ID Task

Task Name Duration Start Finish Predecessors


Cost Resource Names
Mode
Half 2, 2019
A M J J A S O N D
1 Construction 101 days03/05/2019 20/09/2019 ₹50,155,500.00
2 Earthwork 5 days 03/05/2019 09/05/2019 ₹2,400.00 Labour[2] Labour[2]
3 PCC 7 days 15/05/2019 23/05/2019 2FS+3 days
₹6,570.00 Labour[2],Mason,cement[1
Labour[2],Mason,cement[1 1],aggregate[1 1],sand[0.5 1] 1],aggregate[1 1],sand[0.5 1]
4 Foundation 9 days 24/05/2019 05/06/2019 3 ₹7,180.00 Mason,Labour,aggregate[2 1],cement[2 1],sand[1 1]Mason,Labour,aggregate[2 1],cement[2 1],sand[1 1]
5 Frame 15 days 06/06/2019 26/06/2019 4 ₹50,020,900.00 Mason[2],Labour[2],cement[3 Mason[2],Labour[2],cement[3 1],aggregate[5 1],sand[3 1],brick[10,000 1000]
construction 1],aggregate[5
6 Brickwork 8 days 10/07/2019 19/07/2019 5FS+9 days
₹5,010.00 Mason,Labour,cement[1 1],sand[0.5 1] Mason,Labour,cement[1 1],sand[0.5 1]
7 Electrical 3 days 25/07/2019 29/07/2019 6FS+3 ₹1,560.00 Electrician,Labour Electrician,Labour
work days
8 Internal 10 days 30/07/2019 12/08/2019 7 ₹6,900.00 Mason,Labour,cement[2 Mason,Labour,cement[2 1],sand[1 1]
plastering 1],sand[1 1]
9 external 8 days 22/07/2019 31/07/2019 6 ₹5,260.00 Mason,Labour,cement[1 Mason,Labour,cement[1 1],sand[1 1]
;plastering 1],sand[1 1]
10 plumbing 5 days 13/08/2019 19/08/2019 8 ₹2,600.00 plumber,Labour plumber,Labour
11 white 6 days 20/08/2019 27/08/2019 10 ₹5,620.00 Mason,Labour,paint[10 Mason,Labour,paint[10 1]
washing 1]
12 painting 7 days 28/08/2019 05/09/2019 11 ₹8,640.00 Mason,Labour,paint[20 1] Mason,Labour,paint[20 1]
13 flooring 6 days 06/09/2019 13/09/2019 12 ₹54,220.00 Mason,Labour,cement[1 1],sand[1 1],title[1,000 nos] Mason,Labour,cement[1 1],sand[1 1],title[1,000 nos]
14 cladding 5 days 16/09/2019 20/09/2019 13 ₹27,600.00 Mason,Labour,title[500 nos] Mason,Labour,title[500 nos]
15 water 2 days 01/08/2019 02/08/2019 9 ₹1,040.00 Mason,Labour Mason,Labour
proofing

Task Project Summary Manual Task Start-only Deadline

Project: FIT16CE089 1 Split Inactive Task Duration-only Finish-only Progress