PROGRES POOLS

ID Task Task Name Duration Start 01 December 21 January 11 March 01 May 21 June 11 August 01 October
Mode 20/11 11/12 01/01 22/01 12/02 05/03 26/03 16/04 07/05 28/05 18/06 09/07 30/07 20/08 10/09 01/10
1 BILL.NO.6.1 : PELIMINARIES188 days Wed 28/12/16 25%
2 BILL.NO.6.3 : LAP POOLS 134 days Mon 25%
AND KIDS POOL 27/02/17
3 EQUIPMENT 66 days Thu 01/06/17 0%
4 PIPE WORK 60 days Sat 25/02/17 70%
5 ASSOCIATED ELEKTRICAL 40 days Tue 15%
WORK 16/05/17
6 BILL.NO.6.4 : WATER 163 days Fri 30/12/16 25%
POND OMANG-OMANG
7 EQUIPMENT 44 days Thu 15/06/17 0%
8 PIPE WORK 85 days Fri 30/12/16 70%
9 ASSOCIATED ELEKTRICAL 74 days Wed 32%
WORK 12/04/17
10 BILL.NO.6.5 : WATER 142 days Fri 06/01/17 25%
POND REGENZY CLUB
11 EQUIPMENT 38 days Thu 01/06/17 0%
12 PIPE WORK 85 days Fri 30/12/16 70%
13 ASSOCIATED ELEKTRICAL 97 days Wed 30%
WORK 15/02/17
14 BILL.NO.6.6 : WATER 170 days Fri 06/01/17 25%
POND LOBBY
15 EQUIPMENT 66 days Thu 01/06/17 0%
16 PIPE WORK 120 days Fri 30/12/16 70%
17 ASSOCIATED ELEKTRICAL 114 days Wed 20%
WORK 15/02/17
18 BILL.NO.6.7 : 50 days Mon 0%
MISCELLANEOUS,TESTING 10/07/17
& COMMISSIONING

Critical Manual Task Baseline Milestone External Tasks


Critical Split Start-only Milestone External Milestone
Critical Progress Finish-only Summary Progress Inactive Task
Task Duration-only Summary Inactive Milestone
Split Baseline Manual Summary Inactive Summary
Task Progress Baseline Split Project Summary Deadline