Actual Planned Ahead /

Task Name Duration Start Finish Current Task Based Schedule


Physical Physical Delay
CONSTRUCTION STAGES 965 days Tue 3/12/19 Fri 19/5/23 46.41% 42.54% 3.87%
BRIDGE Works 916 days Tue 3/12/19 Wed 22/3/23 57.47% 68.86% -11.39%
Sg. Bongawan Bridge (CH85+250) 836 days Wed 26/2/20 Fri 10/3/23 33.58% 44.81% -11.23% Bridge Deck [LHS]
Sg. Nyaris-Nyaris Bridge (CH86+475) 877 days Thu 26/12/19 Tue 28/2/23 29.14% 44.36% -15.22% Bridge Deck [LHS]
Sg. Mandahan Bridge (CH90+800) 700 days Tue 3/12/19 Wed 6/7/22 69.44% 55.09% 14.35% Abutment Structure [LHS]
Sg. Kelatuan Bridge (CH100+175) 465 days Tue 3/12/19 Sat 18/9/21 93.17% 100.00% -6.83% Completion of Bridge
Sg. Kimanis Bridge (CH96+375) 666 days Sat 26/12/20 Wed 22/3/23 18.44% 43.27% -24.83% Bore Piling Works
Sg. Benoni Bridge (CH103+825) 483 days Thu 9/1/20 Thu 18/11/21 73.66% 93.76% -20.10% Pavement & Bridge Furniture
INTERCHANGE 965 days Tue 3/12/19 Fri 19/5/23 55.82% 19.50% 36.32%
Kimanis INTERCHANGE (CH97+125) 536 days Tue 3/12/19 Tue 14/12/21 80.03% 95.76% -15.73% Bridge Deck
Benoni INTERCHANGE (CH107+300) 877 days Wed 10/6/20 Fri 19/5/23 51.30% 5.26% 46.04% Bore Piling & Pile Testing
PEDESTRIAN BRIDGE 190 days Mon 22/3/21 Sat 13/11/21 0.00% 73.56% -73.56%
PEDESTRIAN BRIDGE AT CH106+275 190 days Mon 22/3/21 Sat 13/11/21 0.00% 73.56% -73.56% Mild Steel Structure Works
Road WORKS 965 days Tue 3/12/19 Fri 19/5/23 39.68% 40.90% -1.22%
SECTION 1 (CH 85+125 - CH 86+526) 925 days Tue 3/12/19 Sat 1/4/23 21.64% 31.20% -9.56% Surcharge Fill & Resting
SECTION 2 (CH 86+526 - CH 88+900) 780 days Tue 3/12/19 Thu 13/10/22 13.90% 21.61% -7.71% Remove Surcharge & Drainage
SECTION 3 (CH 88+900 - CH 92+000) 854 days Tue 3/12/19 Mon 9/1/23 25.85% 20.85% 5.00% Surcharge Fill & Resting
SECTION 4 (CH 92+000 - CH 94+200) 925 days Tue 3/12/19 Sat 1/4/23 55.95% 49.07% 6.88% Surcharge Fill & Resting
SECTION 5 (CH 94+200 - CH 95+650) 497 days Tue 3/12/19 Thu 28/10/21 60.19% 92.33% -32.14% Laying and Paving Works
SECTION 6 (CH 95+650 - CH 96+347) 786 days Tue 3/12/19 Thu 20/10/22 29.42% 16.49% 12.93% Surcharge Fill & Resting
SECTION 7 (CH 96+347 - CH 97+250) 553 days Tue 3/12/19 Wed 5/1/22 40.33% 78.65% -38.32% Laying and Paving Works
SECTION 8 (CH 97+250 - CH100+005) 748 days Tue 3/12/19 Sat 3/9/22 56.39% 63.34% -6.95% Laying and Paving Works
SECTION 9 (CH 100+005 - CH103+794) 881 days Tue 3/12/19 Thu 9/2/23 49.05% 46.80% 2.25% Removal of Surcharge
SECTION 10 (CH 103+794 - CH 105+800) 965 days Tue 3/12/19 Fri 19/5/23 44.43% 21.55% 22.88% Earthwork & Geotechnical
SECTION 11 (CH 105+800 - CH 107+728) 965 days Tue 3/12/19 Fri 19/5/23 28.88% 39.17% -10.29% Surcharge Fill & Resting