ESP Monthly Plan Issue:01

Revision:01/18.06.2020
Aug-2021
Code: SOP-F-24/02

ID Task Name Duration Start Finish


August 2021
Week 1 Week 2 Week 3 Week 4 Week 5
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
1 1 Engineer Support 23 days Mon Tue
Program 02-08-21 31-08-21
2 1.1 Basic 1 day Mon Mon
Manufacturing 02-08-21 02-08-21
3 1.1.1 Turning 1 day Mon 02-08-21Mon 02-08-21 Imran
4 1.1.2 Milling 1 day Mon 02-08-21Mon 02-08-21 Imran
5 1.1.3 Drilling 1 day Mon 02-08-21Mon 02-08-21 Imran
6 1.2 CNC Turning 8 days Tue 03-08-21Wed 11-08-21
7 1.2.1 Programming 3 days Tue 03-08-21 Thu 05-08-21 Imran
8 1.2.2 Simulation 3 days Thu 05-08-21Sat 07-08-21 Imran
9 1.2.3 Operating 3 days Mon 09-08-21Wed 11-08-21 Imran
10 1.3 CNC Machining 3 days Thu Mon
Center 12-08-21 16-08-21
11 1.3.1 Programming 2 days Thu 12-08-21Fri 13-08-21 Imran
12 1.3.2 Simulation 2 days Fri 13-08-21 Mon 16-08-21 Imran
13 1.3.3 Operating 2 days Fri 13-08-21 Mon 16-08-21 Imran
14 2 Software Programming 11 days Tue 17-08-21Tue 31-08-21
15 2.1 Powermill 3 days Tue 17-08-21Sat 21-08-21
16 2.1.1 Introduction1 day Tue 17-08-21 Tue 17-08-21 Imran
17 2.1.2 Basic Steps 1 day Tue Tue Imran
of Powermill 17-08-21 17-08-21
18 2.1.3 Roughing 2 days Wed Thu
Strategies 18-08-21 19-08-21
19 2.1.3.1 Raster 1 day Wed 18-08-21Wed 18-08-21 Imran
20 2.1.3.2 Offset 1 day Wed 18-08-21Wed 18-08-21 Imran

Prepare By: ___________ Review By: _______________ Approve By: _____________


Page 1 of 3
ESP Monthly Plan Issue:01
Revision:01/18.06.2020
Aug-2021
Code: SOP-F-24/02

ID Task Name Duration Start Finish


August 2021
Week 1 Week 2 Week 3 Week 4 Week 5
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
21 2.1.3.3 Rest 1 day Thu Thu Imran
Machining 19-08-21 19-08-21
22 2.1.4 Boundary 1 day Thu 19-08-21Thu 19-08-21 Imran
23 2.1.5 Finishing 2 days Fri 20-08-21 Sat 21-08-21
Strategies
24 2.1.5.1 Raster 1 day Fri 20-08-21 Fri 20-08-21 Imran
25 2.1.5.2 Radial 1 day Fri 20-08-21 Fri 20-08-21 Imran
26 2.1.5.3 Spiral 1 day Fri 20-08-21 Fri 20-08-21 Imran
27 2.1.5.4 3D offset1 day Sat 21-08-21 Sat 21-08-21 Imran
28 2.1.5.5 1 day Sat 21-08-21 Sat 21-08-21 Imran
Constant Z
29 2.1.5.6 1 day Sat 21-08-21 Sat 21-08-21 Imran
Optimized
Constant Z
30 2.1.5.7 Corner 1 day Sat 21-08-21 Sat 21-08-21 Imran
Pencil
31 2.1.5.8 Corner 1 day Sat 21-08-21 Sat 21-08-21 Imran
Multi-Pencil
32 2.1.5.9 Corner 1 day Sat 21-08-21 Sat 21-08-21 Imran
Automatic
33 2.1.6 Drilling 1 day Mon 23-08-21Mon 23-08-21
34 2.1.6.1 Rotate 1 day Mon 23-08-21Mon 23-08-21 Imran
35 2.1.6.2 Scale 1 day Mon 23-08-21Mon 23-08-21 Imran
36 2.1.6.3 Pattern1 day Mon 23-08-21Mon 23-08-21 Imran
37 2.1.6.4 Drilling 1 day Mon 23-08-21Mon 23-08-21 Imran

Prepare By: ___________ Review By: _______________ Approve By: _____________


Page 2 of 3
ESP Monthly Plan Issue:01
Revision:01/18.06.2020
Aug-2021
Code: SOP-F-24/02

ID Task Name Duration Start Finish


August 2021
Week 1 Week 2 Week 3 Week 4 Week 5
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
38 2.2 Other CNC 1 day Thu Thu
Machines 19-08-21 19-08-21
39 2.2.1 EDM Wire 1 day Thu Thu Imran
Cut Machine 19-08-21 19-08-21
40 2.2.2 Laser Marking
1 day Thu 19-08-21Thu 19-08-21 Imran
41 2.2.3 Laser Cutting
1 day Wed 25-08-21Wed 25-08-21 Imran
42 2.2.4 CNC Router1 day Wed 25-08-21Wed 25-08-21 Imran
43 2.2.5 3D Printing 1 day Wed 25-08-21Wed 25-08-21 Imran
44 2.2.6 Swan Soft 8 days Thu 05-08-21Fri 13-08-21 Imran

Prepare By: ___________ Review By: _______________ Approve By: _____________


Page 3 of 3