Revised Work Schedule for the construction of GPB IV at Chitlang (Rev 5)

ID Task Name Duration Start Finish % Complete Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
M J J A S O N D J F M A M J J A S O N D J F M A M J
1 Construction of GPB IV at Chitlang 638 days Sun 6/19/22 Sun 4/21/24 72% 72%
2 Contract Agreemnent 1 day Sun 6/19/22 Sun 6/19/22 100% 100%
3 Site Mobilization and Clearance Works 33 days Wed 6/22/22 Sun 7/24/22 100% 100%
4 Site Possession 7 days Wed 6/22/22 Tue 6/28/22 100% 100%
5 Site Mobilization 15 days Wed 6/29/22 Wed 7/13/22 100% 100%
6 Insurance 7 days Wed 6/29/22 Tue 7/5/22 100% 100%
7 Mobilization of Equipments and sampling of 15 days Sun 7/10/22 Sun 7/24/22 100% 100%
materials
8 Sampling and Approval of major construction 562 days Wed 6/29/22 Thu 2/15/24 87% 87%
material
9 Sampling, testing and approval of major 30 days Wed 6/29/22 Thu 7/28/22 100% 100%
structural material.
10 Mix design and approval 35 days Thu 7/14/22 Thu 8/18/22 100% 100%
11 Sampling testing and approval of CSEB Brick 50 days Fri 9/30/22 Wed 12/7/22 100% 100%

12 Production and stocking of CSEB brick 150 days Wed 12/7/22 Thu 5/11/23 100% 100%
13 Approval and delivery of wooden door frame 25 days Tue 12/20/22 Sat 1/14/23 100% 100%

14 Sampling and approval of tile and granite 15 days Thu 7/20/23 Fri 8/4/23 100% 100%

15 Delivery of tile and granite 30 days Fri 8/4/23 Sun 9/3/23 100% 100%
16 Approval of paint and putty 15 days Wed 10/4/23 Fri 10/20/23 100% 100%
17 Finalization of design and color shades 30 days Fri 10/20/23 Sun 11/26/23 100% 100%
18 Sampling and approval of aluminum 30 days Fri 8/25/23 Fri 12/8/23 50% 50%
windows and glazing
19 Purchase and delivery of Aluminum windows 70 days Fri 12/8/23 Thu 2/15/24 0% 0%
and glazing
20 Approval of imported doors and partition 30 days Tue 6/27/23 Fri 12/1/23 50% 50%
21 Approval of electric wire and switches 20 days Mon 12/18/23 Sat 1/6/24 100% 100%
22 Approval of electric fixtures, MCBS 30 days Thu 11/2/23 Sat 12/2/23 100% 100%
23 Approval of sanitary and plumbing pipelines 20 days Tue 7/25/23 Sat 8/19/23 95% 95%

24 Approval of sanitary and plumbing fixtures 30 days Thu 9/7/23 Wed 10/11/23 95% 95%

Critical Split Baseline Split Summary Progress


Project: Construction of GPB IV Critical Progress Task Progress Baseline Milestone Summary

Task Baseline Milestone

Submitted By: Nepal Adarsha Nirman Company Pvt.Ltd


Revised Work Schedule for the construction of GPB IV at Chitlang (Rev 5)
ID Task Name Duration Start Finish % Complete Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
M J J A S O N D J F M A M J J A S O N D J F M A M J
25 Approval of fire hydrant pumps and 30 days Wed 8/2/23 Fri 1/12/24 95% 95%
accessories
26 Approval and delivery of passenger lift 120 days Sun 5/21/23 Tue 9/19/23 100% 100%
27 Sampling and approval of Parquete floor 30 days Mon 9/11/23 Thu 10/12/23 100% 100%
28 Approval of expansion joint 20 days Sat 6/10/23 Fri 6/30/23 100% 100%
29 Main Building 610 days Mon 7/11/22 Mon 4/15/24 68% 68%
30 Structural Concreting Works 289 days Mon 7/11/22 Sat 5/20/23 88% 88%
31 Foundation Work 78 days Mon 7/11/22 Tue 9/27/22 63% 63%
32 Survey and layout Works 3 days Mon 7/11/22 Wed 7/13/22 100% 100%
33 Excavation Works 30 days Thu 7/14/22 Sat 8/13/22 100% 100%
34 Antitermite work 10 days Mon 8/8/22 Thu 8/18/22 100% 100%
35 Gravel filling and compaction 12 days Sun 8/14/22 Thu 8/25/22 100% 100%
36 PCC in Foundation 10 days Sun 8/21/22 Tue 8/30/22 100% 100%
37 Raft foundation and column 25 days Wed 8/24/22 Sat 9/17/22 100% 100%
Reinforcement
38 Formwork and concreting Raft 12 days Sun 9/11/22 Thu 9/22/22 100% 100%
foundation
39 Earth Disposal 60 days Fri 7/29/22 Tue 9/27/22 0% 0%
40 Basement Floor 78 days Fri 9/16/22 Tue 12/20/22 100% 100%
41 Column and shear wall reinforcement 21 days Fri 9/16/22 Sun 10/16/22 100% 100%
work
42 Column and shear wall formwork and 20 days Fri 9/30/22 Sun 11/6/22 100% 100%
concreting work
43 Water proofing and plaster in shear 16 days Fri 11/25/22 Sat 12/10/22 100% 100%
wall
44 Initial partial Backfilling and 10 days Sun 12/11/22 Tue 12/20/22 100% 100%
compaction
45 Basement Slab and Beam formwork 18 days Sun 10/23/22 Thu 11/17/22 100% 100%
46 Basement Slab Rebar work 15 days Tue 11/8/22 Tue 11/22/22 100% 100%
47 Slab Concreting 2 days Wed 11/23/22 Thu 11/24/22 100% 100%
48 Ground Floor 37 days Mon 11/28/22 Tue 1/3/23 100% 100%
49 Column Layout 2 days Mon 11/28/22 Tue 11/29/22 100% 100%
50 Column formwork and concreting work 14 days Wed 11/30/22 Tue 12/13/22 100% 100%

Critical Split Baseline Split Summary Progress


Project: Construction of GPB IV Critical Progress Task Progress Baseline Milestone Summary

Task Baseline Milestone

Submitted By: Nepal Adarsha Nirman Company Pvt.Ltd


Revised Work Schedule for the construction of GPB IV at Chitlang (Rev 5)
ID Task Name Duration Start Finish % Complete Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
M J J A S O N D J F M A M J J A S O N D J F M A M J
51 Beam and slab formwork 17 days Wed 12/7/22 Fri 12/23/22 100% 100%
52 Rebar works 19 days Wed 12/14/22 Sun 1/1/23 100% 100%
53 Concreting works 2 days Mon 1/2/23 Tue 1/3/23 100% 100%
54 First Floor 41 days Thu 1/5/23 Wed 2/15/23 100% 100%
55 Column Layout 12 days Sat 1/7/23 Thu 1/19/23 100% 100%
56 Column Rebar formwork and 18 days Thu 1/5/23 Mon 1/23/23 100% 100%
concreting
57 Beam and slab formwork 17 days Wed 1/18/23 Fri 2/3/23 100% 100%
58 Rebar works 20 days Wed 1/25/23 Mon 2/13/23 100% 100%
59 Concreting works 2 days Tue 2/14/23 Wed 2/15/23 100% 100%
60 Second Floor 44 days Thu 2/16/23 Wed 4/5/23 100% 100%
61 Column Layout 2 days Tue 2/21/23 Wed 2/22/23 100% 100%
62 Column Rebar formwork and 23 days Thu 2/16/23 Wed 3/15/23 100% 100%
concreting
63 Beam and slab formwork 20 days Sat 3/11/23 Thu 3/30/23 100% 100%
64 Rebar works 14 days Tue 3/21/23 Mon 4/3/23 100% 100%
65 Concreting works 2 days Tue 4/4/23 Wed 4/5/23 100% 100%
66 Third Floor 44 days Fri 4/7/23 Sat 5/20/23 100% 100%
67 Column Layout 2 days Sun 4/9/23 Mon 4/10/23 100% 100%
68 Column Rebar formwork and 16 days Fri 4/7/23 Sat 4/22/23 100% 100%
concreting
69 Beam and slab formwork 20 days Sun 4/23/23 Fri 5/12/23 100% 100%
70 Rebar works 9 days Thu 5/11/23 Fri 5/19/23 100% 100%
71 Concreting works 1 day Sat 5/20/23 Sat 5/20/23 100% 100%
72 Masonry work 224 days Sat 1/14/23 Fri 9/1/23 100% 100%
73 Basement Floor 19 days Sat 1/14/23 Thu 2/2/23 100% 100%
74 Ground Floor 53 days Sat 2/4/23 Sun 4/2/23 100% 100%
75 First Floor 76 days Sat 3/25/23 Thu 6/8/23 100% 100%
76 Second Floor 37 days Tue 6/6/23 Wed 7/12/23 100% 100%
77 Third Floor 40 days Sat 7/15/23 Thu 8/24/23 100% 100%
78 Installation of safety net 30 days Wed 8/2/23 Fri 9/1/23 100% 100%
79 Parapet Wall (Both Floors) 30 days Sat 7/29/23 Mon 8/28/23 100% 100%
80 Plaster Work 291 days Sat 4/1/23 Fri 1/26/24 97% 97%

Critical Split Baseline Split Summary Progress


Project: Construction of GPB IV Critical Progress Task Progress Baseline Milestone Summary

Task Baseline Milestone

Submitted By: Nepal Adarsha Nirman Company Pvt.Ltd


Revised Work Schedule for the construction of GPB IV at Chitlang (Rev 5)
ID Task Name Duration Start Finish % Complete Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
M J J A S O N D J F M A M J J A S O N D J F M A M J
81 Basement Floor 28 days Sat 4/1/23 Fri 4/28/23 100% 100%
82 Ground Floor 21 days Thu 4/20/23 Wed 5/10/23 100% 100%
83 First Floor 30 days Fri 7/7/23 Sat 8/5/23 100% 100%
84 Second Floor 20 days Sun 7/30/23 Sat 8/19/23 100% 100%
85 Third Floor 20 days Sun 8/20/23 Fri 9/8/23 100% 100%
86 Parapet Wall 15 days Sat 9/9/23 Sat 9/23/23 100% 100%
87 External Plaster work 55 days Tue 9/19/23 Tue 11/21/23 100% 100%
88 Wall Expansion Joint 30 days Thu 12/28/23 Fri 1/26/24 80% 80%
89 Flooring Work 129 days Sun 9/24/23 Thu 2/8/24 82% 82%
90 Water proofing in terrace and bathrooms 79 days Sat 9/30/23 Tue 12/26/23 100% 100%

91 Chipping, Screeding and punning in floor 100 days Sun 9/24/23 Wed 1/10/24 100% 100%
and terrace, screeding for tile
92 Tile in internal room and terrace 100 days Sun 10/22/23 Tue 2/6/24 90% 90%
93 Granite flooring 60 days Mon 12/4/23 Thu 2/1/24 50% 50%
94 Wall and floor tile in bathroom 30 days Wed 12/27/23 Thu 1/25/24 40% 40%
95 Floor Expansion joint 35 days Mon 1/1/24 Sun 2/4/24 75% 75%
96 Granite in kitchen slab and counter basin 14 days Fri 1/26/24 Thu 2/8/24 25% 25%

97 Metal related works 187 days Tue 8/29/23 Mon 3/11/24 58% 58%
98 Metal work for glass partition work 30 days Tue 8/29/23 Wed 9/27/23 100% 100%
99 Metal work water tank 18 days Tue 10/3/23 Sat 10/21/23 100% 100%
100 Staricase and parapet railing work 20 days Tue 1/23/24 Sun 2/11/24 0% 0%
101 Grating 15 days Mon 2/26/24 Mon 3/11/24 0% 0%
102 Paint and other finishing 140 days Fri 11/3/23 Thu 3/21/24 41% 41%
103 Internal putty works 85 days Fri 11/3/23 Fri 1/26/24 75% 75%
104 External putty works 25 days Sun 12/31/23 Wed 1/24/24 70% 70%
105 External texture paint 30 days Fri 2/9/24 Sat 3/9/24 0% 0%
106 False Ceiling Framing 85 days Fri 11/3/23 Fri 1/26/24 80% 80%
107 Internal paint 30 days Sat 1/27/24 Sun 2/25/24 0% 0%
108 Installation of fiber and metal ceiling 25 days Tue 2/6/24 Fri 3/1/24 0% 0%
board
109 External paint 50 days Thu 2/1/24 Thu 3/21/24 0% 0%

Critical Split Baseline Split Summary Progress


Project: Construction of GPB IV Critical Progress Task Progress Baseline Milestone Summary

Task Baseline Milestone

Submitted By: Nepal Adarsha Nirman Company Pvt.Ltd


Revised Work Schedule for the construction of GPB IV at Chitlang (Rev 5)
ID Task Name Duration Start Finish % Complete Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
M J J A S O N D J F M A M J J A S O N D J F M A M J
110 Signage procurement and installation 30 days Sat 1/27/24 Sun 2/25/24 0% 0%
111 Door windows and partition work 83 days Sun 1/7/24 Fri 3/29/24 1% 1%
112 Aluminum windows and glazing work 60 days Sun 1/7/24 Wed 3/6/24 5% 5%
113 Internal Partition and door fitting work 60 days Tue 1/30/24 Fri 3/29/24 0% 0%

114 Intallation of glass doors 20 days Thu 2/29/24 Tue 3/19/24 0% 0%


115 Wooden door shutters procurement and 35 days Sun 1/21/24 Sat 2/24/24 0% 0%
installation
116 Wooden Flooring and skirting 21 days Fri 2/16/24 Thu 3/7/24 0% 0%
117 Installation of toilet cubicle 15 days Fri 3/1/24 Fri 3/15/24 0% 0%
118 Electrical work/data 316 days Thu 5/11/23 Sun 3/31/24 74% 74%
networking/communication
119 Installation of wall and ceiling conduits, 150 days Thu 5/11/23 Sun 10/8/23 100% 100%
metal box
120 Installation of floor conduits 30 days Fri 9/29/23 Mon 11/6/23 100% 100%
121 Installation of electric wire 35 days Mon 12/18/23 Sun 1/21/24 75% 75%
122 Installation of electric switches and MCBS 25 days Fri 2/16/24 Mon 3/11/24 0% 0%

123 Installation of fixtures 20 days Tue 3/12/24 Sun 3/31/24 0% 0%


124 Installation of Earthing system 10 days Mon 1/22/24 Wed 1/31/24 0% 0%
125 Installaiton of lightening protection 7 days Wed 2/21/24 Tue 2/27/24 0% 0%
126 Plumbing work 182 days Tue 8/29/23 Wed 3/6/24 51% 51%
127 Installation of internal pipelines 140 days Tue 8/29/23 Wed 1/24/24 95% 95%
128 Installation of overhead water tank 5 days Thu 1/18/24 Mon 1/22/24 0% 0%
129 Installation of external pipelines 60 days Sun 12/3/23 Wed 1/31/24 0% 0%
130 Installation of external water supply 25 days Mon 1/22/24 Thu 2/15/24 0% 0%
pipeline from source
131 Installation of sanitary fittings 20 days Fri 2/16/24 Wed 3/6/24 0% 0%
132 Installation of solar panel 5 days Wed 2/21/24 Sun 2/25/24 0% 0%
133 Testing and commissioning 5 days Mon 2/26/24 Fri 3/1/24 0% 0%
134 Fire Hydrant System 218 days Sat 9/2/23 Mon 4/15/24 50% 50%
135 Installation of internal pipelines 40 days Sat 9/2/23 Thu 10/12/23 75% 75%
136 Installation of external pipelines 30 days Mon 10/2/23 Fri 1/26/24 75% 75%

Critical Split Baseline Split Summary Progress


Project: Construction of GPB IV Critical Progress Task Progress Baseline Milestone Summary

Task Baseline Milestone

Submitted By: Nepal Adarsha Nirman Company Pvt.Ltd


Revised Work Schedule for the construction of GPB IV at Chitlang (Rev 5)
ID Task Name Duration Start Finish % Complete Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
M J J A S O N D J F M A M J J A S O N D J F M A M J
137 Installation of Mechanical pumps and 30 days Tue 3/12/24 Wed 4/10/24 0% 0%
fittings
138 Testing and commissioning 5 days Thu 4/11/24 Mon 4/15/24 0% 0%
139 Passenger Lift 25 days Thu 1/11/24 Sun 2/4/24 0% 0%
140 Installation of passenger lift 20 days Thu 1/11/24 Tue 1/30/24 0% 0%
141 Operation and testing 5 days Wed 1/31/24 Sun 2/4/24 0% 0%
142 Landscape and external infrastructure work 467 days Sat 12/10/22 Fri 4/5/24 69% 69%
143 Excavation and stone masonry structure 340 days Thu 2/23/23 Sat 2/10/24 95% 95%
144 Grading work 70 days Thu 11/23/23 Wed 1/31/24 40% 40%
145 RCC Pavement 35 days Mon 1/22/24 Sun 2/25/24 0% 0%
146 Recharge pit 25 days Thu 2/1/24 Sun 2/25/24 0% 0%
147 Construction of Water reservoir, rain water 280 days Sat 12/10/22 Fri 9/22/23 100% 100%
tank, fire tank
148 Construction of manhole chambers and 80 days Wed 12/13/23 Fri 3/1/24 50% 50%
drains
149 Flagstone 75 days Mon 1/22/24 Fri 4/5/24 0% 0%
150 Dubo Work 40 days Tue 2/6/24 Sat 3/16/24 0% 0%
151 Street light and pole 30 days Thu 2/1/24 Fri 3/1/24 0% 0%
152 Project Handover 6 days Tue 4/16/24 Sun 4/21/24 0% 0%
153 Inspection and handover 6 days Tue 4/16/24 Sun 4/21/24 0% 0%
154 As Built Drawings 6 days Tue 4/16/24 Sun 4/21/24 0% 0%
155 Site Demobilization 10 days Thu 4/25/24 Sat 5/4/24 0% 0%

Critical Split Baseline Split Summary Progress


Project: Construction of GPB IV Critical Progress Task Progress Baseline Milestone Summary

Task Baseline Milestone

Submitted By: Nepal Adarsha Nirman Company Pvt.Ltd