-10-22
0% 0%
850 Zone A3 - U/G Pipe - Install Pipes 10 d 26-09-22 05-10-22
0% 0%
851 Zone A3 - U/G Pipe - Pressure Test 10 d 28-09-22 07-10-22
0% 0%
852 Zone A3 - U/G Pipe - Inspection (Kajima & CM) 2d 08-10-22 09-10-22
0% 0%
853 Main Factory - Roof Work - Zone A3 87 d 26-09-22 24-12-22 0% 0%
854 Zone A3 - Roof Steel Structure 36 d 26-09-22 02-11-22 0% 0%
855 Zone A3.1&3.2 - Roof Steel Structure 17 d 26-09-22 12-10-22 0% 0%
856 Zone A3.2&3.3 - Roof Steel Structure 17 d 16-10-22 02-11-22 0% 0%
857 Zone A3 - Roof Matel Sheet 70 d 14-10-22 24-12-22 0% 0%
858 Zone A3.1&3.2 - Roof Matel Sheet 35 d 14-10-22 18-11-22 0% 0%
859 Zone A3.2&3.3 - Roof Matel Sheet 35 d 19-11-22 24-12-22 0% 0%
860 Main Factory - Post Tension Slab - Zone A3 102 d 21-10-22 05-02-23 0% 0%
861 Zone A3 - PT Slab Floor 1 69 d 21-10-22 03-01-23 0% 0%
862 Zone A3.2 - PT Slab Floor 1 23 d 21-10-22 13-11-22 0% 0%
863 Zone A3.1 - PT Slab Floor 1 23 d 14-11-22 07-12-22 0% 0%
864 Zone A3.3 - PT Slab Floor 1 23 d 08-12-22 03-01-23 0% 0%
865 Zone A3 - PT Slab Floor 2 79 d 14-11-22 05-02-23 0% 0%
866 Zone A3.2 - PT Slab Floor 2 23 d 14-11-22 07-12-22 0% 0%
867 Zone A3.1 - PT Slab Floor 2 23 d 08-12-22 03-01-23 0% 0%
868 Zone A3.3 - PT Slab Floor 2 33 d 04-01-23 05-02-23 0% 0%

10 OF 16
PROJECT : Relief Project
MASTER SCHEDULE (REV0.01) Dated 11Jul22
ID Task Name Duration Start Finish Planned
% Complete
%
Complete Jun Jul Aug
30-05 06-06 13-06 20-06 27-06 04-07 11-07 18-07 25-07 01-08 08-08 15-08 22-08 29-08
869 Main Factory - Structural Work - Zone B 238 d 18-06-22 21-02-23 10.0840336134454%
5% Main Factory - Structural Work - Zone B 11 Jul, '22
870 Main Factory - Structural Work - Zone B1 195 d 18-06-22 09-01-23 12.3076923076923%
9% Main Factory - Structural Work - Zone B1

871 Main Factory - Substructure- Zone B1 82 d 18-06-22 11-09-22 29.2682926829268%


29% Main Factory - Substructure- Zone B1

872 Zone B1 - Pile Cut-off Level 21 d 18-06-22 08-07-22 100% 100% Zone B1 - Pile Cut-off Level 08 Jul '22

873 Zone B1.1 - Pile Cut-off Level 7d 18-06-22 24-06-22 100% 100% Zone B1.1 - Pile Cut-off Level 24 Jun '22
874 Zone B1.2 - Pile Cut-off Level 7d 25-06-22 01-07-22 100% 100% Zone B1.2 - Pile Cut-off Level 01 Jul '22
875 Zone B1.3 - Pile Cut-off Level 7d 02-07-22 08-07-22 100% 100% Zone B1.3 - Pile Cut-off Level 08 Jul '22
876 Zone B1 - Soil backfill under slab 27 d 25-06-22 22-07-22 62.962962962963%
63% Zone B1 - Soil backfill under slab 22 Jul '22

877 Zone B1.1 - Soil backfill under slab 9d 25-06-22 03-07-22 100% 100% Zone B1.1 - Soil backfill under slab 03 Jul '22
878 Zone B1.2 - Soil backfill under slab 9d 04-07-22 12-07-22 88.8888888888889%
89% Zone B1.2 - Soil backfill under slab 12 Jul '22
879 Zone B1.3 - Soil backfill under slab 9d 14-07-22 22-07-22 0% 0% Zone B1.3 - Soil backfill under slab 22 Jul '22
880 Zone B1 - Foundation and Pier 45 d 04-07-2221-08-2217.7777777777778%
0% Zone B1 - Foundation and Pier 21 Aug '22

881 Zone B1.1 - Foundation and Pier 15 d 04-07-22 19-07-22 53.3333333333333%


0% Zone B1.1 - Foundation and Pier 19 Jul '22
882 Zone B1.2 - Foundation and Pier 15 d 20-07-22 05-08-22 0% 0% Zone B1.2 - Foundation and Pier 05 Aug '22
883 Zone B1.3 - Foundation and Pier 15 d 06-08-22 21-08-22 0% 0% Zone B1.3 - Foundation and Pier 21 Aug '22
884 Zone B1 - PCa.Column, Core wall, Gr.Beam 36 d 06-08-22 11-09-22 0% 0% Zone B1 - PCa.Column, Core wall, Gr.Beam

885 Zone B1.1 - Pca.Column, Core wall, Gr.Beam 12 d 06-08-22 18-08-22 0% 0% Zone B1.1 - Pca.Column, Core wall, Gr.Beam 18 Aug '22
886 Zone B1.2 - Pca.Column, Core wall, Gr.Beam 12 d 19-08-22 30-08-22 0% 0% Zone B1.2 - Pca.Column, Core wall, Gr.Beam 30 Aug '22
887 Zone B1.3 - Pca.Column, Core wall, Gr.Beam 12 d 31-08-22 11-09-22 0% 0% Zone B1.3 - Pca.Column, Core wall, Gr.Beam
888 Main Factory - Underground Piping Work - Zone B1 22 d 04-09-2225-09-220% 0% Main Factory - Underground Piping Work - Zone B1

889 Zone B1 - U/G Toilet x 1 Rm. 22 d 04-09-22 25-09-22 0% 0% Zone B1 - U/G Toilet x 1 Rm.
890 Zone B1 - U/G Toilet x 1 Rm. - Excavation 4d 04-09-22 07-09-22 0% 0% Zone B1 - U/G Toilet x 1 Rm. - Excavation
891 Zone B1 - U/G Toilet x 1 Rm. - Sand Compacted 4d 06-09-22 09-09-22 0% 0% Zone B1 - U/G Toilet x 1 Rm. - Sand Compacte
892 Zone B1 - U/G Toilet x 1 Rm. - Install Pipes 13 d 08-09-22 20-09-22 0% 0% Zone B1 - U/G Toilet x 1 Rm. - Inst
893 Zone B1 - U/G Toilet x 1 Rm. - Pressure Test 3d 21-09-22 23-09-22 0% 0%
894 Zone B1 - U/G Toilet x 1 Rm. - Inspection (Kajima & CM) 2d 24-09-22 25-09-22 0% 0%
895 Zone B1 - U/G Pipe 16 d 08-09-22 23-09-22 0% 0% Zone B1 - U
896 Zone B1 - U/G Pipe - Excavation 7d 08-09-22 14-09-22
0% 0% Zone B1 - U/G Pipe - Ex
897 Zone B1 - U/G Pipe - Sand Compacted 7d 09-09-22 15-09-22
0% 0% Zone B1 - U/G Pipe - Sand
898 Zone B1 - U/G Pipe - Install Pipes 10 d 10-09-22 19-09-22
0% 0% Zone B1 - U/G Pi
899 Zone B1 - U/G Pipe - Pressure Test 10 d 12-09-22 21-09-22
0% 0% Zone B1 - U
900 Zone B1 - U/G Pipe - Inspection (Kajima & CM) 2d 22-09-22 23-09-22
0% 0%
901 Main Factory - Roof Work - Zone B1 88 d 20-08-22 17-11-22 0% 0% Main Factory - Roof Work - Zone B1

902 Zone B1 - Roof Steel Structure 34 d 20-08-22 22-09-22 0% 0% Zone B1 - Roof Steel Structure

903 Zone B1.1&1.2 - Roof Steel Structure 17 d 20-08-22 05-09-22 0% 0% Zone B1.1&1.2 - Roof Steel Structure
904 Zone B1.2&1.3 - Roof Steel Structure 17 d 06-09-22 22-09-22 0% 0% Zone B1.2&1.3 - Roof Steel Structur
905 Zone B1 - Roof Matel Sheet 70 d 07-09-22 17-11-22 0% 0% Zone B1 - Roof Matel S

906 Zone B1.1&1.2 - Roof Matel Sheet 35 d 07-09-22 11-10-22 0% 0% Zone B1.1&1.2 - Roof Matel S
907 Zone B1.2&1.3 - Roof Matel Sheet 35 d 12-10-22 17-11-22 0% 0%
908 Main Factory - Post Tension Slab - Zone B1 92 d 03-10-22 09-01-23 0% 0%
909 Zone B1 - PT Slab Floor 1 69 d 03-10-22 13-12-22 0% 0%
910 Zone B1.1 - PT Slab Floor 1 23 d 03-10-22 27-10-22 0% 0%
911 Zone B1.2 - PT Slab Floor 1 23 d 28-10-22 19-11-22 0% 0%
912 Zone B1.3 - PT Slab Floor 1 23 d 20-11-22 13-12-22 0% 0%
913 Zone B1 - PT Slab Floor 2 69 d 28-10-22 09-01-23 0% 0%
914 Zone B1.1 - PT Slab Floor 2 23 d 28-10-22 19-11-22 0% 0%
915 Zone B1.2 - PT Slab Floor 2 23 d 20-11-22 13-12-22 0% 0%
916 Zone B1.3 - PT Slab Floor 2 23 d 14-12-22 09-01-23 0% 0%
917 Main Factory - Structural Work - Zone B2 189 d 02-07-22 17-01-23 5.29100529100529%
4% Main Factory - Structural Work - Zone B2

918 Main Factory - Substructure- Zone B2 82 d 02-07-22 25-09-22 12.1951219512195%


14% Main Factory - Substructure- Zone B2

919 Zone B2 - Pile Cut-off Level 21 d 02-07-22 23-07-22 47.6190476190476%


70% Zone B2 - Pile Cut-off Level 23 Jul '22

920 Zone B2.1 - Pile Cut-off Level 7d 02-07-22 08-07-22 100% 100% Zone B2.1 - Pile Cut-off Level 08 Jul '22
921 Zone B2.2 - Pile Cut-off Level 7d 09-07-22 16-07-22 42.8571428571429%
55% Zone B2.2 - Pile Cut-off Level 16 Jul '22
922 Zone B2.3 - Pile Cut-off Level 7d 17-07-22 23-07-22 0% 55% Zone B2.3 - Pile Cut-off Level 23 Jul '22
923 Zone B2 - Soil backfill under slab 27 d 09-07-22 07-08-22 11.1111111111111%
12% Zone B2 - Soil backfill under slab 07 Aug '22

924 Zone B2.1 - Soil backfill under slab 9d 09-07-22 18-07-22 33.3333333333333%
35% Zone B2.1 - Soil backfill under slab 18 Jul '22
925 Zone B2.2 - Soil backfill under slab 9d 19-07-22 27-07-22 0% 0% Zone B2.2 - Soil backfill under slab 27 Jul '22
926 Zone B2.3 - Soil backfill under slab 9d 30-07-22 07-08-22 0% 0% Zone B2.3 - Soil backfill under slab 07 Aug '22
927 Zone B2 - Foundation and Pier 45 d 19-07-2204-09-220% 0% Zone B2 - Foundation and Pier

928 Zone B2.1 - Foundation and Pier 15 d 19-07-22 04-08-22 0% 0% Zone B2.1 - Foundation and Pier 04 Aug '22
929 Zone B2.2 - Foundation and Pier 15 d 05-08-22 20-08-22 0% 0% Zone B2.2 - Foundation and Pier 20 Aug '22
930 Zone B2.3 - Foundation and Pier 15 d 21-08-22 04-09-22 0% 0% Zone B2.3 - Foundation and Pier
931 Zone B2 - PCa.Column, Core wall, Gr.Beam 36 d 21-08-22 25-09-22 0% 0% Zone B2 - PCa.Column, Core wall, Gr.Beam

932 Zone B2.1 - Pca.Column, Core wall, Gr.Beam 12 d 21-08-22 01-09-22 0% 0% Zone B2.1 - Pca.Column, Core wall, Gr.Beam 01 Sep '22
933 Zone B2.2 - Pca.Column, Core wall, Gr.Beam 12 d 02-09-22 13-09-22 0% 0% Zone B2.2 - Pca.Column, Core wall, Gr.Beam
934 Zone B2.3 - Pca.Column, Core wall, Gr.Beam 12 d 14-09-22 25-09-22 0% 0% Zone B2.3 - Pc
935 Main Factory - Underground Piping Work - Zone B2 22 d 17-09-2208-10-220% 0% Main Fact

936 Zone B2 - U/G Toilet x 1 Rm. 22 d 17-09-22 08-10-22 0% 0%


937 Zone B2 - U/G Toilet x 1 Rm. - Excavation 4d 17-09-22 20-09-22 0% 0%
938 Zone B2 - U/G Toilet x 1 Rm. - Sand Compacted 4d 19-09-22 22-09-22 0% 0%
939 Zone B2 - U/G Toilet x 1 Rm. - Install Pipes 13 d 21-09-22 03-10-22 0% 0%
940 Zone B2 - U/G Toilet x 1 Rm. - Pressure Test 3d 04-10-22 06-10-22 0% 0%
941 Zone B2 - U/G Toilet x 1 Rm. - Inspection (Kajima & CM) 2d 07-10-22 08-10-22 0% 0%
942 Zone B2 - U/G Pipe 16 d 21-09-22 06-10-22 0% 0%
943 Zone B2 - U/G Pipe - Excavation 7d 21-09-22 27-09-22
0% 0%
944 Zone B2 - U/G Pipe - Sand Compacted 7d 22-09-22 28-09-22
0% 0%
945 Zone B2 - U/G Pipe - Install Pipes 10 d 23-09-22 02-10-22
0% 0%
946 Zone B2 - U/G Pipe - Pressure Test 10 d 25-09-22 04-10-22
0% 0%
947 Zone B2 - U/G Pipe - Inspection (Kajima & CM) 2d 05-10-22 06-10-22
0% 0%
948 Main Factory - Roof Work - Zone B2 94 d 02-09-22 07-12-22 0% 0% Main Factory - Roof Work - Zone B2

949 Zone B2 - Roof Steel Structure 34 d 02-09-22 05-10-22 0% 0% Zone B2 - Roof Steel Structure

950 Zone B2.1&2.2 - Roof Steel Structure 17 d 02-09-22 18-09-22 0% 0% Zone B2.1&2.2 - Roof Steel Structure
951 Zone B2.2&2.3 - Roof Steel Structure 17 d 19-09-22 05-10-22 0% 0%
952 Zone B2 - Roof Matel Sheet 77 d 19-09-22 07-12-22 0% 0%
953 Zone B2.1&2.2 - Roof Matel Sheet 35 d 19-09-22 25-10-22 0% 0%
954 Zone B2.2&2.3 - Roof Matel Sheet 42 d 26-10-22 07-12-22 0% 0%

11 OF 16
PROJECT : Relief Project
MASTER SCHEDULE (REV0.01) Dated 11Jul22
ID Task Name Duration Start Finish Planned
% Complete
%
Complete Jun Jul Aug
30-05 06-06 13-06 20-06 27-06 04-07 11-07 18-07 25-07 01-08 08-08 15-08 22-08 29-08
955 Main Factory - Post Tension Slab - Zone B2 94 d 09-10-22 17-01-23 0% 0% 11 Jul, '22
956 Zone B2 - PT Slab Floor 1 69 d 09-10-22 19-12-22 0% 0%
957 Zone B2.1 - PT Slab Floor 1 23 d 09-10-22 02-11-22 0% 0%
958 Zone B2.2 - PT Slab Floor 1 23 d 03-11-22 25-11-22 0% 0%
959 Zone B2.3 - PT Slab Floor 1 23 d 26-11-22 19-12-22 0% 0%
960 Zone B2 - PT Slab Floor 2 73 d 01-11-22 17-01-23 0% 0%
961 Zone B2.1 - PT Slab Floor 2 23 d 01-11-22 23-11-22 0% 0%
962 Zone B2.2 - PT Slab Floor 2 23 d 24-11-22 17-12-22 0% 0%
963 Zone B2.3 - PT Slab Floor 2 27 d 18-12-22 17-01-23 0% 0%
964 Main Factory - Structural Work - Zone B3 192 d 17-07-22 03-02-23 0% 5% Main Factory - Structural Work - Zone B3

965 Main Factory - Substructure- Zone B3 82 d 17-07-22 09-10-22 0% 16% Main Factory - Substructure- Zone B3

966 Zone B3 - Pile Cut-off Level 21 d 17-07-22 08-08-22 0% 100% Zone B3 - Pile Cut-off Level 08 Aug '22

967 Zone B3.1 - Pile Cut-off Level 7d 17-07-22 23-07-22 0% 100% Zone B3.1 - Pile Cut-off Level 23 Jul '22
968 Zone B3.2 - Pile Cut-off Level 7d 24-07-22 01-08-22 0% 100% Zone B3.2 - Pile Cut-off Level 01 Aug '22
969 Zone B3.3 - Pile Cut-off Level 7d 02-08-22 08-08-22 0% 100% Zone B3.3 - Pile Cut-off Level 08 Aug '22
970 Zone B3 - Soil backfill under slab 27 d 24-07-22 22-08-22 0% 0% Zone B3 - Soil backfill under slab 22 Aug '22

971 Zone B3.1 - Soil backfill under slab 9d 24-07-22 03-08-22 0% 0% Zone B3.1 - Soil backfill under slab 03 Aug '22
972 Zone B3.2 - Soil backfill under slab 9d 04-08-22 13-08-22 0% 0% Zone B3.2 - Soil backfill under slab 13 Aug '22
973 Zone B3.3 - Soil backfill under slab 9d 14-08-22 22-08-22 0% 0% Zone B3.3 - Soil backfill under slab 22 Aug '22
974 Zone B3 - Foundation and Pier 45 d 04-08-2218-09-220% 0% Zone B3 - Foundation and Pier

975 Zone B3.1 - Foundation and Pier 15 d 04-08-22 19-08-22 0% 0% Zone B3.1 - Foundation and Pier 19 Aug '22
976 Zone B3.2 - Foundation and Pier 15 d 20-08-22 03-09-22 0% 0% Zone B3.2 - Foundation and Pier 03 S
977 Zone B3.3 - Foundation and Pier 15 d 04-09-22 18-09-22 0% 0% Zone B3.3 - Foundation and Pier
978 Zone B3 - PCa.Column, Core wall, Gr.Beam 36 d 04-09-22 09-10-22 0% 0% Zone B3 - PCa.Column, Core wall, Gr.Beam

979 Zone B3.1 - Pca.Column, Core wall, Gr.Beam 12 d 04-09-22 15-09-22 0% 0% Zone B3.1 - Pca.Column, Core wall, Gr.Beam
980 Zone B3.2 - Pca.Column, Core wall, Gr.Beam 12 d 16-09-22 27-09-22 0% 0% Zone B
981 Zone B3.3 - Pca.Column, Core wall, Gr.Beam 12 d 28-09-22 09-10-22 0% 0%
982 Main Factory - Underground Piping Work - Zone B3 16 d 07-10-2223-10-220% 0%
983 Zone B3 - U/G Pipe 16 d 07-10-22 23-10-22 0% 0%
984 Zone B3 - U/G Pipe - Excavation 7d 07-10-22 14-10-22
0% 0%
985 Zone B3 - U/G Pipe - Sand Compacted 7d 08-10-22 15-10-22
0% 0%
986 Zone B3 - U/G Pipe - Install Pipes 10 d 09-10-22 19-10-22
0% 0%
987 Zone B3 - U/G Pipe - Pressure Test 10 d 11-10-22 21-10-22
0% 0%
988 Zone B3 - U/G Pipe - Inspection (Kajima & CM) 2d 22-10-22 23-10-22
0% 0%
989 Main Factory - Roof Work - Zone B3 87 d 16-09-22 14-12-22 0% 0%
990 Zone B3 - Roof Steel Structure 34 d 16-09-22 20-10-22 0% 0%
991 Zone B3.1&3.2 - Roof Steel Structure 17 d 16-09-22 02-10-22 0% 0%
992 Zone B3.2&3.3 - Roof Steel Structure 17 d 03-10-22 20-10-22 0% 0%
993 Zone B3 - Roof Matel Sheet 70 d 03-10-22 14-12-22 0% 0%
994 Zone B3.1&3.2 - Roof Matel Sheet 35 d 03-10-22 08-11-22 0% 0%
995 Zone B3.2&3.3 - Roof Matel Sheet 35 d 09-11-22 14-12-22 0% 0%
996 Main Factory - Post Tension Slab - Zone B3 97 d 25-10-22 03-02-23 0% 0%
997 Zone B3 - PT Slab Floor 1 69 d 25-10-22 06-01-23 0% 0%
998 Zone B3.1 - PT Slab Floor 1 23 d 25-10-22 16-11-22 0% 0%
999 Zone B3.2 - PT Slab Floor 1 23 d 17-11-22 10-12-22 0% 0%
1000 Zone B3.3 - PT Slab Floor 1 23 d 11-12-22 06-01-23 0% 0%
1001 Zone B3 - PT Slab Floor 2 74 d 17-11-22 03-02-23 0% 0%
1002 Zone B3.1 - PT Slab Floor 2 23 d 17-11-22 10-12-22 0% 0%
1003 Zone B3.2 - PT Slab Floor 2 23 d 11-12-22 06-01-23 0% 0%
1004 Zone B3.3 - PT Slab Floor 2 28 d 07-01-23 03-02-23 0% 0%
1005 Main Factory - Structural Work - Zone B4 196 d 02-08-22 21-02-23 0% 2% Main Factory - Structural Work - Zone B4

1006 Main Factory - Substructure- Zone B4 82 d 02-08-22 25-10-22 0% 6% Main Factory - Substructure- Zone B4

1007 Zone B4 - Pile Cut-off Level 21 d 02-08-22 23-08-22 0% 35% Zone B4 - Pile Cut-off Level 23 Aug '22

1008 Zone B4.1 - Pile Cut-off Level 7d 02-08-22 08-08-22 0% 35% Zone B4.1 - Pile Cut-off Level 08 Aug '22
1009 Zone B4.2 - Pile Cut-off Level 7d 09-08-22 16-08-22 0% 35% Zone B4.2 - Pile Cut-off Level 16 Aug '22
1010 Zone B4.3 - Pile Cut-off Level 7d 17-08-22 23-08-22 0% 35% Zone B4.3 - Pile Cut-off Level 23 Aug '22
1011 Zone B4 - Soil backfill under slab 27 d 09-08-22 05-09-22 0% 0% Zone B4 - Soil backfill under slab

1012 Zone B4.1 - Soil backfill under slab 9d 09-08-22 18-08-22 0% 0% Zone B4.1 - Soil backfill under slab 18 Aug '22
1013 Zone B4.2 - Soil backfill under slab 9d 19-08-22 27-08-22 0% 0% Zone B4.2 - Soil backfill under slab 27 Aug '22
1014 Zone B4.3 - Soil backfill under slab 9d 28-08-22 05-09-22 0% 0% Zone B4.3 - Soil backfill under slab
1015 Zone B4 - Foundation and Pier 45 d 19-08-2202-10-220% 0% Zone B4 - Foundation and Pier

1016 Zone B4.1 - Foundation and Pier 15 d 19-08-22 02-09-22 0% 0% Zone B4.1 - Foundation and Pier 02 Sep
1017 Zone B4.2 - Foundation and Pier 15 d 03-09-22 17-09-22 0% 0% Zone B4.2 - Foundation and Pier
1018 Zone B4.3 - Foundation and Pier 15 d 18-09-22 02-10-22 0% 0%
1019 Zone B4 - PCa.Column, Core wall, Gr.Beam 36 d 18-09-22 25-10-22 0% 0%
1020 Zone B4.1 - Pca.Column, Core wall, Gr.Beam 12 d 18-09-22 29-09-22 0% 0%
1021 Zone B4.2 - Pca.Column, Core wall, Gr.Beam 12 d 30-09-22 11-10-22 0% 0%
1022 Zone B4.3 - Pca.Column, Core wall, Gr.Beam 12 d 12-10-22 25-10-22 0% 0%
1023 Main Factory - Underground Piping Work - Zone B4 22 d 16-10-2207-11-220% 0%
1024 Zone B4 - U/G Toilet x 1 Rm. 22 d 16-10-22 07-11-22 0% 0%
1025 Zone B4 - U/G Toilet x 1 Rm. - Excavation 4d 16-10-22 19-10-22 0% 0%
1026 Zone B4 - U/G Toilet x 1 Rm. - Sand Compacted 4d 18-10-22 21-10-22 0% 0%
1027 Zone B4 - U/G Toilet x 1 Rm. - Install Pipes 13 d 20-10-22 02-11-22 0% 0%
1028 Zone B4 - U/G Toilet x 1 Rm. - Pressure Test 3d 03-11-22 05-11-22 0% 0%
1029 Zone B4 - U/G Toilet x 1 Rm. - Inspection (Kajima & CM) 2d 06-11-22 07-11-22 0% 0%
1030 Zone B4 - U/G Pipe 16 d 20-10-22 05-11-22 0% 0%
1031 Zone B4 - U/G Pipe - Excavation 7d 20-10-22 27-10-22
0% 0%
1032 Zone B4 - U/G Pipe - Sand Compacted 7d 21-10-22 28-10-22
0% 0%
1033 Zone B4 - U/G Pipe - Install Pipes 10 d 22-10-22 01-11-22
0% 0%
1034 Zone B4 - U/G Pipe - Pressure Test 10 d 25-10-22 03-11-22
0% 0%
1035 Zone B4 - U/G Pipe - Inspection (Kajima & CM) 2d 04-11-22 05-11-22
0% 0%
1036 Main Factory - Roof Work - Zone B4 95 d 30-09-22 09-01-23 0% 0%
1037 Zone B4 - Roof Steel Structure 34 d 30-09-22 04-11-22 0% 0%
1038 Zone B4.1&4.2 - Roof Steel Structure 17 d 30-09-22 17-10-22 0% 0%
1039 Zone B4.2&4.3 - Roof Steel Structure 17 d 18-10-22 04-11-22 0% 0%
1040 Zone B4 - Roof Matel Sheet 78 d 18-10-22 09-01-23 0% 0%

12 OF 16
PROJECT : Relief Project
MASTER SCHEDULE (REV0.01) Dated 11Jul22
ID Task Name Duration Start Finish Planned
% Complete
%
Complete Jun Jul Aug
30-05 06-06 13-06 20-06 27-06 04-07 11-07 18-07 25-07 01-08 08-08 15-08 22-08 29-08
1041 Zone B4.1&4.2 - Roof Matel Sheet 39 d 18-10-22 26-11-22 0% 0% 11 Jul, '22
1042 Zone B4.2&4.3 - Roof Matel Sheet 39 d 27-11-22 09-01-23 0% 0%
1043 Main Factory - Post Tension Slab - Zone B4 101 d 08-11-22 21-02-23 0% 0%
1044 Zone B4 - PT Slab Floor 1 70 d 08-11-22 21-01-23 0% 0%
1045 Zone B4.1 - PT Slab Floor 1 23 d 08-11-22 30-11-22 0% 0%
1046 Zone B4.2 - PT Slab Floor 1 23 d 01-12-22 24-12-22 0% 0%
1047 Zone B4.3 - PT Slab Floor 1 24 d 25-12-22 21-01-23 0% 0%
1048 Zone B4 - PT Slab Floor 2 78 d 01-12-22 21-02-23 0% 0%
1049 Zone B4.1 - PT Slab Floor 2 26 d 01-12-22 27-12-22 0% 0%
1050 Zone B4.2 - PT Slab Floor 2 26 d 28-12-22 26-01-23 0% 0%
1051 Zone B4.3 - PT Slab Floor 2 26 d 27-01-23 21-02-23 0% 0%
1052 Main Factory - Architectural Work 180 d 31-10-22 12-05-23 0% 0%
1053 Main Factory - Architectural Work - Zone A 180 d 31-10-22 12-05-23 0% 0%
1054 Zone A - 1F.&2F. Interior block wall & Dry wall 121 d 31-10-22 05-03-23 0% 0%
1055 Zone A - Pca.Wall installation 84 d 14-11-22 10-02-23 0% 0%
1056 Zone A - 1F&2F. Toilet wall & floor ceramic tile / RC.Stair 98 d 06-12-22 18-03-23 0% 0%
1057 Zone A - 1F&2F. Shutter, Door & Window 98 d 29-12-22 11-04-23 0% 0%
1058 Zone A - 1F.&2F. Ceiling finishes 70 d 16-01-23 27-03-23 0% 0%
1059 Zone A - 1F.&2F. Floor finishes 70 d 16-02-23 05-05-23 0% 0%
1060 Zone A - Dock leveler installation 42 d 10-03-23 26-04-23 0% 0%
1061 Zone A - 1F.&2F. Miscellaneous finishing 28 d 08-04-23 12-05-23 0% 0%
1062 Main Factory - Architectural Work - Zone B 179 d 01-11-22 12-05-23 0% 0%
1063 Zone B - 1F.&2F. Interior block wall & Dry wall 112 d 01-11-22 25-02-23 0% 0%
1064 Zone B - Pca.Wall installation 84 d 15-11-22 11-02-23 0% 0%
1065 Zone B - 1F&2F. Toilet wall & floor ceramic tile / RC.Stair 98 d 07-12-22 19-03-23 0% 0%
1066 Zone B - 1F&2F. Shutter, Door & Window 98 d 28-12-22 10-04-23 0% 0%
1067 Zone B - 1F.&2F. Ceiling finishes 70 d 15-01-23 26-03-23 0% 0%
1068 Zone B - 1F.&2F. Floor finishes 70 d 16-02-23 05-05-23 0% 0%
1069 Zone B - Dock leveler installation 42 d 10-03-23 26-04-23 0% 0%
1070 Zone B - 1F.&2F. Miscellaneous finishing 28 d 08-04-23 12-05-23 0% 0%
1071 Main Factory - MEP work by other (Not TKC Scope of Work, TKC is not 141 d 19-08-22 14-01-23 0% 0% Main Factory - MEP work by other (Not TKC Scope of Work, TKC is not responsible)

responsible)
1072 Main Factory - MEP Work - Roof Truss (Installation Fire fighting pipe) 41 d 19-08-22 29-09-22 0% 0% Main Factory - MEP Work - Roof Truss (Installation Fire fighting pipe)

1073 Zone A1 - Roof Truss - Completed MEP Installation Fire Fighting pipe at Roof Truss 0d 19-08-22 19-08-22 0% 0% Zone A1 - Roof Truss - Completed MEP Installation Fire Fighting pipe at Roof Truss 19 Aug '22
1074 Zone A2 - Roof Truss - Completed MEP Installation Fire Fighting pipe at Roof Truss 0d 01-09-22 01-09-22 0% 0% Zone A2 - Roof Truss - Completed MEP Installation Fire Fighting pipe at Roof Truss 01 Sep '22
1075 Zone A3 - Roof Truss - Completed MEP Installation Fire Fighting pipe at Roof Truss 0d 25-09-22 25-09-22 0% 0% Zone A3

1076 Zone B1 - Roof Truss - Completed MEP Installation Fire Fighting pipe at Roof Truss 0d 19-08-22 19-08-22 0% 0% Zone B1 - Roof Truss - Completed MEP Installation Fire Fighting pipe at Roof Truss 19 Aug '22
1077 Zone B2 - Roof Truss - Completed MEP Installation Fire Fighting pipe at Roof Truss 0d 01-09-22 01-09-22 0% 0% Zone B2 - Roof Truss - Completed MEP Installation Fire Fighting pipe at Roof Truss 01 Sep '22
1078 Zone B3 - Roof Truss - Completed MEP Installation Fire Fighting pipe at Roof Truss 0d 15-09-22 15-09-22 0% 0% Zone B3 - Roof Truss - Completed MEP Install

1079 Zone B4 - Roof Truss - Completed MEP Installation Fire Fighting pipe at Roof Truss 0d 29-09-22 29-09-22 0% 0%
1080 Main Factory - MEP Installation 57 d 13-11-22 14-01-23 0% 0%
1081 Main Factory - MEP Installation Fixed - Zone A 56 d 13-11-22 13-01-23 0% 0%
1082 Main Factory - MEP Installation Fixed Zone A - Start 0d 13-11-22 13-11-22 0% 0%
1083 Main Factory - MEP Installation Fixed Zone A - Completed 0d 13-01-23 13-01-23 0% 0%
1084 Main Factory - MEP Installation Fixed - Zone B 56 d 14-11-22 14-01-23 0% 0%
1085 Main Factory - MEP Installation Fixed Zone B - Start 0d 14-11-22 14-11-22 0% 0%
1086 Main Factory - MEP Installation Fixed Zone B - Completed 0d 14-01-23 14-01-23 0% 0%
1087 Main Factory - Inspection 17 d 06-05-23 22-05-23 0% 0%
1088 Main Factory - Inspection - Zone A 17 d 06-05-2322-05-230% 0%
1089 Zone A - TKC Inspection 12 d 06-05-23 17-05-23 0% 0%
1090 Zone A - Consultant & Owner Inspection 10 d 13-05-23 22-05-23 0% 0%
1091 Main Factory - Inspection - Zone B 17 d 06-05-2322-05-230% 0%
1092 Zone B - TKC Inspection 12 d 06-05-23 17-05-23 0% 0%
1093 Zone B - Consultant & Owner Inspection 10 d 13-05-23 22-05-23 0% 0%
1094 Office and Canteen 322 d 15-06-22 22-05-23 8.38509316770186%
3% Office and Canteen

1095 Office and Canteen - Structural Work 200 d 15-06-22 11-01-23 13.5% 11% Office and Canteen - Structural Work

1096 Office and Canteen - Substructure 82 d 15-06-22 08-09-22 32.9268292682927%


33% Office and Canteen - Substructure

1097 Office and Canteen - Pile Cut-off Level 21 d 15-06-22 05-07-22 100% 100% Office and Canteen - Pile Cut-off Level 05 Jul '22

1098 Office and Canteen (O2) - Pile Cut-off Level 7d 15-06-22 21-06-22 100% 100% Office and Canteen (O2) - Pile Cut-off Level 21 Jun '22
1099 Office and Canteen (O1) - Pile Cut-off Level 7d 22-06-22 28-06-22 100% 100% Office and Canteen (O1) - Pile Cut-off Level 28 Jun '22
1100 Office and Canteen (O3) - Pile Cut-off Level 7d 29-06-22 05-07-22 100% 100% Office and Canteen (O3) - Pile Cut-off Level 05 Jul '22
1101 Office and Canteen - Soil backfill under slab 27 d 22-06-22 19-07-22 74.0740740740741%
75% Office and Canteen - Soil backfill under slab 19 Jul '22

1102 Office and Canteen (O2) - Soil backfill under slab 9d 22-06-22 30-06-22 100% 100% Office and Canteen (O2) - Soil backfill under slab 30 Jun '22
1103 Office and Canteen (O1) - Soil backfill under slab 9d 01-07-22 09-07-22 100% 100% Office and Canteen (O1) - Soil backfill under slab 09 Jul '22
1104 Office and Canteen (O3) - Soil backfill under slab 9d 10-07-22 19-07-22 22.2222222222222%
25% Office and Canteen (O3) - Soil backfill under slab 19 Jul '22
1105 Office and Canteen - Foundation and Pier 45 d 01-07-2218-08-2224.4444444444444%
3% Office and Canteen - Foundation and Pier 18 Aug '22

1106 Office and Canteen (O2) - Foundation and Pier 15 d 01-07-22 16-07-22 73.3333333333333%
8% Office and Canteen (O2) - Foundation and Pier 16 Jul '22
1107 Office and Canteen (O1) - Foundation and Pier 15 d 17-07-22 02-08-22 0% 0% Office and Canteen (O1) - Foundation and Pier 02 Aug '22
1108 Office and Canteen (O3) - Foundation and Pier 15 d 03-08-22 18-08-22 0% 0% Office and Canteen (O3) - Foundation and Pier 18 Aug '22
1109 Office and Canteen - PCa.Column, Core wall, Gr.Beam 36 d 03-08-22 08-09-22 0% 0% Office and Canteen - PCa.Column, Core wall, Gr.Beam

1110 Office and Canteen (O2) - Pca.Column, Core wall, Gr.Beam 12 d 03-08-22 15-08-22 0% 0% Office and Canteen (O2) - Pca.Column, Core wall, Gr.Beam 15 Aug '22
1111 Office and Canteen (O1) - Pca.Column, Core wall, Gr.Beam 12 d 16-08-22 27-08-22 0% 0% Office and Canteen (O1) - Pca.Column, Core wall, Gr.Beam 27 Aug '22
1112 Office and Canteen (O3) - Pca.Column, Core wall, Gr.Beam 12 d 28-08-22 08-09-22 0% 0% Office and Canteen (O3) - Pca.Column, Core wall, Gr.Beam
1113 Office and Canteen - Underground Piping Work 26 d 03-08-2229-08-220% 0% Office and Canteen - Underground Piping Work 29 Aug '22

1114 Office and Canteen - U/G Toilet x 3 Rm. 26 d 03-08-22 29-08-22 0% 0% Office and Canteen - U/G Toilet x 3 Rm. 29 Aug '22
1115 Office and Canteen - U/G Toilet x 3 Rm. - Excavation 4d 03-08-22 06-08-22 0% 0% Office and Canteen - U/G Toilet x 3 Rm. - Excavation 06 Aug '22
1116 Office and Canteen - U/G Toilet x 3 Rm. - Sand Compacted 4d 05-08-22 08-08-22 0% 0% Office and Canteen - U/G Toilet x 3 Rm. - Sand Compacted 08 Aug '22
1117 Office and Canteen - U/G Toilet x 3 Rm. - Install Pipes 14 d 07-08-22 21-08-22 0% 0% Office and Canteen - U/G Toilet x 3 Rm. - Install Pipes 21 Aug '22
1118 Office and Canteen - U/G Toilet x 3 Rm. - Pressure Test 6d 22-08-22 27-08-22 0% 0% Office and Canteen - U/G Toilet x 3 Rm. - Pressure Test 27 Aug '22
1119 Office and Canteen - U/G Toilet x 3 Rm. - Inspection (Kajima & CM) 2d 28-08-22 29-08-22 0% 0% Office and Canteen - U/G Toilet x 3 Rm. - Inspection (Kajima & CM) 29 Aug '22
1120 Office and Canteen - U/G Pipe 20 d 03-08-22 23-08-22 0% 0% Office and Canteen - U/G Pipe 23 Aug '22
1121 Office and Canteen - U/G Pipe - Excavation 7d 03-08-22 09-08-22 0% 0% Office and Canteen - U/G Pipe - Excavation 09 Aug '22
1122 Office and Canteen - U/G Pipe - Sand Compacted 7d 04-08-22 10-08-22 0% 0% Office and Canteen - U/G Pipe - Sand Compacted 10 Aug '22
1123 Office and Canteen - U/G Pipe - Install Pipes 10 d 09-08-22 19-08-22 0% 0% Office and Canteen - U/G Pipe - Install Pipes 19 Aug '22
1124 Office and Canteen - U/G Pipe - Pressure Test 10 d 11-08-22 21-08-22 0% 0% Office and Canteen - U/G Pipe - Pressure Test 21 Aug '22
1125 Office and Canteen - U/G Pipe - Inspection (Kajima & CM) 2d 22-08-22 23-08-22 0% 0% Office and Canteen - U/G Pipe - Inspection (Kajima & CM) 23 Aug '22

13 OF 16
PROJECT : Relief Project
MASTER SCHEDULE (REV0.01) Dated 11Jul22
ID Task Name Duration Start Finish Planned
% Complete
%
Complete Jun Jul Aug
30-05 06-06 13-06 20-06 27-06 04-07 11-07 18-07 25-07 01-08 08-08 15-08 22-08 29-08
1126 Office and Canteen - Post Tension Slab 86 d 24-08-22 19-11-22 0% 0% 11 Jul, '22 Office and Canteen - Post Tension Slab

1127 Office and Canteen - PT Slab, RC Slab - Floor 1 32 d 24-08-22 24-09-22 0% 0% Office and Canteen - PT Slab, RC Slab - Floor 1

1128 Office and Canteen (O2) - PT Slab, RC Slab - Floor 1 9d 24-08-22 01-09-22 0% 0% Office and Canteen (O2) - PT Slab, RC Slab - Floor 1 01 Sep '22
1129 Office and Canteen (O1) - PT Slab, RC Slab - Floor 1 9d 02-09-22 10-09-22 0% 0% Office and Canteen (O1) - PT Slab, RC Slab - Floor 1
1130 Office and Canteen (O3) - PT Slab, RC Slab - Floor 1 14 d 11-09-22 24-09-22 0% 0% Office and Canteen (O3) - PT Sl
1131 Office and Canteen - PT Slab, RC Slab - Floor M 36 d 07-09-22 12-10-22 0% 0% Office and Canteen - PT Slab, RC Slab - Flo

1132 Office and Canteen (O2) - PT Slab, RC Slab - Floor M 12 d 07-09-22 18-09-22 0% 0% Office and Canteen (O2) - PT Slab, RC Slab - Flo
1133 Office and Canteen (O1) - PT Slab, RC Slab - Floor M 12 d 19-09-22 30-09-22 0% 0% Of
1134 Office and Canteen (O3) - PT Slab, RC Slab - Floor M 12 d 01-10-22 12-10-22 0% 0%
1135 Office and Canteen - PT Slab - Floor 2 36 d 25-09-22 01-11-22 0% 0%
1136 Office and Canteen (O2) - PT Slab - Floor 2 12 d 25-09-22 06-10-22 0% 0%
1137 Office and Canteen (O1) - PT Slab - Floor 2 12 d 07-10-22 19-10-22 0% 0%
1138 Office and Canteen (O3) - PT Slab - Floor 2 12 d 20-10-22 01-11-22 0% 0%
1139 Office and Canteen - PT Slab - PT Slab Roof 36 d 14-10-22 19-11-22 0% 0%
1140 Office and Canteen (O2) - PT Slab - Shade 12 d 14-10-22 26-10-22 0% 0%
1141 Office and Canteen (O1) - PT Slab - Shade 12 d 27-10-22 07-11-22 0% 0%
1142 Office and Canteen (O3) - PT Slab - Shade 12 d 08-11-22 19-11-22 0% 0%
1143 Office and Canteen - Roof Work 63 d 05-11-22 11-01-23 0% 0%
1144 Office and Canteen - Top Roof Part 35 d 05-11-22 10-12-22 0% 0%
1145 Office and Canteen - Waterprofing 28 d 11-12-22 11-01-23 0% 0%
1146 Office and Canteen - Landscape Area 102 d 12-01-2330-04-230% 0%
1147 Office and Canteen - Architectural Work 196 d 03-10-22 30-04-23 0% 0%
1148 Office and Canteen - Interior wall 112 d 03-10-22 29-01-23 0% 0%
1149 Office and Canteen - Interior wall - Floor 1 70 d 03-10-22 14-12-22 0% 0%
1150 Office and Canteen - Interior wall - Floor M 70 d 26-10-22 08-01-23 0% 0%
1151 Office and Canteen - Interior wall - Floor 2 70 d 16-11-22 29-01-230% 0%
1152 Office and Canteen - RC.Stair & Finishing 126 d 02-11-22 13-03-23 0% 0%
1153 Office and Canteen - Toilet wall tile 98 d 16-11-22 26-02-23 0% 0%
1154 Office and Canteen - Toilet wall tile - Floor 1 42 d 16-11-22 28-12-22 0% 0%
1155 Office and Canteen - Toilet wall tile - Floor M 42 d 15-12-22 29-01-23 0% 0%
1156 Office and Canteen - Toilet wall tile - Floor 2 42 d 16-01-23 26-02-23 0% 0%
1157 Office and Canteen - Toilet floor tile 84 d 29-12-22 27-03-23 0% 0%
1158 Office and Canteen - Toilet floor tile - Floor 1 28 d 29-12-22 29-01-23 0% 0%
1159 Office and Canteen - Toilet floor tile - Floor M 28 d 30-01-23 26-02-23 0% 0%
1160 Office and Canteen - Toilet floor tile - Floor 2 28 d 27-02-23 27-03-23 0% 0%
1161 Office and Canteen - Ceiling finishes 98 d 16-11-22 26-02-23 0% 0%
1162 Office and Canteen - Ceiling finishes - Floor 1 56 d 16-11-22 15-01-23 0% 0%
1163 Office and Canteen - Ceiling finishes - Floor M 56 d 08-12-22 05-02-23 0% 0%
1164 Office and Canteen - Ceiling finishes - Floor 2 56 d 29-12-22 26-02-23 0% 0%
1165 Office and Canteen - Foor finishes 98 d 29-12-22 11-04-23 0% 0%
1166 Office and Canteen - Foor finishes - Floor 1 56 d 29-12-22 26-02-23 0% 0%
1167 Office and Canteen - Foor finishes - Floor M 56 d 23-01-23 20-03-23 0% 0%
1168 Office and Canteen - Foor finishes - Floor 2 56 d 13-02-23 11-04-23 0% 0%
1169 Office and Canteen - 1F.~2F. Miscellaneous finishing 56 d 27-02-23 30-04-23 0% 0%
1170 Office and Canteen - Façade, Curtain wall, Door & Window 114 d 20-11-22 19-03-23 0% 0%
1171 Office and Canteen - Façade, Curtain wall, Door & Window - Floor 1 57 d 20-11-22 20-01-23 0% 0%
1172 Office and Canteen (O2) - Façade, Curtain wall, Door & Window - Floor 1 19 d 20-11-22 09-12-22 0% 0%
1173 Office and Canteen (O1) - Façade, Curtain wall, Door & Window - Floor 1 19 d 10-12-22 28-12-22 0% 0%
1174 Office and Canteen (O3) - Façade, Curtain wall, Door & Window - Floor 1 19 d 29-12-22 20-01-23
0% 0%
1175 Office and Canteen - Façade, Curtain wall, Door & Window - Floor 2 57 d 21-01-23 19-03-23
0% 0%
1176 Office and Canteen (O2) - Façade, Curtain wall, Door & Window - Floor 2 19 d 21-01-23 08-02-23
0% 0%
1177 Office and Canteen (O1) - Façade, Curtain wall, Door & Window - Floor 2 19 d 09-02-23 27-02-23
0% 0%
1178 Office and Canteen (O3) - Façade, Curtain wall, Door & Window - Floor 2 19 d 28-02-23 19-03-23
0% 0%
1179 Office and Canteen - MEP Installation by other (Not TKC Scope of Work, 70 d 17-10-2228-12-220% 0%
TKC is not responsible)
1180 Office and Canteen - MEP Installation Fixed Floor 1 28 d 17-10-2215-11-220% 0%
1181 Office and Canteen - MEP Installation Fixed Floor 1- Start 0d 17-10-22 17-10-22 0% 0%
1182 Office and Canteen - MEP Installation Fixed Floor 1- Completed 0d 15-11-22 15-11-22 0% 0%
1183 Office and Canteen - MEP Installation Fixed Floor M 28 d 08-11-2207-12-220% 0%
1184 Office and Canteen - MEP Installation Fixed Floor M - Start 0d 08-11-2208-11-22 0% 0%
1185 Office and Canteen - MEP Installation Fixed Floor M - Completed 0d 07-12-2207-12-22 0% 0%
1186 Office and Canteen - MEP Installation Fixed Floor 2 28 d 29-11-2228-12-220% 0%
1187 Office and Canteen - MEP Installation Fixed Floor 2 - Start 0d 29-11-2229-11-220% 0%
1188 Office and Canteen - MEP Installation Fixed Floor 2 - Completed 0d 28-12-2228-12-220% 0%
1189 Office and Canteen - Inspection 20 d 02-05-23 22-05-23 0% 0%
1190 Office and Canteen - TKC Inspection 14 d 02-05-23 16-05-23 0% 0%
1191 Office and Canteen - Consultant & Owner Inspection 13 d 10-05-23 22-05-23 0% 0%
1192 East Utility Building 150 d 19-06-22 21-11-22 15.3333333333333%
12% East Utility Building

1193 East Utility Building - Structural Work 128 d 19-06-22 30-10-22 17.96875%
15% East Utility Building - Structural Work

1194 East Utility Building - Substructure 69 d 19-06-22 30-08-22 33.3333333333333%


26% East Utility Building - Substructure 30 Aug '22

1195 East Utility Building - Pile Cut-off Level 21 d 19-06-22 09-07-22 100% 100% East Utility Building - Pile Cut-off Level 09 Jul '22

1196 East Utility Building (E1) - Pile Cut-off Level 7d 19-06-22 25-06-22 100% 100% East Utility Building (E1) - Pile Cut-off Level 25 Jun '22
1197 East Utility Building (E2) - Pile Cut-off Level 7d 26-06-22 02-07-22 100% 100% East Utility Building (E2) - Pile Cut-off Level 02 Jul '22
1198 East Utility Building (E3) - Pile Cut-off Level 7d 03-07-22 09-07-22 100% 100% East Utility Building (E3) - Pile Cut-off Level 09 Jul '22
1199 East Utility Building - Soil backfill under slab 27 d 26-06-22 23-07-22 59.2592592592593%
59% East Utility Building - Soil backfill under slab 23 Jul '22

1200 East Utility Building (E1) - Soil backfill under slab 9d 26-06-22 04-07-22 100% 100% East Utility Building (E1) - Soil backfill under slab 04 Jul '22
1201 East Utility Building (E2) - Soil backfill under slab 9d 05-07-22 14-07-22 77.7777777777778%
78% East Utility Building (E2) - Soil backfill under slab 14 Jul '22
1202 East Utility Building (E3) - Soil backfill under slab 9d 15-07-22 23-07-22 0% 0% East Utility Building (E3) - Soil backfill under slab 23 Jul '22
1203 East Utility Building - Foundation and Pier 27 d 05-07-2203-08-2225.9259259259259%
0% East Utility Building - Foundation and Pier 03 Aug '22

1204 East Utility Building (E1) - Foundation and Pier 9d 05-07-22 14-07-22 77.7777777777778%
0% East Utility Building (E1) - Foundation and Pier 14 Jul '22
1205 East Utility Building (E2) - Foundation and Pier 9d 15-07-22 23-07-22 0% 0% East Utility Building (E2) - Foundation and Pier 23 Jul '22

14 OF 16
PROJECT : Relief Project
MASTER SCHEDULE (REV0.01) Dated 11Jul22
ID Task Name Duration Start Finish Planned
% Complete
%
Complete Jun Jul Aug
30-05 06-06 13-06 20-06 27-06 04-07 11-07 18-07 25-07 01-08 08-08 15-08 22-08 29-08
1206 East Utility Building (E3) - Foundation and Pier 9d 24-07-22 03-08-22 0% 0% 11East
Jul, Utility
'22 Building (E3) - Foundation and Pier 03 Aug '22
1207 East Utility Building - Gr.Beam 42 d 10-07-22 24-08-22 4.76190476190476%
0% East Utility Building - Gr.Beam 24 Aug '22

1208 East Utility Building (E1) - Gr.Beam 14 d 10-07-22 24-07-22 14.2857142857143%


0% East Utility Building (E1) - Gr.Beam 24 Jul '22
1209 East Utility Building (E2) - Gr.Beam 14 d 25-07-22 09-08-22 0% 0% East Utility Building (E2) - Gr.Beam 09 Aug '22
1210 East Utility Building (E3) - Gr.Beam 14 d 10-08-22 24-08-22 0% 0% East Utility Building (E3) - Gr.Beam 24 Aug '22
1211 East Utility Building - Pca.Column 27 d 03-08-22 30-08-22 0% 0% East Utility Building - Pca.Column 30 Aug '22

1212 East Utility Building (E1) - Pca.Column 9d 03-08-22 11-08-22 0% 0% East Utility Building (E1) - Pca.Column 11 Aug '22
1213 East Utility Building (E2) - Pca.Column 9d 13-08-22 21-08-22 0% 0% East Utility Building (E2) - Pca.Column 21 Aug '22
1214 East Utility Building (E3) - Pca.Column 9d 22-08-22 30-08-22 0% 0% East Utility Building (E3) - Pca.Column 30 Aug '22
1215 East Utility Building - Post Tension Slab 38 d 20-08-22 26-09-22 0% 0% East Utility Building - Post Tension Slab

1216 East Utility Building - PT Slab Floor 1 24 d 20-08-22 12-09-22 0% 0% East Utility Building - PT Slab Floor 1

1217 East Utility Building (E1) - PT Slab Floor 1 8d 20-08-22 27-08-22 0% 0% East Utility Building (E1) - PT Slab Floor 1 27 Aug '22
1218 East Utility Building (E2) - PT Slab Floor 1 8d 28-08-22 04-09-22 0% 0% East Utility Building (E2) - PT Slab Floor 1
1219 East Utility Building (E3) - PT Slab Floor 1 8d 05-09-22 12-09-22 0% 0% East Utility Building (E3) - PT Slab Floor 1
1220 East Utility Building - PT Slab Roof Floor 24 d 03-09-22 26-09-22 0% 0% East Utility Building - PT Slab Roof Floor

1221 East Utility Building (E1) - PT Slab Roof Floor 8d 03-09-22 10-09-22 0% 0% East Utility Building (E1) - PT Slab Roof Floor
1222 East Utility Building (E2) - PT Slab Roof Floor 8d 11-09-22 18-09-22 0% 0% East Utility Building (E2)
1223 East Utility Building (E3) - PT Slab Roof Floor 8d 19-09-22 26-09-22 0% 0%
1224 East Utility Building - Roof Work 42 d 17-09-22 30-10-22 0% 0%
1225 East Utility Building - Aluminum trellis, Equip, FDN 21 d 17-09-22 07-10-22 0% 0% East Utili

1226 East Utility Building - Waterproofing 28 d 01-10-22 30-10-22 0% 0%


1227 East Utility Building - Architectural Work 35 d 08-10-22 13-11-22 0% 0%
1228 East Utility Building - Installation PC.wall & Interior block wall & Plastering 25 d 08-10-22 03-11-22 0% 0%
1229 East Utility Building - Shutter, Door & Window 18 d 23-10-22 10-11-22 0% 0%
1230 East Utility Building - Miscellaneous finishing 14 d 31-10-22 13-11-22 0% 0%
1231 East Utility Building - Inspection 14 d 07-11-22 20-11-22 0% 0%
1232 East Utility Building - TKC Inspection 11 d 07-11-22 17-11-22 0% 0%
1233 East Utility Building - Consultant & Owner Inspection 3d 18-11-22 20-11-22 0% 0%
1234 Handover to MEP Contractor for Installation Main Equipment 0d 21-11-22 21-11-22 0% 0%
1235 South Utility Building 206 d 19-06-22 21-01-23 11.1650485436893%
7% South Utility Building

1236 South Utility Building - Structural Work 164 d 19-06-22 06-12-22 14.0243902439024%
14% South Utility Building - Structural Work

1237 South Utility Building - Substructure 79 d 19-06-22 09-09-22 29.1139240506329%


25% South Utility Building - Substructure

1238 South Utility Building - Pile Cut-off Level 21 d 19-06-22 09-07-22 100% 100% South Utility Building - Pile Cut-off Level 09 Jul '22

1239 South Utility Building - Zone A - Pile Cut-off Level 21 d 19-06-22 09-07-22 100% 100% South Utility Building - Zone A - Pile Cut-off Level 09 Jul '22
1240 South Utility Building - Zone B - Pile Cut-off Level 21 d 19-06-22 09-07-22 100% 100% South Utility Building - Zone B - Pile Cut-off Level 09 Jul '22
1241 South Utility Building - Soil backfill under slab 28 d 26-06-22 24-07-22 57.1428571428571%
60% South Utility Building - Soil backfill under slab 24 Jul '22

1242 South Utility Building - Foundation and Pier 45 d 03-07-2220-08-2220% 3% South Utility Building - Foundation and Pier 20 Aug '22

1243 South Utility Building - Zone A - Foundation and Pier (GL.11-29) 45 d 03-07-22 20-08-22 20% 2% South Utility Building - Zone A - Foundation and Pier (GL.11-29) 20 Aug '22
1244 South Utility Building - Zone B - Foundation and Pier (GL.1.3-11) 39 d 09-07-22 20-08-22 7.69230769230769%
5% South Utility Building - Zone B - Foundation and Pier (GL.1.3-11) 20 Aug '22
1245 South Utility Building - Gr.Beam 30 d 31-07-22 30-08-22 0% 0% South Utility Building - Gr.Beam 30 Aug '22

1246 South Utility Building - Zone A - Gr.Beam 21 d 31-07-22 21-08-22 0% 0% South Utility Building - Zone A - Gr.Beam 21 Aug '22
1247 South Utility Building - Zone B - Gr.Beam 18 d 13-08-22 30-08-22 0% 0% South Utility Building - Zone B - Gr.Beam 30 Aug '22
1248 South Utility Building - Pca.Column 28 d 13-08-22 09-09-22 0% 0% South Utility Building - Pca.Column

1249 South Utility Building - Zone A - Pca.Column 28 d 13-08-22 09-09-22 0% 0% South Utility Building - Zone A - Pca.Column
1250 South Utility Building - Zone B - Pca.Column 28 d 13-08-22 09-09-22 0% 0% South Utility Building - Zone B - Pca.Column
1251 South Utility Building - Roof Work 42 d 27-08-22 07-10-22 0% 0% South Utility Building - Roof Work

1252 South Utility Building - Roof Steel Structure / RB2 28 d 27-08-22 23-09-22 0% 0% South Utility Building - Roof Steel Structure / RB2

1253 South Utility Building - Roof Matel Sheet, Cladding 28 d 10-09-22 07-10-22 0% 0% South Utility Building - Roof Matel

1254 South Utility Building - Post Tension Slab 42 d 24-09-22 06-11-22 0% 0%


1255 South Utility Building - PT Slab Floor 1 28 d 24-09-22 22-10-22 0% 0%
1256 South Utility Building - PT Slab Floor 1 (GL.1.3-4) 21 d 24-09-22 15-10-22 0% 0%
1257 South Utility Building - PT Slab Floor 1 (GL.4-11) 14 d 08-10-22 22-10-22 0% 0%
1258 South Utility Building - PT Slab Floor 2 28 d 08-10-22 06-11-22 0% 0%
1259 South Utility Building - PT Slab Floor 2 (GL.19-27) 21 d 08-10-22 30-10-22 0% 0%
1260 South Utility Building - PT Slab Floor 2 (GL.1.3-4) 21 d 16-10-22 06-11-22 0% 0%
1261 South Utility Building - PT Slab Floor 2 (GL.4-11) 14 d 23-10-22 06-11-22 0% 0%
1262 South Utility Building - Stair Work 36 d 31-10-22 06-12-22 0% 0%
1263 South Utility Building - RC.Stair, Link Bridge 28 d 31-10-22 27-11-22 0% 0%
1264 South Utility Building - External Stl. Staircase 18 d 18-11-22 06-12-22 0% 0%
1265 South Utility Building - Water Tank 137 d 20-07-22 09-12-22 0% 0% South Utility Building - Water Tank

1266 South Utility Building - WT.Base slab, RC. Slab 35 d 20-07-22 26-08-22 0% 0% South Utility Building - WT.Base slab, RC. Slab 26 Aug '22

1267 South Utility Building - WT.Base slab, RC. Slab (GL.27-Y) 10 d 20-07-22 31-07-22
0% 0% South Utility Building - WT.Base slab, RC. Slab (GL.27-Y) 31 Jul '22
1268 South Utility Building - WT.Base slab, RC. Slab (GL.22-27) 10 d 23-07-22 03-08-22
0% 0% South Utility Building - WT.Base slab, RC. Slab (GL.22-27) 03 Aug '22
1269 South Utility Building - WT.Base slab, RC. Slab (GL.19-22) 10 d 31-07-22 09-08-22
0% 0% South Utility Building - WT.Base slab, RC. Slab (GL.19-22) 09 Aug '22
1270 South Utility Building - WT.Base slab, RC. Slab (GL.15-19) 10 d 09-08-22 19-08-22
0% 0% South Utility Building - WT.Base slab, RC. Slab (GL.15-19) 19 Aug '22
1271 South Utility Building - WT.Base slab, RC. Slab (GL.11-1) 10 d 17-08-22 26-08-22
0% 0% South Utility Building - WT.Base slab, RC. Slab (GL.11-1) 26 Aug '22
1272 South Utility Building - WT.RC.Wall 41 d 27-08-22 06-10-22 0% 0% South Utility Building - WT.RC.Wall

1273 South Utility Building - WT.RC.Wall (GL.23-27) 13 d 27-08-22 08-09-22


0% 0% South Utility Building - WT.RC.Wall (GL.23-27)
1274 South Utility Building - WT.RC.Wall (GL.22-24) 13 d 06-09-22 18-09-22
0% 0% South Utility Building - WT.RC.Wall (GL.22-24
1275 South Utility Building - WT.RC.Wall (GL.19-22) 13 d 17-09-22 29-09-22
0% 0% Sout
1276 South Utility Building - Pca.column at WT.area (GL.23-27) 7d 09-09-22 15-09-22
0% 0% South Utility Building - Pca.column at WT.are
1277 South Utility Building - Pca.column at WT.area (GL.22-24) 7d 19-09-22 25-09-22
0% 0% South Ut
1278 South Utility Building - Pca.column at WT.area (GL.19-22) 7d 30-09-22 06-10-22
0% 0%
1279 South Utility Building - WT.Top slab 28 d 01-10-22 30-10-22 0% 0%
1280 South Utility Building - WT.Top slab (GL.22-27) 14 d 01-10-22 15-10-22 0% 0%
1281 South Utility Building - WT.Top slab (GL.19-22) 14 d 16-10-22 30-10-22 0% 0%
1282 South Utility Building - Rf.steel structure / RB2 21 d 31-10-22 20-11-22 0% 0%
1283 South Utility Building - Roof metal sht, Cladding 25 d 14-11-22 09-12-22 0% 0%
1284 South Utility Building - Architect Work 77 d 23-10-22 13-01-23 0% 0%
1285 South Utility Building - 1F.&2F. Installation PC.wall /Painting work 49 d 23-10-22 12-12-22 0% 0%
1286 South Utility Building - 1F&2F. Interior wall 35 d 07-11-22 12-12-22 0% 0%
1287 South Utility Building - 1F&2F. Wall tile & Celing finishes 35 d 14-11-22 19-12-22 0% 0%
1288 South Utility Building - 1F&2F. Shutter, Door & Window 35 d 21-11-22 26-12-22 0% 0%
1289 South Utility Building - 1F.&2F. Floor finishes 35 d 28-11-22 06-01-23 0% 0%

15 OF 16
PROJECT : Relief Project
MASTER SCHEDULE (REV0.01) Dated 11Jul22
ID Task Name Duration Start Finish Planned
% Complete
%
Complete Jun Jul Aug
30-05 06-06 13-06 20-06 27-06 04-07 11-07 18-07 25-07 01-08 08-08 15-08 22-08 29-08
1290 South Utility Building - 1F.&2F. Miscellaneous finishing 28 d 13-12-22 13-01-23 0% 0% 11 Jul, '22
1291 South Utility Building - MEP Work by other (Not TKC Scope of Work, TKC 77 d 26-08-22 13-11-22 0% 0% South Utility Building - MEP Work by other (Not TKC Scope of Work, TKC is not responsible)

is not responsible)
1292 South Utility Building - MEP Work - Roof Truss (Installation Fire fighting 0 d 26-08-22 26-08-22 0% 0% South Utility Building - MEP Work - Roof Truss (Installation Fire fighting pipe) 26 Aug '22

pipe)
1293 South Utility Building - Roof Truss - Completed MEP Installation Fire Fighting pipe at Roof 0 d 26-08-22 26-08-22 0% 0% South Utility Building - Roof Truss - Completed MEP Installation Fire Fighting pipe at Roof Truss 26 Aug '22
Truss
1294 South Utility Building - MEP Installation Fixed 14 d 30-10-22 13-11-22 0% 0%
1295 South Utility Building - MEP Installation Fixed - MEP Start 0d 30-10-22 30-10-22 0% 0%
1296 South Utility Building - MEP Installation Fixed - MEP Completed 0d 13-11-22 13-11-22 0% 0%
1297 South Utility Building - Inspection 15 d 06-01-23 20-01-23 0% 0%
1298 South Utility Building - TKC Inspection 8d 06-01-23 13-01-23 0% 0%
1299 South Utility Building - Consultant & Owner Inspection 7d 14-01-23 20-01-23 0% 0%
1300 South Utility Building - Handover to Owner 1d 21-01-23 21-01-23 0% 0%
1301 External Work 294 d 14-07-22 22-05-23 0% 0% External Work

1302 External Work - Retention pond 213 d 14-07-22 21-02-23 0% 0% External Work - Retention pond
1303 Retention Pond - Soil Excavation 63 d 14-07-22 17-09-22 0% 0% Retention Pond - Soil Excavation
1304 Retention Pond - Finishing work 30 d 23-01-23 21-02-23 0% 0%
1305 External Work - Boundary fence & Main entrance 292 d 16-07-22 22-05-23 0% 0% External Work - Boundary fence & Main entrance
1306 External Work - Boundary fence 292 d 16-07-22 22-05-23 0% 0% External Work - Boundary fence
1307 Mock up Boundary fence type 2 (West Side) 14 d 16-07-22 31-07-22 0% 0% Mock up Boundary fence type 2 (West Side) 31 Jul '22
1308 Boundary fence Team 1 - At Future Expansion (West Side) 114 d 01-08-22 25-11-22 0% 0% Boundary fence Team 1 - At Future Expansion (West Side)
1309 Mock up Boundary fence type 3 (North Side to East Side) 24 d 20-07-22 15-08-22 0% 0% Mock up Boundary fence type 3 (North Side to East Side) 15 Aug '22
1310 Mock up Boundary fence type 1 (North Side to East Side) 22 d 01-08-22 23-08-22 0% 0% Mock up Boundary fence type 1 (North Side to East Side) 23 Aug '22
1311 Boundary fence Team 2 - At Main Factory (North Side to East Side) 160 d 28-08-22 10-02-23 0% 0% Boundary fence Team 2 - At Main Factory (North Side to East Side)
1312 Boundary fence Team 3 - At Parking Area (South Side) 130 d 25-10-22 09-03-23 0% 0%
1313 Boundary fence Team 4 - At Retention Pond (South Side) 140 d 21-12-22 22-05-23 0% 0%
1314 External Work - Main entrance 60 d 16-03-23 22-05-23 0% 0%
1315 External Work - Stormwater drainage system 278 d 01-08-22 22-05-23 0% 0% External Work - Stormwater drainage system
1316 Stormwater drainage system Zone 1 - At Retention Pond 132 d 01-08-22 14-12-22 0% 0% Stormwater drainage system Zone 1 - At Retention Pond
1317 Stormwater drainage system Zone 2 - At Parking Area (South side) 168 d 23-08-22 13-02-23 0% 0% Stormwater drainage system Zone 2 - At Parking Area (South side)
1318 Stormwater drainage system Zone 3 - At Future Expansion 182 d 22-09-22 30-03-23 0% 0%
1319 Stormwater drainage system Zone 4 - At Main Factory 213 d 06-10-22 22-05-23 0% 0%
1320 External Work - Guardhouse & Custrm office 180 d 11-09-22 17-03-23 0% 0% External Work - Guardho
1321 External Work - Road & Pavement, Loading dock, Truck scale 215 d 04-10-22 22-05-23 0% 0%
1322 Road & Pavement Zone 1 - At Retention Pond 104 d 04-10-22 22-01-23 0% 0%
1323 Road & Pavement Zone 2 - At Parking Area (South side) 133 d 27-10-22 14-03-23 0% 0%
1324 Road & Pavement Zone 3 - At Future Expansion 154 d 19-11-22 05-05-23 0% 0%
1325 Road & Pavement Zone 4 - At Main Factory 157 d 03-12-22 22-05-23 0% 0%
1326 External Work - Car & Motorcycle parking (Southside) 194 d 27-10-22 22-05-23 0% 0%
1327 External Work - VIP & Visitor parking (Northside) 168 d 22-11-22 22-05-23 0% 0%
1328 External Work - Green area & Landscape 98 d 05-02-23 22-05-23 0% 0%
1329 External Work - Truck Scale 215 d 04-10-22 22-05-23 0% 0%
1330 External Work - Walk Way 238 d 11-09-22 22-05-23 0% 0% Extern
1331 External Work - Pipe Rack 81 d 22-02-23 22-05-23 0% 0%
1332 MEP Work by Other Contractor (Not TKC Scope of Work, TKC is not 231 d 15-08-22 11-04-23 0% 0% MEP Work by Other Contractor (Not TKC Scope of Work, TKC is not responsible)

responsible)
1333 MEP Work - Main Factory 231 d 15-08-22 11-04-23 0% 0% MEP Work - Main Factory
1334 MEP Work - Main Factory Zone A 231 d 15-08-22 11-04-23 0% 0% MEP Work - Main Factory Zone A
1335 Zone A1 - MEP Work at Roof Truss (Installation Fire fighting pipe) 5d 15-08-22 19-08-22 0% 0% Zone A1 - MEP Work at Roof Truss (Installation Fire fighting pipe) 19 Aug '22
1336 Zone A2 - MEP Work at Roof Truss (Installation Fire fighting pipe) 5d 28-08-22 01-09-22 0% 0% Zone A2 - MEP Work at Roof Truss (Installation Fire fighting pipe) 01 Sep '22
1337 Zone A3 - MEP Work at Roof Truss (Installation Fire fighting pipe) 5d 21-09-22 25-09-22 0% 0% Zone A3
1338 Zone A - MEP Installation Work (EE, AC and SN) 56 d 14-11-22 13-01-23 0% 0%
1339 Zone A - Testing & Commissioning 14 d 28-03-23 11-04-23 0% 0%
1340 MEP Work - Main Factory Zone B 231 d 15-08-22 11-04-23 0% 0% MEP Work - Main Factory Zone B
1341 Zone B1 - MEP Work at Roof Truss (Installation Fire fighting pipe) 5d 15-08-22 19-08-22 0% 0% Zone B1 - MEP Work at Roof Truss (Installation Fire fighting pipe) 19 Aug '22
1342 Zone B2 - MEP Work at Roof Truss (Installation Fire fighting pipe) 5d 28-08-22 01-09-22 0% 0% Zone B2 - MEP Work at Roof Truss (Installation Fire fighting pipe) 01 Sep '22
1343 Zone B3 - MEP Work at Roof Truss (Installation Fire fighting pipe) 5d 11-09-22 15-09-22 0% 0% Zone B3 - MEP Work at Roof Truss (Installatio
1344 Zone B4 - MEP Work at Roof Truss (Installation Fire fighting pipe) 5d 25-09-22 29-09-22 0% 0%
1345 Zone B - MEP Installation Work (EE, AC and SN) 56 d 15-11-22 14-01-23 0% 0%
1346 Zone B - Testing & Commissioning 14 d 28-03-23 11-04-23 0% 0%
1347 MEP Work - Office and Canteen 168 d 18-10-22 11-04-23 0% 0%
1348 Office and Canteen - MEP Installation Work (EE, AC and SN) - Floor 1 28 d 18-10-22 15-11-22 0% 0%
1349 Office and Canteen - MEP Installation Work (EE, AC and SN) - Floor M 28 d 09-11-22 07-12-22 0% 0%
1350 Office and Canteen - MEP Installation Work (EE, AC and SN) - Floor 2 28 d 30-11-22 28-12-22 0% 0%
1351 Office and Canteen - Testing & Commissioning 14 d 28-03-23 11-04-23 0% 0%
1352 MEP Work - East Building 120 d 22-11-22 27-03-23 0% 0%
1353 East Building - Installation Main Equipment 120 d 22-11-22 27-03-23 0% 0%
1354 MEP Work - South Building 82 d 22-08-22 13-11-22 0% 0% MEP Work - South Building
1355 South Building - MEP Work at Roof Truss (Installation Fire fighting pipe) 5d 22-08-22 26-08-22 0% 0% South Building - MEP Work at Roof Truss (Installation Fire fighting pipe) 26 Aug '22
1356 South Building - MEP Installation Work (EE, AC and SN) 14 d 31-10-22 13-11-22 0% 0%
1357 Handover & Practical Completion 90 d 23-02-23 01-06-23 0% 0%
1358 Handover & Practical Completion - As Built Drawing 90 d 23-02-23 01-06-23 0% 0%
1359 Handover & Practical Completion - Completed Document 90 d 23-02-23 01-06-23 0% 0%
1360 Practical Completion 0d 01-06-23 01-06-23 0% 0%