PROJEK PENYELENGGARAAN FASILITI : PROPOSED ROAD RESURFACING AND

THE ASSOCIATED WORKS AT THE INTERNATIONAL ISLAMIC UNIVERSITY


MALAYSIA, GOMBAK, SELANGOR DARUL EHSAN.
ID Task Task Name Duration Start Finish
Jan '24 Feb '24
Mode W1 W2 W3 W4 W5 W6 W7
1 ROAD RESURFACING & OTHERS WORK FOR IIUM 38 days Tue 9/1/24 Wed 21/2/24 0%
2 GENERAL MILESTONE 1 day Tue 9/1/24 Tue 9/1/24 0%
3 Project Start (Site Possesion) 1 day Tue 9/1/24 Tue 9/1/24 9/1
4 General & Preliminaries 37 days Tue 9/1/24 Tue 20/2/24 0%
5 Mobilization 2 days Mon 15/1/24 Tue 16/1/24 0%
6 Survey & Setting out 1 day Tue 16/1/24 Tue 16/1/24 0%
7 Milling & Paving Work (Main Road) 14 days Wed 17/1/24 Thu 1/2/24 0%
8 50mm thk. of Milling Work 14 days Wed 17/1/24 Thu 1/2/24 0%
9 Tack Coat Work 14 days Wed 17/1/24 Thu 1/2/24 0%
10 50mm thk. Of Paving Work 14 days Wed 17/1/24 Thu 1/2/24 0%
11 Paving Work (Al-Ghazali Walk) 3 days Fri 2/2/24 Mon 5/2/24 0%
12 Tack Coat Work 3 days Fri 2/2/24 Mon 5/2/24 0%
13 30mm thk. Of Paving Work 3 days Fri 2/2/24 Mon 5/2/24 0%
14 Miscellaneous Works 10 days Tue 6/2/24 Fri 16/2/24 0%
15 Road Marking 10 days Tue 6/2/24 Fri 16/2/24 0%
16 Road Kerb 10 days Tue 6/2/24 Fri 16/2/24 0%
17 Road Signage 10 days Tue 6/2/24 Fri 16/2/24 0%
18 Bicycle Lane 7 days Fri 9/2/24 Fri 16/2/24 0%
19 Road Marking 7 days Fri 9/2/24 Fri 16/2/24 0%
20 Signage 7 days Fri 9/2/24 Fri 16/2/24 0%
21 Testing Works 3 days Sat 17/2/24 Tue 20/2/24 0%
22 Coring Test 2 days Sat 17/2/24 Mon 19/2/24 0%
23 Reflectrometer Test 1 day Tue 20/2/24 Tue 20/2/24 0%
24 INSPECTION & HANDOVER 1 day Wed 21/2/24 Wed 21/2/24 0%
25 Final site clearing 1 day Wed 21/2/24 Wed 21/2/24 0%
26 Inspection 1 day Wed 21/2/24 Wed 21/2/24 0%
27 Hand Over 1 day Wed 21/2/24 Wed 21/2/24 0%
28 GENERAL MILESTONE 1 day Wed 21/2/24 Wed 21/2/24 0%
29 The end of project 1 day Wed 21/2/24 Wed 21/2/24 21/2

Critical Split Finish-only Baseline Milestone Manual Summary Inactive Task


UDA HOLDINGS SDN. BHD.
Critical Split Task Progress Duration-only Milestone Project Summary Inactive Milestone
Pipe Relocation LOT 3346
Baseline CPM (4.1.2024) Critical Progress Manual Task Baseline Summary Progress External Tasks Inactive Summary