CH85 450 TO CH86 414 FULL Date Start Date Complete Workdone
ALADIN Volumne Weight Planning Overall Weight Section 1
ESTIMATED WORK LENGTH 964 m FULL 2 week % Weight
1 embankment fill 1.1.2022 24.1.2022 17,000.00 m3 4,200.00 25% 0.0067% 0.0270% 0.1700%
2 laying final chipping 10.1.2022 14.1.2022 1,680.00 m3 - 0% 0.0000% 0.0610% 0.2400%
3 intalltion of geotextile 15.1.2022 18.1.2022 350.00 m - 0% 0.0000% 0.0459% 0.2597%
4 surcharge fill 25.1.2022 21.2.2022 26,000.00 m3 500.00 2% 0.0009% 0.0490% 0.1337%
5 remove surcharge fill 22.8.2022 13.9.2022 7,800.00 m3 - 0% 0.0000% 0.0104% 0.0942%
6 subgrade preparation 10.9.2022 22.9.2022 964.00 m - 0% 0.0000% 0.0170% 0.0247%
7 subbase 20.9.2022 30.9.2022 964.00 m - 0% 0.0000% 0.1093% 0.1588%
8 roadbase 1st layer 25.9.2022 5.10.2022 964.00 m - 0% 0.0000% 0.0849% 0.1234%
9 roadbase 2nd layer 30.9.2022 10.10.2022 964.00 m - 0% 0.0000% 0.0849% 0.1234%
10 binder course 11.10.2022 17.10.2022 964.00 m - 0% 0.0000% 0.3469% 0.5042%
11 wearing course 24.10.2022 30.10.2022 964.00 m - 0% 0.0000% 0.1775% 0.2579%
CH86 675 TO CH86 950 FULL Date Start Date Complete Workdone
ALADIN Volumne Weight Planning Overall Weight Section 2
ESTIMATED WORK LENGTH 275 m FULL 2 week % Weight
1 subgrade preparation 1.1.2022 6.1.2022 275.00 m 275.00 100% 0.0024% 0.0024% 0.0419%
2 subbase 7.1.2022 12.1.2022 275.00 m - 0% 0.0000% 0.0156% 0.2691%
3 roadbase 1st layer 13.1.2022 18.1.2022 275.00 m - 0% 0.0000% 0.0121% 0.2091%
4 roadbase 2nd layer 19.1.2022 27.1.2022 275.00 m - 0% 0.0000% 0.0121% 0.2091%
5 binder course 28.1.2022 31.1.2022 275.00 m - 0% 0.0000% 0.0495% 0.8543%
6 wearing course 14.2.2022 17.2.2022 275.00 m - 0% 0.0000% 0.0253% 0.4370%
CH87 275 TO CH87 550 FULL Date Start Date Complete Workdone
ALADIN Volumne Weight Planning Overall Weight Section 2
ESTIMATED WORK LENGTH 275 m FULL 2 week % Weight
1 subgrade preparation 13.1.2022 18.1.2022 275.00 m 275.00 100% 0.0049% 0.0049% 0.0419%
2 subbase 19.1.2022 24.1.2022 275.00 m - 0% 0.0000% 0.0312% 0.2691%
3 roadbase 1st layer 25.1.2022 30.1.2022 275.00 m 275.00 100% 0.0242% 0.0242% 0.2091%
4 roadbase 2nd layer 31.1.2022 7.2.2022 275.00 m - 0% 0.0000% 0.0242% 0.2091%
5 binder course 8.2.2022 11.2.2022 275.00 m - 0% 0.0000% 0.0990% 0.8543%
6 wearing course 25.2.2022 28.2.2022 275.00 m - 0% 0.0000% 0.0506% 0.4370%
CH87 725 TO CH88 550 FULL Date Start Date Complete Workdone
ALADIN Volumne Weight Planning Overall Weight Section 2
ESTIMATED WORK LENGTH 825 m FULL 2 week % Weight
1 subgrade preparation 25.1.2022 7.2.2022 825.00 m 500.00 61% 0.0088% 0.0146% 0.0419%
2 subbase 8.2.2022 23.2.2022 825.00 m 500.00 61% 0.0567% 0.0935% 0.2691%
3 roadbase 1st layer 24.2.2022 9.3.2022 825.00 m 500.00 61% 0.0440% 0.0727% 0.2091%
4 roadbase 2nd layer 10.3.2022 2.4.2022 825.00 m - 0% 0.0000% 0.0727% 0.2091%
5 binder course 3.4.2022 12.4.2022 825.00 m - 0% 0.0000% 0.2969% 0.8543%
6 wearing course 13.4.2022 22.4.2022 825.00 m - 0% 0.0000% 0.1519% 0.4370%
CH88 450 TO CH89 350 RHS Date Start Date Complete Workdone
ALADIN Volumne Weight Planning Overall Weight Section 2 + 3
ESTIMATED WORK LENGTH 900 m RHS 2 week % Weight
1 remove surcharge fill 1.1.2022 10.1.2022 5,000.00 m3 - 0% 0.0000% 0.0033% 0.4800%
2 subgrade preparation 24.2.2022 5.3.2022 900.00 m - 0% 0.0000% 0.0079% 0.0966%
3 subbase 6.3.2022 16.3.2022 900.00 m - 0% 0.0000% 0.0510% 0.6206%
4 roadbase 1st layer 17.3.2022 27.3.2022 900.00 m - 0% 0.0000% 0.0793% 0.9644%
5 roadbase 2nd layer 28.3.2022 9.4.2022 900.00 m - 0% 0.0000% 0.0793% 0.9644%
6 binder course 10.4.2022 15.4.2022 900.00 m - 0% 0.0000% 0.1619% 1.9699%
7 wearing course 1.5.2022 6.5.2022 900.00 m - 0% 0.0000% 0.0828% 1.0077%
CH89 350 TO CH89 450 RHS Date Start Date Complete Workdone
ALADIN Volumne Weight Planning Overall Weight Section 3
ESTIMATED WORK LENGTH 100 m RHS 2 week % Weight
1 embankment fill 1.1.2022 7.1.2022 3,000.00 m3 - 0% 0.0000% 0.0048% 0.1707%
2 surcharge fill 8.1.2022 18.1.2022 5,100.00 m3 - 0% 0.0000% 0.0096% 0.3900%
3 remove surcharge fill 19.7.2022 25.7.2022 2,000.00 m3 - 0% 0.0000% 0.0027% 0.2755%
4 subgrade preparation 26.7.2022 28.7.2022 100.00 m - 0% 0.0000% 0.0009% 0.0547%
5 subbase 29.7.2022 1.8.2022 100.00 m - 0% 0.0000% 0.0057% 0.3515%
6 roadbase 1st layer 2.8.2022 4.8.2022 100.00 m - 0% 0.0000% 0.0044% 0.2731%
7 roadbase 2nd layer 5.8.2022 7.8.2022 100.00 m - 0% 0.0000% 0.0044% 0.2731%
8 binder course 8.8.2022 10.8.2022 100.00 m - 0% 0.0000% 0.0180% 1.1156%
9 wearing course 25.8.2022 27.8.2022 100.00 m - 0% 0.0000% 0.0092% 0.5707%
CH89 450 TO CH89 700 RHS Date Start Date Complete Workdone
ALADIN Volumne Weight Planning Overall Weight Section 3
ESTIMATED WORK LENGTH 250 m RHS 2 week % Weight
3 remove surcharge fill 1.1.2022 11.1.2022 5,000.00 m3 - 0% 0.0000% 0.0066% 0.2755%
4 subgrade preparation 6.3.2022 9.3.2022 250.00 m - 0% 0.0000% 0.0022% 0.0547%
5 subbase 10.3.2022 16.3.2022 250.00 m - 0% 0.0000% 0.0142% 0.3515%
6 roadbase 1st layer 17.3.2022 23.3.2022 250.00 m - 0% 0.0000% 0.0110% 0.2731%
7 roadbase 2nd layer 24.3.2022 30.3.2022 250.00 m - 0% 0.0000% 0.0110% 0.2731%
8 binder course 1.4.2022 4.4.2022 250.00 m - 0% 0.0000% 0.0450% 1.1156%
9 wearing course 20.4.2022 23.4.2022 250.00 m - 0% 0.0000% 0.0230% 0.5707%
CH89 700 TO CH89 800 RHS Date Start Date Complete Workdone
ALADIN Volumne Weight Planning Overall Weight Section 3
ESTIMATED WORK LENGTH 100 m RHS 2 week % Weight
1 embankment fill 19.1.2022 26.1.2022 4,000.00 m3 - 0% 0.0000% 0.0064% 0.1707%
2 surcharge fill 27.1.2022 8.2.2022 5,100.00 m3 - 0% 0.0000% 0.0096% 0.3900%
3 remove surcharge fill 9.8.2022 13.8.2022 2,100.00 m3 - 0% 0.0000% 0.0028% 0.2755%
4 subgrade preparation 14.8.2022 16.8.2022 100.00 m - 0% 0.0000% 0.0009% 0.0547%
5 subbase 17.8.2022 19.8.2022 100.00 m - 0% 0.0000% 0.0057% 0.3515%
6 roadbase 1st layer 20.8.2022 22.8.2022 100.00 m - 0% 0.0000% 0.0044% 0.2731%
7 roadbase 2nd layer 23.8.2022 25.8.2022 100.00 m - 0% 0.0000% 0.0044% 0.2731%
8 binder course 26.8.2022 28.8.2022 100.00 m - 0% 0.0000% 0.0180% 1.1156%
9 wearing course 15.9.2022 18.9.2022 100.00 m - 0% 0.0000% 0.0092% 0.5707%
CH89 800 TO CH90 125 RHS Date Start Date Complete Workdone
ALADIN Volumne Weight Planning Overall Weight Section 3
ESTIMATED WORK LENGTH 325 m RHS 2 week % Weight
3 remove surcharge fill 9.2.2022 23.2.2022 6,500.00 m3 200.00 3% 0.0003% 0.0086% 0.2755%
4 subgrade preparation 9.3.2022 14.3.2022 250.00 m - 0% 0.0000% 0.0022% 0.0547%
5 subbase 15.3.2022 20.3.2022 250.00 m - 0% 0.0000% 0.0142% 0.3515%
6 roadbase 1st layer 21.3.2022 26.3.2022 250.00 m - 0% 0.0000% 0.0110% 0.2731%
7 roadbase 2nd layer 27.3.2022 2.4.2022 250.00 m - 0% 0.0000% 0.0110% 0.2731%
8 binder course 3.4.2022 6.4.2022 250.00 m - 0% 0.0000% 0.0450% 1.1156%
9 wearing course 25.4.2022 28.4.2022 250.00 m - 0% 0.0000% 0.0230% 0.5707%
CH90 125 TO CH90 350 RHS Date Start Date Complete Workdone
ALADIN Volumne Weight Planning Overall Weight Section 3
ESTIMATED WORK LENGTH 225 m RHS 2 week % Weight
1 embankment fill 9.2.2022 1.3.2022 9,100.00 m3 200.00 2% 0.0003% 0.0146% 0.1707%
2 surcharge fill 2.3.2022 12.4.2022 11,400.00 m3 - 0% 0.0000% 0.0214% 0.3900%
3 remove surcharge fill 13.10.2022 30.10.2022 4,500.00 m3 - 0% 0.0000% 0.0060% 0.2755%
4 subgrade preparation 1.11.2022 4.11.2022 225.00 m - 0% 0.0000% 0.0020% 0.0547%
5 subbase 5.11.2022 10.11.2022 225.00 m - 0% 0.0000% 0.0128% 0.3515%
6 roadbase 1st layer 11.11.2022 16.11.2022 225.00 m - 0% 0.0000% 0.0099% 0.2731%
7 roadbase 2nd layer 17.11.2022 22.11.2022 225.00 m - 0% 0.0000% 0.0099% 0.2731%
8 binder course 23.11.2022 26.11.2022 225.00 m - 0% 0.0000% 0.0405% 1.1156%
9 wearing course 15.12.2022 18.12.2022 225.00 m - 0% 0.0000% 0.0207% 0.5707%
CH90 350 TO CH90 525 RHS Date Start Date Complete Workdone
ALADIN Volumne Weight Planning Overall Weight Section 3
ESTIMATED WORK LENGTH 175 m RHS 2 week % Weight
3 remove surcharge fill 24.2.2022 26.2.2022 600.00 m3 - 0% 0.0000% 0.0008% 0.2755%
4 subgrade preparation 15.3.2022 18.3.2022 175.00 m - 0% 0.0000% 0.0015% 0.0547%
5 subbase 19.3.2022 22.3.2022 175.00 m - 0% 0.0000% 0.0099% 0.3515%
6 roadbase 1st layer 23.3.2022 26.3.2022 175.00 m - 0% 0.0000% 0.0077% 0.2731%
7 roadbase 2nd layer 27.3.2022 30.3.2022 175.00 m - 0% 0.0000% 0.0077% 0.2731%
8 binder course 1.4.2022 2.4.2022 175.00 m - 0% 0.0000% 0.0315% 1.1156%
9 wearing course 22.4.2022 23.4.2022 175.00 m - 0% 0.0000% 0.0161% 0.5707%
CH90 525 TO CH90 780 RHS Date Start Date Complete Workdone
ALADIN Volumne Weight Planning Overall Weight Section 1
ESTIMATED WORK LENGTH 255 m RHS 2 week % Weight
1 embankment fill 27.2.2022 27.3.2022 12,500.00 m3 - 0% 0.0000% 0.0200% 0.1707%
2 surcharge fill 28.3.2022 1.5.2022 13,000.00 m3 - 0% 0.0000% 0.0245% 0.3900%
3 remove surcharge fill 2.11.2022 17.11.2022 5,100.00 m3 - 0% 0.0000% 0.0068% 0.2755%
4 subgrade preparation 18.11.2022 22.11.2022 255.00 m - 0% 0.0000% 0.0022% 0.0547%
5 subbase 23.11.2022 28.11.2022 255.00 m - 0% 0.0000% 0.0145% 0.3515%
6 roadbase 1st layer 29.11.2022 4.12.2022 255.00 m - 0% 0.0000% 0.0112% 0.2731%
7 roadbase 2nd layer 5.12.2022 10.12.2022 255.00 m - 0% 0.0000% 0.0112% 0.2731%
` 8 binder course 11.12.2022 14.12.2022 255.00 m - 0% 0.0000% 0.0459% 1.1156%
9 wearing course 1.1.2023 4.1.2023 255.00 m - 0% 0.0000% 0.0235% 0.5707%
CH90 900 TO CH91 050 FULL Date Start Date Complete Workdone
JOHNLEE Volumne Weight Planning Overall Weight Section 3
ESTIMATED WORK LENGTH 150 m FULL 2 week % Weight
1 embankment fill 1.3.2022 10.3.2022 1,000.00 m3 - 0% 0.0000% 0.0016% 0.1707%
2 subgrade preparation 21.3.2022 24.3.2022 150.00 m - 0% 0.0000% 0.0013% 0.0547%
3 subbase 25.3.2022 28.3.2022 150.00 m - 0% 0.0000% 0.0085% 0.3515%
4 roadbase 1st layer 29.3.2022 3.4.2022 150.00 m - 0% 0.0000% 0.0066% 0.2731%
5 roadbase 2nd layer 4.4.2022 9.4.2022 150.00 m - 0% 0.0000% 0.0066% 0.2731%
` 6 binder course 10.4.2022 11.4.2022 150.00 m - 0% 0.0000% 0.0270% 1.1156%
7 wearing course 20.4.2022 21.4.2022 150.00 m - 0% 0.0000% 0.0138% 0.5707%
CH91 450 TO CH91 700 FULL Date Start Date Complete Workdone
JOHNLEE Volumne Weight Planning Overall Weight Section 3
ESTIMATED WORK LENGTH 250 m FULL 2 week % Weight
1 remove surcharge fill 1.6.2022 10.6.2022 5,000.00 m3 - 0% 0.0000% 0.0066% 0.2755%
2 subgrade preparation 11.6.2022 16.6.2022 250.00 m - 0% 0.0000% 0.0022% 0.0547%
3 subbase 17.6.2022 13.6.2022 250.00 m - 0% 0.0000% 0.0142% 0.3515%
4 roadbase 1st layer 14.6.2022 20.6.2022 250.00 m - 0% 0.0000% 0.0110% 0.2731%
5 roadbase 2nd layer 21.6.2022 27.6.2022 250.00 m - 0% 0.0000% 0.0110% 0.2731%
` 6 binder course 28.6.2022 30.6.2022 250.00 m - 0% 0.0000% 0.0450% 1.1156%
7 wearing course 15.7.2022 17.7.2022 250.00 m - 0% 0.0000% 0.0230% 0.5707%
CH92 000 TO CH93 800 FULL Date Start Date Complete Workdone
JOHNLEE Volumne Weight Planning Overall Weight Section 4
ESTIMATED WORK LENGTH 1800 m FULL 2 week % Weight
1 remove surcharge fill 1.1.2022 2.2.2022 16,000.00 m3 8,000.00 50% 0.0106% 0.0213% 0.1939%
2 subgrade preparation 14.1.2022 15.3.2022 1,800.00 m 200.00 11% 0.0035% 0.0318% 0.0388%
3 subbase 1.2.2022 20.3.2022 1,800.00 m 50.00 3% 0.0057% 0.2041% 0.2494%
4 roadbase 1st layer 8.2.2022 27.3.2022 1,800.00 m - 0% 0.0000% 0.1586% 0.1938%
5 roadbase 2nd layer 15.2.2022 5.4.2022 1,800.00 m - 0% 0.0000% 0.1586% 0.1938%
` 6 binder course 6.4.2022 12.4.2022 1,800.00 m - 0% 0.0000% 0.6478% 0.7917%
7 wearing course 20.4.2022 25.4.2022 1,800.00 m - 0% 0.0000% 0.3314% 0.4050%
CH93 800 TO CH94 200 FULL Date Start Date Complete Workdone
JOHNLEE Volumne Weight Planning Overall Weight Section 1
ESTIMATED WORK LENGTH 400 m FULL 2 week % Weight
1 remove surcharge fill 1.5.2022 10.5.2022 8,000.00 m3 - 0% 0.0000% 0.0106% 0.1939%
2 subgrade preparation 5.5.2022 15.5.2022 400.00 m - 0% 0.0000% 0.0071% 0.0388%
3 subbase 10.5.2022 20.5.2022 400.00 m - 0% 0.0000% 0.0453% 0.2494%
4 roadbase 1st layer 15.5.2022 25.5.2022 400.00 m - 0% 0.0000% 0.0352% 0.1938%
5 roadbase 2nd layer 20.5.2022 31.5.2022 400.00 m - 0% 0.0000% 0.0352% 0.1938%
` 6 binder course 1.6.2022 3.6.2022 400.00 m - 0% 0.0000% 0.1439% 0.7917%
7 wearing course 15.6.2022 18.6.2022 400.00 m - 0% 0.0000% 0.0736% 0.4050%
CH93 800 TO CH94 200 FULL Date Start Date Complete Workdone
JOHNLEE Volumne Weight Planning Overall Weight Section 5
ESTIMATED WORK LENGTH 400 m FULL 2 week % Weight
1 subbase 1.1.22 7.1.22 400.00 m 400.00 100% 0.0453% 0.0453% 0.1644%
2 roadbase 1st layer 8.1.22 13.1.22 400.00 m - 0% 0.0000% 0.0705% 0.2555%
3 roadbase 2nd layer 14.1.22 19.1.22 400.00 m - 0% 0.0000% 0.0705% 0.2555%
` 4 binder course 20.1.22 21.1.22 400.00 m - 0% 0.0000% 0.1439% 0.5218%
5 wearing course 15.2.22 17.2.22 400.00 m - 0% 0.0000% 0.0736% 0.2669%
CH95 600 TO CH96 025 FULL Date Start Date Complete Workdone
JOHNLEE Volumne Weight Planning Overall Weight Section 6
ESTIMATED WORK LENGTH 375 m FULL 2 week % Weight
1 remove surcharge fill 1.7.22 11.7.22 7,500.00 m3 - 0% 0.0000% 0.0100% 0.0400%
2 subgrade preparation 12.7.22 20.7.22 375.00 m - 0% 0.0000% 0.0066% 0.0123%
3 subbase 21.7.22 30.8.22 375.00 m - 0% 0.0000% 0.0425% 0.0790%
4 roadbase 1st layer 1.9.22 10.9.22 375.00 m - 0% 0.0000% 0.0661% 0.1228%
5 roadbase 2nd layer 11.9.22 20.9.22 375.00 m - 0% 0.0000% 0.0661% 0.1228%
` 6 binder course 21.9.22 23.9.22 375.00 m - 0% 0.0000% 0.1350% 0.2508%
7 wearing course 15.10.22 17.10.22 375.00 m - 0% 0.0000% 0.0690% 0.1283%
CH96 025 TO CH96 350 FULL Date Start Date Complete Workdone
JOHNLEE Volumne Weight Planning Overall Weight Section 6
ESTIMATED WORK LENGTH 325 m FULL 2 week % Weight
1 embankment fill 1.1.22 30.1.22 8,000.00 m3 - 0% 0.0000% 0.0128% 0.1764%
2 subgrade preparation 1.2.22 11.2.22 255.00 m - 0% 0.0000% 0.0045% 0.0123%
3 subbase 12.2.22 22.2.22 255.00 m - 0% 0.0000% 0.0289% 0.0790%
4 roadbase 1st layer 23.2.22 3.3.22 255.00 m - 0% 0.0000% 0.0449% 0.1228%
5 roadbase 2nd layer 4.3.22 14.3.22 255.00 m - 0% 0.0000% 0.0449% 0.1228%
` 6 binder course 15.3.22 18.3.22 255.00 m - 0% 0.0000% 0.0918% 0.2508%
7 wearing course 1.4.22 3.4.22 255.00 m - 0% 0.0000% 0.0469% 0.1283%
CH97 225 TO CH97 550 RHS Date Start Date Complete Workdone
AMIN Volumne Weight Planning Overall Weight Section 8
ESTIMATED WORK LENGTH 325 m RHS 2 week % Weight
1 roadbase 1st layer 6.1.22 9.1.22 325.00 m 325.00 100% 0.0286% 0.0286% 0.2427%
2 roadbase 2nd layer 10.1.22 14.1.22 325.00 m 325.00 100% 0.0286% 0.0286% 0.2427%
` 3 binder course 15.1.22 19.1.22 325.00 m - 0% 0.0000% 0.1170% 0.9914%
4 wearing course 20.1.22 21.1.22 325.00 m - 0% 0.0000% 0.0598% 0.5072%
CH98 600 TO CH98 800 FULL Date Start Date Complete Workdone
AMIN Volumne Weight Planning Overall Weight Section 8
ESTIMATED WORK LENGTH 200 m FULL 2 week % Weight
1 roadbase 1st layer 10.1.22 15.1.22 200.00 m 200.00 100% 0.0176% 0.0176% 0.2427%
2 roadbase 2nd layer 16.1.22 20.1.22 200.00 m 100.00 50% 0.0088% 0.0176% 0.2427%
` 3 binder course 21.1.22 23.1.22 200.00 m - 0% 0.0000% 0.0720% 0.9914%
4 wearing course 15.2.22 17.2.22 200.00 m - 0% 0.0000% 0.0368% 0.5072%
CH98 800 TO CH98 925 FULL Date Start Date Complete Workdone
AMIN Volumne Weight Planning Overall Weight Section 8
ESTIMATED WORK LENGTH 125 m FULL 2 week % Weight
1 embankment fill 15.1.22 23.1.22 5,000.00 m3 1,500.00 30% 0.0024% 0.0080% 0.3680%
2 surcharge fill 24.1.22 8.2.22 6,500.00 m3 - 0% 0.0000% 0.0123% 0.0891%
3 remove surcharge fill 9.8.22 13.8.22 2,500.00 m3 - 0% 0.0000% 0.0033% 0.0628%
4 subgrade preparation 14.8.22 17.8.22 125.00 m - 0% 0.0000% 0.0022% 0.0486%
5 subbase 18.8.22 21.8.22 125.00 m - 0% 0.0000% 0.0142% 0.3123%
6 roadbase 1st layer 22.8.22 26.8.22 125.00 m - 0% 0.0000% 0.0110% 0.2427%
7 roadbase 2nd layer 27.8.22 2.9.22 125.00 m - 0% 0.0000% 0.0110% 0.2427%
` 8 binder course 3.9.22 4.9.22 125.00 m - 0% 0.0000% 0.0450% 0.9914%
9 wearing course 15.9.22 16.9.22 125.00 m - 0% 0.0000% 0.0230% 0.5072%
CH98 925 TO CH100 000 FULL Date Start Date Complete Workdone
AMIN Volumne Weight Planning Overall Weight Section 8
ESTIMATED WORK LENGTH 1075 m FULL 2 week % Weight
1 subgrade preparation 24.1.22 15.2.22 1,075.00 m 400.00 37% 0.0071% 0.0190% 0.0486%
2 subbase 16.2.22 4.3.22 1,075.00 m 150.00 14% 0.0170% 0.1219% 0.3123%
3 roadbase 1st layer 5.3.22 25.3.22 1,075.00 m - 0% 0.0000% 0.0947% 0.2427%
4 roadbase 2nd layer 26.3.22 14.4.22 1,075.00 m - 0% 0.0000% 0.0947% 0.2427%
` 5 binder course 15.4.22 18.4.22 1,075.00 m - 0% 0.0000% 0.3869% 0.9914%
6 wearing course 1.5.22 4.5.22 1,075.00 m - 0% 0.0000% 0.1979% 0.5072%
CH101 550 TO CH101 700 FULL Date Start Date Complete Workdone
AMIN Volumne Weight Planning Overall Weight Section 9
ESTIMATED WORK LENGTH 150 m FULL 2 week % Weight
1 remove and replace 1.2.22 10.2.22 5,100.00 m3 - 0% 0.0000% 0.0089% 0.2673%
2 embankment fill 11.2.22 25.2.22 6,100.00 m3 - 0% 0.0000% 0.0098% 0.5134%
3 surcharge fill 26.2.22 6.3.22 5,100.00 m3 - 0% 0.0000% 0.0096% 0.3580%
4 remove surcharge fill 7.9.22 12.9.22 2,100.00 m3 - 0% 0.0000% 0.0028% 0.2509%
5 subgrade preparation 13.9.22 18.9.22 150.00 m - 0% 0.0000% 0.0026% 0.0669%
6 subbase 19.9.22 23.9.22 150.00 m - 0% 0.0000% 0.0170% 0.4296%
7 roadbase 1st layer 24.9.22 28.9.22 150.00 m - 0% 0.0000% 0.0132% 0.3338%
8 roadbase 2nd layer 29.9.22 5.10.22 150.00 m - 0% 0.0000% 0.0132% 0.3338%
` 9 binder course 6.10.22 7.10.22 150.00 m - 0% 0.0000% 0.0540% 1.3635%
10 wearing course 20.10.22 21.10.22 150.00 m - 0% 0.0000% 0.0276% 0.6975%
CH101 850 TO CH101 975 LHS Date Start Date Complete Workdone
AMIN Volumne Weight Planning Overall Weight Section 9
ESTIMATED WORK LENGTH 125 m LHS 2 week % Weight
1 subgrade preparation 5.3.22 7.3.22 125.00 m 25.00 20% 0.0004% 0.0022% 0.0669%
2 subbase 8.3.22 12.3.22 125.00 m 25.00 20% 0.0028% 0.0142% 0.4296%
3 roadbase 1st layer 13.3.22 17.3.22 125.00 m - 0% 0.0000% 0.0110% 0.3338%
4 roadbase 2nd layer 18.3.22 22.3.22 125.00 m - 0% 0.0000% 0.0110% 0.3338%
` 5 binder course 23.3.22 24.3.22 125.00 m - 0% 0.0000% 0.0450% 1.3635%
6 wearing course 15.4.22 16.4.22 125.00 m - 0% 0.0000% 0.0230% 0.6975%
CH101 700 TO CH102 450 RHS Date Start Date Complete Workdone
AMIN Volumne Weight Planning Overall Weight Section 1
ESTIMATED WORK LENGTH 750 m RHS 2 week % Weight
1 subgrade preparation 13.3.22 26.3.22 750.00 m - 0% 0.0000% 0.0132% 0.0669%
2 subbase 20.3.22 28.3.22 750.00 m - 0% 0.0000% 0.0850% 0.4296%
3 roadbase 1st layer 25.3.22 5.4.22 750.00 m - 0% 0.0000% 0.0661% 0.3338%
4 roadbase 2nd layer 1.4.22 10.4.22 750.00 m - 0% 0.0000% 0.0661% 0.3338%
` 5 binder course 11.4.22 13.4.22 750.00 m - 0% 0.0000% 0.2699% 1.3635%
6 wearing course 1.5.22 3.5.22 750.00 m - 0% 0.0000% 0.1381% 0.6975%
CH102 450 TO CH103 700 FULL Date Start Date Complete Workdone
AMIN Volumne Weight Planning Overall Weight Section 9
ESTIMATED WORK LENGTH 1250 m FULL 2 week % Weight
1 remove surcharge fill 1.2.22 1.3.22 25,000.00 m3 - 0% 0.0000% 0.0332% 0.2509%
2 subgrade preparation 1.4.22 1.5.22 1,250.00 m - 0% 0.0000% 0.0221% 0.0669%
3 subbase 20.4.22 15.5.22 1,250.00 m - 0% 0.0000% 0.1417% 0.4296%
4 roadbase 1st layer 10.5.22 1.6.22 1,250.00 m - 0% 0.0000% 0.1101% 0.3338%
5 roadbase 2nd layer 20.5.22 15.6.22 1,250.00 m - 0% 0.0000% 0.1101% 0.3338%
` 6 binder course 16.6.22 21.6.22 1,250.00 m - 0% 0.0000% 0.4498% 1.3635%
7 wearing course 15.7.22 20.7.22 1,250.00 m - 0% 0.0000% 0.2301% 0.6975%
CH103 900 TO CH104 000 FULL Date Start Date Complete Workdone
JIMMY Volumne Weight Planning Overall Weight Section 10
ESTIMATED WORK LENGTH 100 m FULL 2 week % Weight
1 surcharge fill 1.1.22 15.1.22 3,500.00 m3 - 0% 0.0000% 0.0066% 0.2770%
2 remove surcharge fill 15.7.22 1.8.22 2,000.00 m3 - 0% 0.0000% 0.0027% 0.1922%
3 subgrade preparation 1.8.22 4.8.22 100.00 m - 0% 0.0000% 0.0018% 0.0354%
4 subbase 5.8.22 9.8.22 100.00 m - 0% 0.0000% 0.0113% 0.2274%
5 roadbase 1st layer 10.8.22 14.8.22 100.00 m - 0% 0.0000% 0.0088% 0.1767%
6 roadbase 2nd layer 15.8.22 20.8.22 100.00 m - 0% 0.0000% 0.0088% 0.1767%
` 7 binder course 21.8.22 22.8.22 100.00 m - 0% 0.0000% 0.0360% 0.7219%
8 wearing course 15.9.22 16.9.22 100.00 m - 0% 0.0000% 0.0184% 0.3693%
CH104 000 TO CH104 500 FULL Date Start Date Complete Workdone
JIMMY Volumne Weight Planning Overall Weight Section 10
ESTIMATED WORK LENGTH 500 m FULL 2 week % Weight
1 remove surcharge fill 1.2.22 25.2.22 10,000.00 m3 - 0% 0.0000% 0.0133% 0.1922%
2 subgrade preparation 20.2.22 15.3.22 500.00 m - 0% 0.0000% 0.0088% 0.0354%
3 subbase 16.3.22 4.4.22 500.00 m - 0% 0.0000% 0.0567% 0.2274%
4 roadbase 1st layer 5.4.22 25.4.22 500.00 m - 0% 0.0000% 0.0440% 0.1767%
5 roadbase 2nd layer 26.4.22 14.5.22 500.00 m - 0% 0.0000% 0.0440% 0.1767%
` 6 binder course 15.5.22 18.5.22 500.00 m - 0% 0.0000% 0.1799% 0.7219%
7 wearing course 1.6.22 4.6.22 500.00 m - 0% 0.0000% 0.0920% 0.3693%
CH104 500 TO CH104 650 FULL Date Start Date Complete Workdone
JIMMY Volumne Weight Planning Overall Weight Section 10
ESTIMATED WORK LENGTH 150 m FULL 2 week % Weight
1 embankment fill 16.1.22 1.2.22 8,000.00 m3 6,500.00 81% 0.0104% 0.0128% 0.1745%
2 surcharge fill 2.2.22 12.2.22 5,000.00 m3 - 0% 0.0000% 0.0094% 0.2770%
3 remove surcharge fill 13.8.22 30.8.22 2,100.00 m3 - 0% 0.0000% 0.0028% 0.1922%
4 subgrade preparation 25.8.22 3.9.22 150.00 m - 0% 0.0000% 0.0026% 0.0354%
5 subbase 4.9.22 10.9.22 150.00 m - 0% 0.0000% 0.0170% 0.2274%
6 roadbase 1st layer 11.9.22 17.9.22 150.00 m - 0% 0.0000% 0.0132% 0.1767%
7 roadbase 2nd layer 18.9.22 24.9.22 150.00 m - 0% 0.0000% 0.0132% 0.1767%
` 8 binder course 25.9.22 27.9.22 150.00 m - 0% 0.0000% 0.0540% 0.7219%
9 wearing course 15.10.22 17.10.22 150.00 m - 0% 0.0000% 0.0276% 0.3693%
CH105 000 TO CH105 500 LHS Date Start Date Complete Workdone
JIMMY Volumne Weight Planning Overall Weight Section 10
ESTIMATED WORK LENGTH 500 m LHS 2 week % Weight
1 subgrade preparation 4.1.22 10.1.22 200.00 m 200.00 100% 0.0018% 0.0018% 0.0354%
2 subbase 11.1.22 14.1.22 200.00 m 200.00 100% 0.0113% 0.0113% 0.2274%
3 roadbase 1st layer 15.1.22 21.1.22 200.00 m - 0% 0.0000% 0.0088% 0.1767%
4 roadbase 2nd layer 22.1.22 27.1.22 500.00 m - 0% 0.0000% 0.0220% 0.1767%
` 5 binder course 28.1.22 30.1.22 500.00 m - 0% 0.0000% 0.0900% 0.7219%
6 wearing course 15.2.22 17.2.22 500.00 m - 0% 0.0000% 0.0460% 0.3693%
CH105 550 TO CH105 850 FULL Date Start Date Complete Workdone
JIMMY Volumne Weight Planning Overall Weight Section 10
ESTIMATED WORK LENGTH 300 m FULL 2 week % Weight
1 remove and replace 13.2.22 20.2.22 3,500.00 m3 - 0% 0.0000% 0.0061% 0.2810%
2 embankment fill 21.2.22 15.3.22 4,500.00 m3 - 0% 0.0000% 0.0072% 0.1745%
3 surcharge fill 16.3.22 1.4.22 5,000.00 m3 500.00 10% 0.0009% 0.0094% 0.2770%
4 remove surcharge fill 1.10.22 10.10.22 3,000.00 m3 - 0% 0.0000% 0.0040% 0.1922%
5 subgrade preparation 5.10.22 13.10.22 300.00 m - 0% 0.0000% 0.0053% 0.0354%
6 subbase 10.10.22 18.10.22 300.00 m - 0% 0.0000% 0.0340% 0.2274%
7 roadbase 1st layer 19.10.22 30.10.22 300.00 m - 0% 0.0000% 0.0264% 0.1767%
8 roadbase 2nd layer 1.11.22 15.11.22 300.00 m - 0% 0.0000% 0.0264% 0.1767%
` 9 binder course 16.11.22 20.11.22 300.00 m - 0% 0.0000% 0.1080% 0.7219%
10 wearing course 15.12.22 18.12.22 300.00 m - 0% 0.0000% 0.0552% 0.3693%
CH105 850 TO CH106 100 FULL Date Start Date Complete Workdone
JIMMY Volumne Weight Planning Overall Weight Section 11
ESTIMATED WORK LENGTH 250 m FULL 2 week % Weight
1 embankment fill 2.4.22 12.4.22 8,500.00 m3 - 0% 0.0000% 0.0136% 0.3736%
2 surcharge fill 13.4.22 23.4.22 8,000.00 m3 - 0% 0.0000% 0.0151% 0.1764%
3 remove surcharge fill 24.10.22 30.10.22 3,500.00 m3 - 0% 0.0000% 0.0047% 0.1243%
4 subgrade preparation 30.10.22 6.11.22 250.00 m - 0% 0.0000% 0.0044% 0.0340%
5 subbase 7.11.22 13.11.22 250.00 m - 0% 0.0000% 0.0283% 0.2186%
6 roadbase 1st layer 14.11.22 20.11.22 250.00 m - 0% 0.0000% 0.0220% 0.1698%
7 roadbase 2nd layer 21.11.22 27.11.22 250.00 m - 0% 0.0000% 0.0220% 0.1698%
` 8 binder course 28.11.22 30.11.22 250.00 m - 0% 0.0000% 0.0900% 0.6938%
9 wearing course 15.12.22 17.12.22 250.00 m - 0% 0.0000% 0.0460% 0.3549%
CH106 100 TO CH106 475 FULL Date Start Date Complete Workdone
JIMMY Volumne Weight Planning Overall Weight Section 11
ESTIMATED WORK LENGTH 375 m FULL 2 week % Weight
1 laying final chipping 1.1.22 10.1.22 375.00 m 300.00 80% 0.0262% 0.0327% 0.1308%
2 embankment fill 1.4.22 14.4.22 9,000.00 m3 - 0% 0.0000% 0.0144% 0.3736%
3 surcharge fill 15.4.22 5.5.22 11,000.00 m3 - 0% 0.0000% 0.0207% 0.1764%
4 remove surcharge fill 6.11.22 16.11.22 7,000.00 m3 - 0% 0.0000% 0.0093% 0.1243%
5 subgrade preparation 13.11.22 20.11.22 375.00 m - 0% 0.0000% 0.0066% 0.0340%
6 subbase 21.11.22 25.11.22 375.00 m - 0% 0.0000% 0.0425% 0.2186%
7 roadbase 1st layer 26.11.22 2.12.22 375.00 m - 0% 0.0000% 0.0330% 0.1698%
8 roadbase 2nd layer 3.12.22 8.12.22 375.00 m - 0% 0.0000% 0.0330% 0.1698%
` 9 binder course 9.12.22 11.12.22 375.00 m - 0% 0.0000% 0.1350% 0.6938%
10 wearing course 20.12.22 22.12.22 375.00 m - 0% 0.0000% 0.0690% 0.3549%
CH106 475 TO CH106 900 FULL Date Start Date Complete Workdone
JIMMY Volumne Weight Planning Overall Weight Section 11
ESTIMATED WORK LENGTH 425 m FULL 2 week % Weight
1 embankment fill 20.2.22 5.3.22 10,500.00 m3 3,000.00 29% 0.0048% 0.0168% 0.3736%
2 surcharge fill 6.3.22 26.3.22 17,500.00 m3 - 0% 0.0000% 0.0330% 0.1764%
3 remove surcharge fill 1.10.22 15.10.22 8,000.00 m3 - 0% 0.0000% 0.0107% 0.1243%
4 subgrade preparation 10.10.22 25.10.22 625.00 m - 0% 0.0000% 0.0110% 0.0340%
5 subbase 26.10.22 10.11.22 625.00 m - 0% 0.0000% 0.0709% 0.2186%
6 roadbase 1st layer 11.11.22 26.11.22 625.00 m - 0% 0.0000% 0.0551% 0.1698%
7 roadbase 2nd layer 27.11.22 13.12.22 625.00 m - 0% 0.0000% 0.0551% 0.1698%
` 8 binder course 14.12.22 20.12.22 625.00 m - 0% 0.0000% 0.2249% 0.6938%
9 wearing course 1.1.22 10.1.22 625.00 m - 0% 0.0000% 0.1151% 0.3549%
CH106 900 TO CH107 300 Slip Road A Date Start Date Complete Workdone
JIMMY Volumne Weight Planning Overall Weight Section 11
ESTIMATED WORK LENGTH 400 m FULL 2 week % Weight
1 embankment fill 1.1.22 10.1.22 1,800.00 m3 500.00 28% 0.0008% 0.0029% 0.3736%
2 subgrade preparation 11.1.22 16.1.22 400.00 m - 0% 0.0000% 0.0035% 0.0340%
3 subbase 17.1.22 20.1.22 400.00 m - 0% 0.0000% 0.0227% 0.2186%
4 roadbase 1st layer 21.1.22 24.1.22 400.00 m - 0% 0.0000% 0.0176% 0.1698%
5 roadbase 2nd layer 25.1.22 30.1.22 400.00 m - 0% 0.0000% 0.0176% 0.1698%
` 6 binder course 1.2.22 2.2.22 400.00 m - 0% 0.0000% 0.0720% 0.6938%
7 wearing course 20.2.22 22.2.22 400.00 m - 0% 0.0000% 0.0368% 0.3549%
CH107 300 TO CH107 700 Slip Road C Date Start Date Complete Workdone
JIMMY Volumne Weight Planning Overall Weight Section 11
ESTIMATED WORK LENGTH 400 m FULL 2 week % Weight
1 roadbase 1st layer 6.1.22 10.1.22 400.00 m 400.00 100% 0.0176% 0.0176% 0.1698%
2 roadbase 2nd layer 11.1.22 16.1.22 400.00 m - 0% 0.0000% 0.0176% 0.1698%
` 3 binder course 20.1.22 22.1.22 400.00 m - 0% 0.0000% 0.0720% 0.6938%
4 wearing course 1.2.22 3.2.22 400.00 m - 0% 0.0000% 0.0368% 0.3549%
OVERALL
Total : ACCUMULATIVE PLANNING
0.2185% 1.8158%