ID Task Name Duration Start Feb '19 Mar '19 Apr '19 May '

20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5
1 KERJA‐KERJA PEMBANGUNAN BANDAR PENEGRANG 92 days Sat 2/2/19
2 SITE PLANING 1 day? Tue 2/12/19
3 Preliminaries 29 days Sat 2/2/19
4 Generate Work Program / Gantt Chart 2 days Sat 2/2/19
5 Collect Site Location Plan & All Related Info From Lecturer 2 days Mon 2/4/19
6 Breakdown Company Organization 2 days Wed 2/6/19
7 Job/Work Distribution 2 days Fri 2/8/19
8 Design For Poster 1 2 days Sun 2/10/19
9 Site Inventory & Site Analysis 7 days Sat 2/9/19
10 Study Existing Terrain Profile 3 days Sat 2/9/19
11 Sketch Existing Natural Drainage Pattern 2 days Tue 2/12/19
12 Design For Poster 2 2 days Thu 2/14/19
13 Conceptual Grading Plan 15 days Thu 2/14/19
14 Design Concept Proposed Platform Level 7 days Thu 2/14/19
15 Determine The Drainage Outlet / Final Discharge Location 1 day Thu 2/21/19
16 Determine The STP Location 1 day Fri 2/22/19
17 Determine Detention Pond Location 1 day Sat 2/23/19
18 Determine Silk Trap & Earth Drain 1 day Sun 2/24/19
19 Determine Access Road From Existing Nearest Road 1 day Mon 2/25/19
20 Design Concept for Typical Road Crossection 1 day Tue 2/26/19
21 Design For Poster 3 2 days Wed 2/27/19
22 Poster Presentation (2nd Meeting) 1 day Sat 3/2/19
23 EARTHWORK DESIGN 18 days Sun 3/3/19

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: PROJEK IDP SITE INVES
Summary Manual Summary Rollup Progress
Date: Thu 2/28/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
ID Task Name Duration Start Feb '19 Mar '19 Apr '19 May '
20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5
24 indicating proposed levels for buildings, roads, cut & fill slopes 4 days Sun 3/3/19
25 indicating cut & fill areas 4 days Thu 3/7/19
26 Earthwork cross sections 4 days Mon 3/11/19
27 Earthwork volume calculation 3 days Fri 3/15/19
28 Slope Stability Calculations 3 days Mon 3/18/19
29 EROSION & SEDIMENTATION CONTROL DESIGN 25 days Thu 3/21/19
30 Design For Erosion & Sedimentation Control Plan (ESCP) 7 days Thu 3/21/19
31 Design Calculation Detail 9 days Thu 3/28/19
32 Silk Trap 3 days Thu 3/28/19
33 Sedimentation Pond 3 days Sun 3/31/19
34 Earth Drain 3 days Wed 4/3/19
35 Establish For Typical Detail Drawing 9 days Sat 4/6/19
36 Silk Trap 3 days Sat 4/6/19
37 Sedimentation Pond 3 days Tue 4/9/19
38 Earth Drain 3 days Fri 4/12/19
39 ESTABLISH/COMPILATION FINAL IDP 1 REPORT 20 days Mon 4/15/19
40 FINISH DATE (Interview @ Final Meeting) 0 days Sat 5/4/19 5/

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: PROJEK IDP SITE INVES
Summary Manual Summary Rollup Progress
Date: Thu 2/28/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only