ID Task Name Duration Start Finish % Complete Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
M J J A S O N D J F M A M J J A S O N D J F M A M J
1 Construction of GPB IV at Chitlang 638 days Sun 6/19/22 Sun 4/21/24 72% 72%
2 Contract Agreemnent 1 day Sun 6/19/22 Sun 6/19/22 100% 100%
3 Site Mobilization and Clearance Works 33 days Wed 6/22/22 Sun 7/24/22 100% 100%
4 Site Possession 7 days Wed 6/22/22 Tue 6/28/22 100% 100%
5 Site Mobilization 15 days Wed 6/29/22 Wed 7/13/22 100% 100%
6 Insurance 7 days Wed 6/29/22 Tue 7/5/22 100% 100%
7 Mobilization of Equipments and sampling of 15 days Sun 7/10/22 Sun 7/24/22 100% 100%
materials
8 Sampling and Approval of major construction 562 days Wed 6/29/22 Thu 2/15/24 87% 87%
material
9 Sampling, testing and approval of major 30 days Wed 6/29/22 Thu 7/28/22 100% 100%
structural material.
10 Mix design and approval 35 days Thu 7/14/22 Thu 8/18/22 100% 100%
11 Sampling testing and approval of CSEB Brick 50 days Fri 9/30/22 Wed 12/7/22 100% 100%
12 Production and stocking of CSEB brick 150 days Wed 12/7/22 Thu 5/11/23 100% 100%
13 Approval and delivery of wooden door frame 25 days Tue 12/20/22 Sat 1/14/23 100% 100%
14 Sampling and approval of tile and granite 15 days Thu 7/20/23 Fri 8/4/23 100% 100%
15 Delivery of tile and granite 30 days Fri 8/4/23 Sun 9/3/23 100% 100%
16 Approval of paint and putty 15 days Wed 10/4/23 Fri 10/20/23 100% 100%
17 Finalization of design and color shades 30 days Fri 10/20/23 Sun 11/26/23 100% 100%
18 Sampling and approval of aluminum 30 days Fri 8/25/23 Fri 12/8/23 50% 50%
windows and glazing
19 Purchase and delivery of Aluminum windows 70 days Fri 12/8/23 Thu 2/15/24 0% 0%
and glazing
20 Approval of imported doors and partition 30 days Tue 6/27/23 Fri 12/1/23 50% 50%
21 Approval of electric wire and switches 20 days Mon 12/18/23 Sat 1/6/24 100% 100%
22 Approval of electric fixtures, MCBS 30 days Thu 11/2/23 Sat 12/2/23 100% 100%
23 Approval of sanitary and plumbing pipelines 20 days Tue 7/25/23 Sat 8/19/23 95% 95%
24 Approval of sanitary and plumbing fixtures 30 days Thu 9/7/23 Wed 10/11/23 95% 95%
91 Chipping, Screeding and punning in floor 100 days Sun 9/24/23 Wed 1/10/24 100% 100%
and terrace, screeding for tile
92 Tile in internal room and terrace 100 days Sun 10/22/23 Tue 2/6/24 90% 90%
93 Granite flooring 60 days Mon 12/4/23 Thu 2/1/24 50% 50%
94 Wall and floor tile in bathroom 30 days Wed 12/27/23 Thu 1/25/24 40% 40%
95 Floor Expansion joint 35 days Mon 1/1/24 Sun 2/4/24 75% 75%
96 Granite in kitchen slab and counter basin 14 days Fri 1/26/24 Thu 2/8/24 25% 25%
97 Metal related works 187 days Tue 8/29/23 Mon 3/11/24 58% 58%
98 Metal work for glass partition work 30 days Tue 8/29/23 Wed 9/27/23 100% 100%
99 Metal work water tank 18 days Tue 10/3/23 Sat 10/21/23 100% 100%
100 Staricase and parapet railing work 20 days Tue 1/23/24 Sun 2/11/24 0% 0%
101 Grating 15 days Mon 2/26/24 Mon 3/11/24 0% 0%
102 Paint and other finishing 140 days Fri 11/3/23 Thu 3/21/24 41% 41%
103 Internal putty works 85 days Fri 11/3/23 Fri 1/26/24 75% 75%
104 External putty works 25 days Sun 12/31/23 Wed 1/24/24 70% 70%
105 External texture paint 30 days Fri 2/9/24 Sat 3/9/24 0% 0%
106 False Ceiling Framing 85 days Fri 11/3/23 Fri 1/26/24 80% 80%
107 Internal paint 30 days Sat 1/27/24 Sun 2/25/24 0% 0%
108 Installation of fiber and metal ceiling 25 days Tue 2/6/24 Fri 3/1/24 0% 0%
board
109 External paint 50 days Thu 2/1/24 Thu 3/21/24 0% 0%