Critical Tasks

Critical Tasks Status

Critical: Yes

Status: Future Task

Critical: No

ID Name Start Finish % Complete Remaining Work Resource Names

1 Designing Concept document 26-09-19 08:00 09-10-19 17:00 0% 0 hrs

6 Create drawings 10-10-19 08:00 23-10-19 17:00 0% 0 hrs

7 Validation and Approval of Drawings 24-10-19 08:00 13-11-19 17:00 0% 0 hrs

8 Estimating materials required 14-11-19 08:00 27-11-19 17:00 0% 0 hrs

17 Installation of Construction Equipments 28-11-19 08:00 18-12-19 17:00 0% 0 hrs

18 Construcition of warehouse building 19-12-19 08:00 08-04-20 17:00 0% 0 hrs

21 Construction of other facilities 19-12-19 08:00 08-04-20 17:00 0% 0 hrs

24 Flooring and Painting of Entire warehouse and Other Buildings 09-04-20 08:00 20-05-20 17:00 0% 0 hrs

29 Laying Pathway movement for AGV 21-05-20 08:00 10-06-20 17:00 0% 0 hrs

31 Fixing computers and installing software packages 11-06-20 08:00 01-07-20 17:00 0% 0 hrs

32 Trail run of Entire ware house system 02-07-20 08:00 15-07-20 17:00 0% 0 hrs

33 Commisioning and Handover of Warehouse to client 16-07-20 08:00 29-07-20 17:00 0% 0 hrs