KRIEL ARTISAN CENTER PROGRAMME OF REMEDIAL WORKS

Wed 9/11/19
ID Task Name Duration Start Sep 22, '19 Oct 6, '19
T S W S T M F
1 WORKSHOP 7 days Tue 9/10/19

2 Install Cover Roller Shutter Doors 2 days Tue 9/10/19

3 Scrape/Grind Existing Varnished Walls 3 days Tue 9/10/19

4 Remove Existing Asbestos Soffit 1 day Tue 9/10/19

5 Install 12 mm Soffit Plywood 2 days Wed 9/11/19

6 Apply Plaster Key & Plaster Walls 2 days Fri 9/13/19

7 Paintwork-1st Coat 1 day Tue 9/17/19

8 Paintwork-Final Coat 1 day Wed 9/18/19

9 ADMIN OFFICE 5 days Wed 9/18/19

10 Remove Glass Partition 1 day Wed 9/18/19

11 Reinstall Glass Partition 2 days Wed 9/18/19

12 Rhinolite 1 day Fri 9/20/19

13 Paintwork-1st Coat 1 day Mon 9/23/19

14 Paintwork-Final Coat 1 day Tue 9/24/19

15 CLASSROOM 1 3 days Mon 9/23/19

16 Rhinolite 1 day Mon 9/23/19

17 Paintwork-1st Coat 1 day Tue 9/24/19

18 Paintwork-Final Coat 1 day Wed 9/25/19

19 CLASSROOM 2 11 days Thu 9/12/19

20 Remove Existing Door Frame 1 day Thu 9/12/19

21 Reinstall Door Frame 1 day Thu 9/12/19

22 Rhinolite 1 day Tue 9/24/19

23 Paintwork-1st Coat 1 day Wed 9/25/19

24 Paintwork-Final Coat 1 day Thu 9/26/19

25 KITCHEN & CAFETERIA 3 days Wed 9/25/19

26 Rhinolite 1 day Wed 9/25/19

27 Paintwork-1st Coat 1 day Thu 9/26/19

28 Paintwork-Final Coat 1 day Fri 9/27/19

29 FIRST AID ROOM 3 days Wed 9/25/19

30 Rhinolite 1 day Wed 9/25/19

31 Paintwork-1st Coat 1 day Thu 9/26/19

32 Paintwork-Final Coat 1 day Fri 9/27/19

33 MALE & FEMALE TOILETS 7 days Wed 9/25/19

34 Fix Vanity Tops & Splashbacks 2 days Wed 9/25/19

35 Remove & Reinstall WHB's 1 day Fri 9/27/19

36 Remove Toilets 1 day Mon 9/30/19

37 Floors - Remove Shower Tiles 1 day Tue 10/1/19

38 Floors - Tiling 1 day Wed 10/2/19

39 Reinstall Toilets 1 day Thu 10/3/19

40 EXTERNAL WORKS 21 days Mon 9/9/19

41 Brickwork - Pedestrian Side 2 days Mon 9/9/19

42 Fence Posts 1 day Mon 9/9/19

43 Rollergate Beam Repairs 1 day Tue 9/10/19

44 Install Gate Motor 1 day Wed 9/11/19

45 Paintwork - Finishes To Gate 1 day Thu 9/12/19

46 Install Gutters & Downpipes 2 days Thu 9/12/19

47 Construct Platform For Jojo Tank 1 day Mon 9/16/19

48 Install Jojo Tank 1 day Tue 9/17/19

49 Construct Storm Water Drain 1 day Wed 9/18/19

50 Repairs To Rafters, Purlins & Roof Over Hang 4 days Mon 9/16/19

51 Complete Roof Sheeting Installation (Eaves 2 days Fri 9/20/19


& Close )Holes
52 Flashing Between Brickwork & Roof 2 days Tue 9/24/19

53 Straighten Rafters 2 days Thu 9/26/19

54 Finish Rafter Openings Accordingly 2 days Mon 9/30/19

55 Tie Beams to Columns 1 day Wed 10/2/19

56 Repair Plastering 1 day Wed 9/11/19

57 Repairs To Ramps, Surface Beds & Saw Cut 1 day Thu 9/19/19
Joints
58 Clean & Snag 2 days Fri 10/4/19

59 Handover 0 days Mon 10/7/19

Page 1 Revision 0