Professional Documents
Culture Documents
PT VK (Persero) Tbk.
Project Start Date 8/1/2021 (Sunday) Display Week 1 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8
Project Lead Hari Anggono 2 Aug 2021 9 Aug 2021 16 Aug 2021 23 Aug 2021 30 Aug 2021 6 Sep 2021 13 Sep 2021 20 Sep 2021
2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
% WORK
WBS TASK LEAD START END DAYS M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
DONE DAYS
1 UMUM - -
2 SONDIR - -
3 PEMBORAN - -
3 TEST PIT - -
4 UMUM - -