Project Title Turbine Flow Monitoring System Site In charge Tayyab Akram

PO date 8/24/2019

Clean PO Receive Date 8/25/2019


Completion date 12/3/2019

Sr# Description Job's Status Dead Lines Finish Date


1 Project Hand over Meeting 100% 2-Oct-19 2-Oct-19
2 Project Execution Planing 100% 4-Oct-19 4-Oct-19

Gantt Chart 100% 4-Oct-19 16-Oct-19


3
4 IBOQ 100% 4-Oct-19 4-Oct-19
5 Project Audit Sheet 100% 8-Oct-19 8-Oct-19
6 Risk Assesment 100% 8-Oct-19 16-Oct-19
7 Final Workable Topology 100% 4-Oct-19 4-Oct-19
8 Deviation Notifcation 0%
9 DOR Signature 50% 16-Oct-19 16-Oct-19
10 Kick of Meeting with Client 0% 18-Oct-19
11 Design Preperation 50% 30-Oct-19
12 Budget Approval 0%
13 Design Approval 0% 30-Oct-19
14 Buying Ordering 0%
15 Inhouse Engineering 50% 30-Oct-19
Panel Drawing
16 100% 15-Oct-19 16-Oct-19
17 Panel Drawing approval 50% 15-Oct-19
18 Panel wiring start 0% 16-Oct-19 16-Oct-19
19 Panel Wirring end 0% 29-Oct-19
20 Internal FAT 0% 1-Nov-19
21 Client FAT 0% NA
22 Delivery 0% 7-Nov-19
23 Site Installation 0% 4-Nov-19
24 SAT 0% 3-Dec-19
25 Commissioing 0% 3-Dec-19
26 DPR 0% 4-Dec-19
27 JC 0% 3-Dec-19
28 Change Order 0% NA
29 Site Hold 0% NA
30 Job Done 0% 3-Dec-19
Back To Summary

9/4/2019 New PO entered, Kick Off meeting done


9/12/2019 Internal meeting done,
9/26/2019 Panel wring awaited.
P.O Number 1190014277 To be Filled

Our Offer SEPL/Q/JR/1649/564401.5


Refrence

Over Days Remarks

11 Project Team shared there information


about onsite installation on 10 Oct 2019

Sent to Client

currently I am working on it
MAH

Changes in Power Drawing by Project


1 Team
Sent to Client for Approval

in client scop