2.00 Earthworks
Clearing and Grubbing 123.00 0.281% 98,400.00 0.281% 0.000% 0.281% 98,400.00 - 98,400.00
Cut and Excavation 2,641.60 0.094% 33,020.00 0.094% 0.000% 0.094% 33,020.00 - 33,020.00
Road fill and earthfill 5,239.00 35.925% 12,573,600.00 12.000% 13.500% 25.500% 4,200,000.00 4,725,000.00 8,925,000.00
Hauling out of Unsuitable materials 60.00 0.214% 75,000.00 0.214% 0.000% 0.214% 75,000.00 - 75,000.00
5.00 Electrical Lines ( Meralco ) 1 12.939% 4,528,648.96 6.470% 0.000% 6.470% 2,929,809.44 - 2,929,809.44
6.00 Water Line System 1 8.808% 3,082,910.09 8.808% 0.000% 8.808% 3,082,910.09 - 3,082,910.09
TOTAL COST 100.000% 35,000,000.00
TOTAL 62.896% 16.2670% 79.16% 22,679,175.48 5,299,680.00 27,978,855.48
Prepared by :
Project Engineer
Project : Crystal Homes - Guitnang Bayan II
Location : Abuab II Road, Guitnang Bayan II, San Mateo, Rizal
Date : 17-Nov-17