Project Management | Design | Turnkey | Advisory Services

CLUBHOUSE

TOWER-C

TOWER-D
S.No Description Tower C

1 Total saleable Area 3,36,807 Sq. ft.

2 Car parking (B + S) 294 Nos.

3 No. of 1 BHK Flats 84 Nos.

4 No. of 2 BHK Flats 90 Nos.

5 No. of 3 BHK Flats 162 Nos.

6 No. of floors 1B + 1S +14 Floors

7 Total No. of Flats 336 Nos.


S.No Category Organisation

1 Client APG Intelli Homes Pv t. Ltd

2 PMC Synergy Property Dev elopment Serv ices Pv t. Ltd

3 Architect Space Matrix Design consultants Pv t. Ltd

4 Structural Consultants Ramboll India Pv t. Ltd

5 MEP Consultants Ralys Engineering Consultants Pv t. Ltd

6 Landscaping Elements Design Studios

7 Main Civ il Contractor Simplex infrastructures Limited

8 Electrical Contractor Classic Electricals

9 Plumbing Contractor A2A Engineering

10 Painting Contractor Sai Painters/Singh Trading Company

M/s Sriniv asan & Co/Shree Rajendra


11 Flooring Contractor
Constructions/MK Infra Pv t Ltd
12 W aterproofing Contractor Emise Construction Therapy Pv t Ltd

13 Lift W orks M/s Thyssen Krupp Elev ator (India) Pv t Ltd

14 uPVC w orks Profenster India Limited


S.No Description Status
1 MOEF Clearance Received
2 NOC from BESCOM Received
3 NOC from AAI Received
4 NOC from BSNL Received
5 NOC from BWSSB Received
6 Karnataka State Pollution Control Board Approval Received
7 Plan Sanction from BBMP Received
8 Commencement Certificate Received
9 Preliminary Fire NOC Received
10 CEIG (Lifts) Post Construction
11 CEIG (Electrical) Post Construction
12 Occupancy Certificate Post Construction
COMPOUND WALL [34 to 94]

• Work front available- Non availability of dedicated manpower & non


clearance of SIL establishments delaying the works.
• Work front as on 9th Oct-18 - 302 Rmtr [North & West Side]
• Current Labor Strength – No dedicated manpower (Required 20
No’s)

Labour Current Required Shortfall

Carpenter + 4 12 8
Helper
Bar-bender + 6 8 2
Helper
COMPOUND WALL-PLAN for OCT’18

Activity Total Complete Plan for Ach in Cumulati %


d Till Oct’18 Oct’18 ve Completi
Sep’18 completio on
n
Excavation 302 M 100 M 150 M 45 M 145 M 48%

PCC 302 M 75 M 150 M 25 M 100 M 33%

RCC-Raft 302 M 75 M 150 M 23 M 98 M 32%

RCC-Wall 302 M 55 M 150 M 00 M 55 M 18%


1st Lift
RCC-Wall 302 M 55 M 150 M 00 M 55 M 18%
2nd Lift
RAMP SIDE RE WALL-TOWER-C[Plan for OCT’18]

Activity Total Complete Plan for Ach in Cumulati %


d Till Oct’18 Oct’18 ve Ach Completi
Sep’18 on
Excavatio 102 M 50 M 52 M - 50 49%
n
PCC 102 M 50 M 52 M - 50 49%

RCC-Raft 102 M 40 M 62 M - 40 39%

RCC-Wall 102 M 29 M 73 M - 29 28%


1st Lift
RCC-Wall 102 M 29 M 73 M - 29 28%
2nd Lift
C1 C2 C3

C1-North C2-North C3-North


10th Nov-18 20th Nov-18 30th Nov-18
20th Oct-18
C1-West

30th Oct-18
C3-Eest
C3 South
10th Oct-18

Completed Committed Date – 14th Aug-18


Balance Anticipated – 30th Oct-18
Delay-75 Days
Work In Progress
14th Floor

13th Floor

12th Floor

11th Floor

10th Floor

9th Floor 100%

8th Floor 71% 29% 100%

7th Floor 100% 100% 100%

6th Floor 100% 100% 100%

5th Floor 100% 100% 100%

4th Floor 100% 100% 100%

3rd Floor 100% 100% 100%

2nd Floor 100% 100% 100%

1st Floor

Floor / Block C1 C2 C3

Tower-C Toilet Ledge Wall works


Legends
Completed
Work in progress
No Clearence from WP
Work front available
WATERPROOFING [INTERNAL-PERCEPT]

• Work front available- Sufficient manpower not deployed.


• Work front as on 9th Oct-18 - 12 Floors [C1/C2/C3]
• Current Labor Strength – 14 No’s (Required 36 No’s)
• Affecting start of tile works in toilet / Utility and balconies

Labour Current Required Shortfall

Mason + Helpers 10 16 6

Applicators 2 6 4

Skilled Labours 2 8 6
14th
13th 100% 100% 100%
12th 100% 100% 100%
11th 100% 100% 100%
10th 100% 100% 100% 100% 100% 100%
9th 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
8th 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
7th 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
6th 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
5th 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
4th 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
3rd 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
2nd 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
1st

Floor / Kitchen / Kitchen / Kitchen / Kitchen / Kitchen / Kitchen / Kitchen / Kitchen / Kitchen / Kitchen / Kitchen / Kitchen /
Toilets Balcony Toilets Balcony Toilets Balcony Toilets Balcony Toilets Balcony Toilets Balcony Toilets Balcony Toilets Balcony Toilets Balcony Toilets Balcony Toilets Balcony Toilets Balcony
Location Utility Utility Utility Utility Utility Utility Utility Utility Utility Utility Utility Utility

2 Coat Cementitious 2 Coat Cementitious 2 Coat Cementitious


Activity Bore Packing Screed Testing & Handing over Bore Packing Screed Testing & Handing over Bore Packing Screed Testing & Handing over
coating coating coating
Block C1 C2 C3

Tower-C Waterproofing Works (Toilet/Kitchen/Balcony/Utility)

LEGENDS
Completed
Ready to Start Work
Work in Progress
Not ready for work
C1 C2 C3
Floor Remarks
Start Finish Start Finish Start Finish

1st Floor 10/16/2018 10/19/2018 10/16/2018 10/19/2018 10/16/2018 10/19/2018

2nd Floor - - - - - -

3rd Floor - - - - - -

4th Floor - - - - - -
5th Floor - - - - - -
6th Floor - - - - - -

7th Floor - - - - - -

8th Floor - - 9/22/2018 9/27/2018 - -

9th Floor 9/22/2018 9/27/2018 9/22/2018 9/27/2018 9/21/2018 9/26/2018

10th Floor 9/24/2018 9/29/2018 9/24/2018 9/29/2018 9/21/2018 9/26/2018


11th Floor 9/30/2018 10/3/2018 9/30/2018 10/3/2018 9/27/2018 9/30/2018

12th Floor 10/4/2018 10/7/2018 10/4/2018 10/7/2018 10/1/2018 10/5/2018

13th Floor 10/8/2018 10/11/2018 10/8/2018 10/11/2018 10/6/2018 10/10/2018


14th Floor 10/12/2018 10/15/2018 10/12/2018 10/15/2018 10/11/2018 10/15/2018
14th
13th 100% 100% 100% 100% 100% 100%
12th 100% 100% 100% 100% 100% 100%
11th 100% 100% 100% 100% 100% 100%
10th 100% 100% 100% 100% 100% 100%
9th 100% 100% 100% 100% 100% 100%
8th 100% 100% 100% 100% 100% 100%
7th 100% 100% 100% 100% 100% 100%
6th 100% 100% 100% 100% 100% 100% 75% 75%
5th 100% 100% 100% 100% 100% 100% 100% 100% 88% 88%
4th 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
3rd 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
2nd 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
1st 100% 100% 100% 100% 100%

Floors / 1st Coat 1st Coat Putty 2nd Coat Putty 1st Coat 1st Coat Putty 2nd Coat Putty 1st Coat 1st Coat Putty 2nd Coat Putty
Primer (Flats) Primer (Flats) Primer (Flats)
Description Putty (Flats) CA Ceiling (Flats) Putty (Flats) CA Ceiling (Flats) Putty (Flats) CA Ceiling (Flats)

Block C1-Sai Painters C2-Sai Painters C3-Singh Trading Company


Tower-C Painting Works

LEGENDS
Completed
Ready to Start Work
Work in Progress
Not ready for work
14th

13th

12th

11th

10th 25% 25% 25%

9th 50% 75% 50% 50%

8th 100% 100% 100% 100% 100% 100%

7th 100% 100% 100% 100% 100% 100%

6th 71% 100% 71% 100% 100% 86% 100% 57% 100% 100% 75% 50%

5th 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 88% 88% 88%

4th 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 7% 100% 100% 100%

3rd 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%

2nd 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%

1st

Balcony/ Main Flooring- Balcony/ Main Flooring- Balcony/ Main Flooring-


Floors / Dado- Dado- Toilet Dado- Dado- Toilet Dado- Dado- Toilet
Utility Bedroom/Living/ Skirting Utility Bedroom/Livin Skirting Utility Bedroom/Living Skirting
Description Toilet Kitchen Flooring Toilet Kitchen Flooring Toilet Kitchen Flooring
Flooring Kitchen Flooring g/Kitchen Flooring /Kitchen

Block C1-Srinivasan & Co C2-Shree Rajendra Constructions C3-MK Infra Ltd

Tower-C Tiling Works

LEGENDS
Completed
Ready to Start Work
Work in Progress
Not ready for work
C1 C2 C3
Floor Remarks
Start Finish Start Finish Start Finish

1st Floor 11/19/2018 11/24/2018 11/19/2018 11/24/2018 11/19/2018 11/24/2018

2nd Floor - - - - - - Completed Excluding Bal/Uti


3rd Floor - - - - - - Completed Excluding Bal/Uti

4th Floor 9/21/2018 9/27/2018 9/21/2018 9/27/2018 9/24/2018 10/3/2018 Work in progress
5th Floor 9/23/2018 9/29/2018 9/23/2018 9/29/2018 10/4/2018 10/9/2018 Work in progress
6th Floor 9/27/2018 10/3/2018 9/27/2018 10/3/2018 10/10/2018 10/14/2018
7th Floor 10/4/2018 10/9/2018 10/4/2018 10/9/2018 10/15/2018 10/19/2018

8th Floor 10/10/2018 10/15/2018 10/10/2018 10/15/2018 10/20/2018 10/19/2018

9th Floor 10/16/2018 10/21/2018 10/16/2018 10/21/2018 10/20/2018 10/24/2018

10th Floor 10/22/2018 10/26/2018 10/22/2018 10/26/2018 10/25/2018 10/29/2018


11th Floor 10/27/2018 10/31/2018 10/27/2018 10/31/2018 10/30/2018 11/3/2018
12th Floor 11/1/2018 11/6/2018 11/1/2018 11/6/2018 11/4/2018 11/8/2018

13th Floor 11/7/2018 11/12/2018 11/7/2018 11/12/2018 11/9/2018 11/13/2018


14th Floor 11/13/2018 11/18/2018 11/13/2018 11/18/2018 11/14/2018 11/18/2018
Block Trade Unit Planned (Avg) Actual (Avg) Deficit (%)

Mason Nos 12 7
C1 -33%
Mason Helper Nos 12 9

Mason Nos 12 8
C2 -33%
Mason Helper Nos 12 8

Mason Nos 13 4
C3 -65%
Mason Helper Nos 13 5
INTERNAL PLUMBING [APARTMENTS]

• Work front as on 26th Sep-18 - Piping works in toilets, balcony &


utility is in progress
• Current Labor Strength – 13 No’s

Labour Current Required Shortfall

Plumber + Helper 13 13 -
14th 100%
13th 100% 100% 100%
12th 100% 100% 100% 100% 100% 100% 100%
11th 100% 100% 100% 100% 100% 100% 100% 71%
10th 100% 100% 100% 100% 100% 100% 57% 43% 100% 100% 100% 100% 100%
9th 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
8th 100% 100% 100% 100% 100% 50% 100% 100% 100% 100% 100% 50% 100% 100% 100% 100% 100% 63%
7th 100% 100% 100% 100% 100% 88% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
6th 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
5th 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
4th 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
3rd 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
2nd 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
1st 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
CPVC & Testing & CPVC & Testing & CPVC & Testing &
Floors / Core Utility & Core Utility & Core Utility &
PVC FV & DF Handing Kitchen PVC FV & DF Handing Kitchen PVC FV & DF Handing Kitchen
Description Cutting Balcony Cutting Balcony Cutting Balcony
Piping over Piping over Piping over
Block C1 C2 C3
Tower-C Plumbing Works

LEGENDS
Completed
Ready to Start Work
Work in Progress
Not ready for work
LEVEL C-1 C-2 C-3
14
13
12
11
10
9 15% 50%
8 95% 85%
7 95% 95%
6 100% 95% 100%
5 100% 100% 100%
4 100% 100% 100%
3 100% 100% 100%
2 100% 100% 100% 13%
1
UPPER STILT 70% 70% 70%
BASEMENT 95% 95% 95%

Testing & Switch Testing & Switch Testing &


Switch DB DB
ACTIVITY wiring DB dressing handing wiring plate handing wiring plate handing
plate fixing dressing dressing
over fixing over fixing over

clearence required from civil


completed
work front available
work under progress
S.No Description Tower D

1 Total saleable Area 3,37,876 Sq.ft.

2 Car parking (B + S) 312 Nos

3 No. of 1 BHK Flats -

4 No. of 2 BHK Flats 156 Nos

5 No. of 3 BHK Flats 156 Nos

6 No. of floors 2S+13 Floors

7 Total No. of Flats 312 Nos


D 1 BLOCK D 2 BLOCK D 3 BLOCK

P1 P2 P3 P4 P5 P6
Milestones Location
Start Date D End Date Start Date D End Date Start Date D End Date Start Date D End Date Start Date D End Date Start Date D End Date

13th floor 5-Jan-19 15 21-Jan-19 9-Jan-19 15 24-Jan-19 9-Jan-19 15 25-Jan-19 11-Jan-19 15 27-Jan-19 15-Jan-19 15 30-Jan-19 17-Jan-19 15 31-Jan-19

12th floor 25-Dec-18 10 4-Jan-19 29-Dec-18 10 8-Jan-19 29-Dec-18 10 8-Jan-19 31-Dec-18 10 10-Jan-19 3-Jan-19 10 14-Jan-19 5-Jan-19 10 16-Jan-19
M-8
11th floor 15-Dec-18 10 24-Dec-18 19-Dec-18 10 28-Dec-18 19-Dec-18 10 28-Dec-18 21-Dec-18 10 30-Dec-18 23-Dec-18 10 2-Jan-19 25-Dec-18 10 4-Jan-19

10th floor 5-Dec-18 10 14-Dec-18 9-Dec-18 10 18-Dec-18 9-Dec-18 10 18-Dec-18 11-Dec-18 10 20-Dec-18 13-Dec-18 10 22-Dec-18 15-Dec-18 10 24-Dec-18
M-7
9th floor 25-Nov-18 10 4-Dec-18 29-Nov-18 10 8-Dec-18 29-Nov-18 10 8-Dec-18 1-Dec-18 10 10-Dec-18 3-Dec-18 10 12-Dec-18 5-Dec-18 10 14-Dec-18

8th floor 15-Nov-18 10 24-Nov-18 19-Nov-18 10 28-Nov-18 19-Nov-18 10 28-Nov-18 21-Nov-18 10 30-Nov-18 23-Nov-18 10 2-Dec-18 25-Nov-18 10 4-Dec-18
M-6
7th floor 5-Nov-18 10 14-Nov-18 9-Nov-18 10 18-Nov-18 9-Nov-18 10 18-Nov-18 11-Nov-18 10 20-Nov-18 13-Nov-18 10 22-Nov-18 15-Nov-18 10 24-Nov-18

6th floor 25-Oct-18 10 4-Nov-18 29-Oct-18 10 8-Nov-18 29-Oct-18 10 8-Nov-18 31-Oct-18 10 10-Nov-18 3-Nov-18 10 12-Nov-18 5-Nov-18 10 14-Nov-18
M-5
5th floor 12-Oct-18 10 24-Oct-18 16-Oct-18 10 28-Oct-18 19-Oct-18 10 28-Oct-18 21-Oct-18 10 30-Oct-18 23-Oct-18 10 2-Nov-18 25-Oct-18 10 4-Nov-18

4th floor 29-Sep-18 12 11-Oct-18 3-Oct-18 12 15-Oct-18 5-Oct-18 12 17-Oct-18 6-Oct-18 12 20-Oct-18 10-Oct-18 12 22-Oct-18 12-Oct-18 12 24-Oct-18
M-4
3rd floor 11-Sep-18 15 28-Sep-18 14-Sep-18 15 1-Oct-18 19-Sep-18 15 4-Oct-18 21-Sep-18 15 5-Oct-18 24-Sep-18 15 9-Oct-18 26-Sep-18 15 11-Oct-18

2nd floor 22-Aug-18 20 10-Sep-18 24-Aug-18 20 12-Sep-18 27-Aug-18 20 16-Sep-18 29-Aug-18 20 20-Sep-18 1-Sep-18 20 23-Sep-18 3-Sep-18 20 25-Sep-18
M-3
1st floor 17-Jul-18 35 21-Aug-18 19-Jul-18 35 23-Aug-18 22-Jul-18 35 26-Aug-18 24-Jul-18 35 28-Aug-18 27-Jul-18 35 31-Aug-18 29-Jul-18 35 2-Sep-18
Pour 1 Pour 3 Pour5
C-21 Aug 18 C-26 Aug 18 C-31 Aug 18
F-31 Aug 18 F-05 Oct 18 F-23 Sep 18

Pour2 Pour 4 Pour6


C-23 Aug 18 C-28 Aug 18 C-02 Sep 18
F-08 Sep 18 F-27 Sep 18 F-15 Sep 18

Completed area C- Committed date


R1 Completion date – 02 Sep 18
F- Finish date
Delay – 33 days
A-Anticipated
Pour 1 Pour 3 Pour5
C-10 Sep 18 C-16 Sep 18 C-23 Sep 18
F-29 Sep 18 A-16 Oct 18 A-12 Oct 18

Pour2 Pour 4 Pour6


C-12 Sep 18 C-20 Sep 18 C-25 Sep 18
A-10 Oct 18 A-13 Oct 18 F-10 Oct 18

Completed area C- Committed date


R1 Completion date – 25 Sep 18
F- Finish date
Delay – 21 days
A-Anticipated
Pour 1 Pour 3 Pour5
C-28 Sep 18 C-04 Oct 18 C-09 Oct 18
A-13 Oct 18 A-28 Oct 18 A-23 Oct 18

Pour2 Pour 4 Pour6


C-01 Oct 18 C-05 Oct 18 C-11 Oct 18
A-21 Oct 18 A-24 Oct 18 A-20 Oct 18

Completed area C- Committed date


R1 Completion date – 11 Oct 18
F- Finish date
Delay – 17 days
A-Anticipated
Pour 1 Pour 3 Pour5
C-11 Oct 18 C-17 Oct 18 C-22 Oct 18
A-26 Oct 18 A-09 Nov 18 A-31 Oct 18

Pour2 Pour 4 Pour6


C-15 Oct 18 C-20 Oct 18 C-24 Oct 18
A-30 Oct 18 A-05 Nov 18 A-29 Oct 18

Completed area C- Committed date


R1 Completion date – 24 Oct 18
F- Finish date
Delay – 16 days
A-Anticipated
TOWER-C STRUCTURE WORKS AS ON DATE TOWER-D STRUCTURE WORKS AS ON DATE
C1 Block C2 Block C3 Block D1 Block D2 Block D3 Block

14th Floor 13th floor


13th floor 12th floor
12th floor
11th floor
11th floor Total Pours 84
10th floor Total Pours 78
10th floor Completed
10 9th floor Completed
9th floor as on date 8
8th floor as on date
8th floor Balance 74
7th floor Balance 70
7th floor
6th floor
6th floor
5th floor
5th floor
4th floor
4th floor
3rd floor
3rd floor
2nd floor 50% Completed 50% Completed
2nd floor 28-Sep-17 10-Oct-17
08-Sep-17 19-Sep-17 29-Sep-17 1st floor 08-Sep-18 05-Oct-18 23-Sep-18
1st floor

15-Aug-17 31st Jul-18


Stilt floor Stilt floor

18-Jul-17 09th Jun-18


Basement Basement
floor floor
Planned Actual / Current Delay
Tower C Completion (R1 Probable On Slab
Schedule) Completion (Against R1)
1st Floor 2-Sep-18 5-Oct-18 33

2nd Floor 25-Sep-18 16-Oct-18 21


3rd Floor 11-Oct-18 28-Oct-18 17

4th Floor 24-Oct-18 9-Nov-18 16


5th Floor 4-Nov-18 17-Nov-18 13

6th Floor 14-Nov-18 25-Nov-18 11


7th Floor 24-Nov-18 3-Dec-18 9

8th Floor 4-Dec-18 11-Dec-18 7

9th Floor 14-Dec-18 19-Dec-18 5

10th Floor 24-Dec-18 27-Dec-18 3

11th Floor 4-Jan-19 4-Jan-19 0

12th Floor 16-Jan-19 16-Jan-19 0

Terrace Floor 31-Jan-19 31-Jan-19 0

COMPLETED
ANTICIPATED
Cumulative for Sep-
D1 D2 D3
18 % Completion
S.No Floors Unit
for Oct-18
Plan Ach Plan Ach Plan Ach Plan Ach

1 1st Floor Nos 1 1 1 1

2 2nd Floor Nos 1 2 2 1 5 1

13%
3 3rd Floor Nos 2 2 2 6 0

4 4th Floor Nos 2 2 4 0

Total Nos 5 0 5 1 6 1 16 2
LEVEL D-1 D-2 D-3
13
12
11
10
9
8
7
6
5
4
3 95%
2 100% 100% 100% 100% 30% 85% 20% 90% 50% 100% 100%
1 100% 100% 70% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
Module box Module box Module box Module box Module box
Slab Module box
fixing & Slab GI wire fixing & GI wire Slab GI wire fixing & Slab GI wire fixing & Slab GI wire fixing & Slab GI wire
ACTIVITY conduiti fixing & wall
wall conduiting Pulling wall Pulling conduiting Pulling wall conduiting Pulling wall conduiting Pulling wall conduiting Pulling
ng conduiting
conduiting conduiting conduiting conduiting conduiting
POURS P1 P2 P3 P4 P5 P6

clearence required from civil


completed
work front available
work under progress
Labors Required (Avg) Avg Shortfall %

Carpenter 120 75 45 38%

Bar Bender 80 67 13 16%


140

120

100

80
Planned Car+Hel
Actual Car+Hel
60
Planned Bar-ben+Hel
Actual Bar-ben+Hel
40

20

0
1-Oct
2-Oct
3-Oct
4-Oct
5-Oct
6-Oct
7-Oct
8-Oct
9-Oct
10-Oct
11-Oct
12-Oct
13-Oct
14-Oct
15-Oct
16-Oct
17-Oct
18-Oct
19-Oct
20-Oct
21-Oct
22-Oct
23-Oct
24-Oct
25-Oct
26-Oct
27-Oct
28-Oct
29-Oct
30-Oct
31-Oct
10-Oct

11-Oct

12-Oct

13-Oct

14-Oct

15-Oct

16-Oct

17-Oct

20-Oct

21-Oct

22-Oct

23-Oct

24-Oct

25-Oct

26-Oct

27-Oct

28-Oct

29-Oct

30-Oct

31-Oct
1-Oct

3-Oct

4-Oct

5-Oct

6-Oct

8-Oct

9-Oct

Date

Planned Car+Hel 120 120 120 120 120 120 120 120 120 120 120 120 120 120 120 120 120 120 120 120 120 120 120 120 120 120 120
Actual Car+Hel 67 69 77 87 83 62 64
Planned Bar-ben+Hel 80 80 80 80 80 80 80 80 80 80 80 80 80 80 80 80 80 80 80 80 80 80 80 80 80 80 80
Actual Bar-ben+Hel 67 69 66 66 64 64 64
• Balance Columns casting from upper stilt floor to Ground floor-15.10.18
• Ground floor slab concrete work including west & east side staircase for balance
portion; D3-15.10.18, D2-20.10.18 and D1-25.10.18
• Dewatering sump.
• UG staircase works-17.10.18
• UG & STP tank Inside clearance for internal external waterproofing works; UG-15.10.18
STP-31.10.18.
• Upper stilt & GF de shuttered area rectification works which including touchup &
grinding works.
• Delay in supply of RMC from approved vendors.
SMOKY
MOUNTAIN
• AFRICAN
QUICK SILVER
PLAIN

D1 SECTION-AERIAL VIEW
SMOKY
MOUNTAIN
• AFRICAN
QUICK SILVER
PLAIN

D2 SECTION-AERIAL VIEW
SMOKY
MOUNTAIN
• AFRICAN
QUICK SILVER
PLAIN

D3 SECTION -AERIAL VIEW


S.No Category Organisation

1 Client APG Intelli Homes Pvt. Ltd

2 PMC Synergy Property Development Services Pvt. Ltd

3 Architect Abin Design Studio

4 Structural Consultants Abin Design Studio[ISA Structural Studio]

5 MEP Consultants Abin Design Studio[Kromatics]

6 Main Civil Contractor Simplex infrastructures Limited


UPPER BASEMENT FLOOR SLAB +97.60 M.LVL
UB Slab
C-26 Jun 18
F-26 Sep 18

Base line date –26 Jun 18 C- Committed date


Completed area F- Finish date
Delay – 92 days
GROUND FLOOR SLAB +100.60 M.LVL
GF Slab
C-25 Jul 18
A-26 Oct 18

C- Committed date
Base line date –25 Jul 18
Completed area A-Anticipated
Delay – 93 days
F- Finish date
FIRST FLOOR SLAB +104.60 M.LVL
FF Slab
C-17 Aug 18
A-10 Nov 18

C- Committed date
Base line date –17 Aug 18
Completed area A-Anticipated
Delay – 85 days
F- Finish date
TERRACE FLOOR +108.60 M.LVL
TF
C-17 Sep 18
A-20 Nov 18

C- Committed date
Base line date –17 Sep 18
Completed area A-Anticipated
Delay – 64 days
F- Finish date
Labors Required Actual (Avg) Shortfall %

Carpenter 24 6 18 75%

Bar Bender 14 5 9 64%

Execution
• Non availability of sufficient carpenters & bar-benders affecting the project
completion.
• No plan of action at site from the management as per the agreed schedule &
commitments.
10
15
20
30

25

0
5

Date
1-Oct
2-Oct
3-Oct

Actual Car+Hel
Planned Car+Hel
4-Oct

Actual Bar-ben+Hel
5-Oct

Planned Bar-ben+Hel
6-Oct
7-Oct

6
6
1-Oct
8-Oct

6
6
3-Oct
9-Oct

6
6
4-Oct
10-Oct

6
6
5-Oct 11-Oct
12-Oct

6
5
6-Oct
13-Oct

4
5
8-Oct
14-Oct

4
5
9-Oct
15-Oct
10-Oct 16-Oct
11-Oct 17-Oct
18-Oct
12-Oct
19-Oct
13-Oct
20-Oct
14-Oct 21-Oct
15-Oct 22-Oct

16-Oct 23-Oct
24-Oct
17-Oct
25-Oct
20-Oct
26-Oct
21-Oct 27-Oct
22-Oct 28-Oct
29-Oct
23-Oct
30-Oct
24-Oct
31-Oct
25-Oct

26-Oct

27-Oct

28-Oct

29-Oct
Actual Car+Hel
Planned Car+Hel

30-Oct
Actual Bar-ben+Hel
Planned Bar-ben+Hel

31-Oct
14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14
24 24 24 24 24 24 24 24 24 24 24 24 24 24 24 24 24 24 24 24 24 24 24 24 24 24 24
SMOKY
MOUNTAIN
• AFRICAN
QUICK SILVER
PLAIN

CLUBHOUSE-VIEW FROM TOWER C’C1


SMOKY
MOUNTAIN
• AFRICAN
QUICK SILVER
PLAIN

CLUBHOUSE-Lower Basement RE wall waterproofing works started


SMOKY
MOUNTAIN
• AFRICAN
QUICK SILVER
PLAIN

CLUBHOUSE-1st Floor Slab Shuttering works is in progress


Innovate to excel

Synergy Property Development Services Pvt Ltd


Pine Valley, Embassy Golf Links Business Park
Domlur, Bangalore 560 071
T +91 (0)80 4288 6000
www.synergyind.com

CIN U74140KA2003PTC031477