DECEMBER – 2018
BY
JAIN CONSTRUCTIONS
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 1 of 56
CONTENTS
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 2 of 56
ABOUT PROJECT
Jain constructions, developing the Sri Ram Garden project “Proposed Residential cum commercial
development” at Suchitra, Hyderabad, Telangana 500067.The project comprises of 2 towers, with 3
basements, Ground Floor & 14 storeys, which includes 210 apartments (2, 3 & 4 BHK), Club house and
other re-creative amenities like sports facilities, relaxing and unwinding zones provided in the 65% of
the open space area.
.
Master Layout
TATA Projects Ltd, QS division (TPL-IPQMS) is providing their Quality Services by deploying the
engineering team to support Unique India construction for adhering timeline, Quality & Safety during
construction along with the innovative technology building information modelling (BIM)
implementation in the project management process & services. The adequate engineers for the
project has been planned and TPL-IPMS started their deployment from the month of Sep 2018.
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 3 of 56
Project Brief
Project Duration
Commencement Date of the project - 19 Sep 2018
Project Duration for structure completion - 18 Months
Total Project Duration - 24 Months
Planned Completion of the project
(Except finishes) - 17 May 2020
Project Team
Consultants
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 4 of 56
SECTION – 1 EXECUTIVE SUMMARY
1.1 Overview
During the month and till December’18, the progress of works happening at Tower B
(Residential block and podium) cellar 3 floor works and Tower-A footings excavation works.
During the month we have planned 2701 cum. of concrete and achieved 1060 cum. In overall
concrete planned 5465 cum. and achieved 3557 cum.
Tower – B, 97% of Footings, 95% of Retaining wall, 100% of Pedestal, 87% of Plinth Beam,
64% of Columns completed and STP area wall 50% completed. Delay in pour 3 area Plinth
Beam & Column casting due to shortfall in shuttering materials from UIC
UIC submitted procurement schedule, TPL verified and submitted to Jain’s for procurement of
Concrete & Steel for the month of December’18.
As per the schedule committed by UIC, Pour-1 slab concrete planned in 17th December’18. Due
to delay in shuttering & reinforcement works concrete done on 30th Dec’18.
UIC getting delayed on pour 3 column casting & pour 2 slab shuttering due to shortfall in
shuttering material & less skilled workers at site,
TPL informed to UIC to arrange one more set of shuttering materials for Retaining wall & pour 1
slab from 1st slab to 2nd slab. UIC informed materials will arrange on 1st week of January’19.
TATA Projects Ltd., QS Division (IPQMS) is providing their Quality Services by deploying the
Engineering team to support Jain Sri Ram Garden construction for adhering Timeline, Quality &
Safety during construction along with the innovative technology Building Information Modelling
(BIM) implementation in the project management process & services. The adequate engineers
for the project has been planned and deployed.
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 5 of 56
1.3 Project Progress Status - As on Dec’2018
TOWER - B
Excavation
PCC
RCC
TOWER - A
Excavation
PCC
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 6 of 56
1 Retaining wall Raft Foundation Rmtr 214 59 155 28%
RCC
Total % of Work
Sl. Description Floor Achieved Balance
No. Unit qty Completed
qty qty
STP works
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 7 of 56
1.4 Procurement Status – as on December 2018
Vendor
S NO Package Date Remarks
/Supplier
1 Civil works - Tower A & B 31-08-2018 UIC
Ultra Tech
2 RMC Supplier 02-10-2018
RMC
SS
3 Water proofing Works 12-10-2018
Enterprises
VK
4 STP 22-10-2018
Engineers
Sree pesto
solutions
5 Pest control system 30-11-2018
India private
limited
6 Wood works
7 MS works
8 SS Works
9 Tile & granite works
10 ACP works
11 Landscape works
12 CP & Sanitary fixtures
13 Painting
14 False Ceiling Works
MEP
GA
15 Earthing Works 30-11-2018
Electricals
16 Electrical contractor - Internal
17 Electrical contractor - External
18 plumbing contractor – Internal & External
19 Firefighting works
20 Lift works
21 HVAC works
22 Service Providers( Communication works)
23 Security services(Solar, CCTV)
24 Parking Management
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 8 of 56
1.5 Material Procurement Status – As on Dec’2018
Balance
Item Description UOM PR Qty Received to be
S.NO Remarks
qty received
1 Steel
2 RMC
3 Cover blocks
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 9 of 56
20mm Nos 5,000 5,000 -
MEP
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 10 of 56
Yellow paint ltr 8.00 8.00
1. Tower A – Retain wall & Footings Excavation work going on full swing from 30th Dec 2018.
Footing (Exp Joint Location) dismantling to start a s per revised footing drawing.
2. Tower B – TPL to be follow up UIC to Speed up Staircase & Ramp 1 & 2 structure works.
3. Tower B – TPL to be follow up UIC to speed up 1st Slab - Pour 2 slab shuttering works
4. Tower A - TPL to be follow up with Design team for Tower A commercial floors drawings
5. Tower A – TPL to be follow up with Ralys to receive Electrical & Plumbing GFC and BOQ
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 11 of 56
1.8 Risk Register:
Raised
Risk Date Stage/Pha Action
Sl.No by Target Date Status Risk Mitigation Comments
Description Raised se by
Whom
TPL
repeatedly
following up
with
Vendor
Tower A & consultants
finalization to
Club house to provide
be comp. by
electrical & Design & MEP GFC &
1 01-11-2018 TPL RALYS 22-12-2018 Open H Jain and
plumbing BOQ BOQ’s. Jain
shall be on
drawings yet to intervene
board by Dt.
to receive. with the
31.12.2018
design
consultants
for getting
the same
TPL
repeatedly
following up
with
consultants PT vendor
Tower A to provide finalization to
commercial Tower A be comp.by
Design &
2 floors 01-11-2018 TPL GENESIS 22-12-2018 Open H drawings. Jain and
drawings
drawings yet Jain to shall be on
to receive intervene board by
with the Dt.31.12.18
design
consultants
for getting
the same
TPL
Tower A Jain will
repeatedly
Footings & take care to
Constructi following up
3 Retaining wall 17-12-2018 TPL JAINS 31-12-2018 Open H increase the
on with clients to
Excavation is machineries
increase
getting delay. & manpower
resources.
Steel indent
for 15th
Nov’18 is
received only
240 MT of
400 MT. Jain Jain has to
has to arrange
Steel Constructi
4 15-11-2018 TPL JAINS 31-12-2018 Open H arrange steel rein.steel. as
Procurement on
reinforcemen per site
t as per site requirements
requirement
to achieve
the progress
without any
delay
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 12 of 56
UIC has to
UIC delayed mobilize
Retaining wall
on procuring add.
& 2nd slab
Constructi Retaining Shuttering
5 pour 1 12-11-2018 TPL UIC 28-12-2018 Open H
on wall. materials for
shuttering
Shuttering retaining wall
material
material & 2nd slab
pour 1.
UIC delayed
on procuring
shuttering
materials for
pour 3 slab,
TPL UIC has to
continuous mobilize
Pour 3 beam
follow up with additional
& slab Constructi
6 17-12-2018 TPL UIC 28-12-2018 Open H the UIC to shuttering
shuttering on
increase the materials for
materials
materials . progressive
Completing of works
the slab
casting as
per schedule
will be very
critical
Jains
1 Steel Indent 04 & 05 Procurement status 30-11-2018 TPL Jains Open 240 MT received out of 400MT
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 13 of 56
Jains Informed in last site visit
on 21-12-18, one more
Machineries & manpower to be
2 17-12-2018 TPL Jains 21-Dec'18 Open machine will engaged for
increased from Tower A excavation
tower A footings excavation,
still is in pending
UIC
1) Progress Review meeting with Unique India construction held on 22-12-18. Also for the
internal co-ordination between the STP, MEP works as well as vendors.
2) Design Review meeting with Genesis & Ralys held on 13-12-18 during the month for the
design & drawings related issues & requirements for our projects.
Revision
S.No Drawing Description Type Received Date
No
TOWER – A
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 14 of 56
Driveway column schedule (DC11 -DC13)&
9 STRUCTURAL R0 27-12-2018
(RC1,RC2)
10 Driveway column schedule (DC1 -DC10) STRUCTURAL R0 27-12-2018
TOWER – B
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 15 of 56
11 Joineries details - Typical floors Architecture R0 11-12-2018
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 16 of 56
2.4. Master Construction Schedule – As per UIC
This schedule has been prepared by UIC and verified by TPL with all assumptions & requirement of
JAIN and submitted on 3rd Oct 2018.
The schedule has been reviewed by TPL keeping Jain’s requirement on completing the project by end
of May 2020, while preparing the schedule following assumptions and considerations made to
achieve the target dates of the project,
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 17 of 56
Design Consultant
1. Genesis to release all Good for construction drawings pertaining to structure & architectural
packages well in advance to TPL for review and check for constructability.
2. Genesis to release working drawings to Ralys, for releasing MEP drawings on time.
3. Ralys to adhere their schedule in line with Project schedule for releasing the GFC drawings.
JAIN’S SCOPE
3 Jain made the agreement to manage the project with labour contractor i.e Unique India
Constructions (UIC), hence it has been assumed that all required materials like cement, steel,
Binding wire, fine aggregate, coarse aggregate, Bricks for masonry, RMC & cover blocks etc., under
supply of Jains will reach site as per the project requirement.
1. Design Suggestions, Costing analysis, Coordination with designers, code practices, Quality with
Safety norms as per Project requirement.
UIC SCOPE
1. One tower crane will be provided by UIC in order to manage all the materials handling.
2. As per the project phasing all the machineries will be provided by UIC like material hoist,
passenger hoist for material and manpower movement.
3. Adequate and good condition of shuttering materials will be provided by labour contractor as per
the project requirement.
4. To manage the external development works required scaffolding materials, consider to adhere
the project schedule and to be provided as required.
5. UIC to mobilize adequate manpower for Shuttering, Reinforcement, and Concrete & Masonry
works to manage the project schedule.
1. All safety & quality standards to be followed without any deviation by UIC.
2. TPL to mobilize the resources for Civil & MEP engineers as per project needs.
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 18 of 56
SECTION – 3: PROJECT CONTROLS
Sl. This
Achieved Balance
No Description Floor Unit month Remarks
qty qty
. planned
TOWER - B
Excavation
PCC
RCC
Footings (Expansion Joint) Nos 4.00 (8) PCC not yet done
1 Foundation 12.00
Compaction in
Plinth Beam Cellar 3 Rmt 556.00
4 815.00 (259) progress
TOWER - A
Excavation
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 19 of 56
running at site. also
Footings Nos 40 14 delay in shifting
2 Foundation (26)
excavated soil.
PCC
RCC
This
Sl. Achieved Balance
Description Floor month Remarks
No. Unit qty qty
planned
STP works
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 20 of 56
3.2 Concrete & Reinforcement Planned vs. Achieved – Dec’2018
%
Item Description Unit Planned Achieved
Achieved
Concrete
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 21 of 56
3.3- Manpower Planned by TPL vs Achieved by UIC– December 2018
Planned
Sl.No Labour Category Unit for this Achieved Balance Remarks
month
1 Carpenter Nos 55 54 -1
2 Carpenter helper Nos 63 55 -8
3 Fitter Nos 43 20 -23
4 Fitter helper Nos 62 21 -41
5 Mason Nos 9 7 -2
6 MC Nos 55 36 -19
7 FC Nos 12 15 3
299 208 -91
TOWER - B
TOWER - A
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 22 of 56
3.5 - Next Month Plan – January 2019
S Earth
Description PCC RCC Remarks
No work
TOWER - B
TOWER - A
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 23 of 56
8 Cellar-2 slab RCC (Pour-2) Cum 164 16 180
Column Cellar2 to cellar-1
9 Cum 31 46 77
Level
Staircase-1 up to mid
10 Cum 5 5
landing
11 Cellar-2 slab RCC (Pour-3) Cum 216 30 246
Block-A
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 24 of 56
SECTION – 4 Monthly Quality Report
4.1 CONTENTS
1 Introduction 03
2 Objectives 03
3 Review of Drawings 03
I. Technical Specifications 03
Architectural) 03
7 Calibration List 08
9 List of Trainings 11
14 List of Documents 19
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 25 of 56
1. Introduction:
This document is the Monthly Project Quality Report of Jain Sri Ram Garden.
The purpose of this report is to provide an overview of the activities which are being
carried out and the quality standards of operation it conforms to and quality standards
which are being implemented.
2. Objectives:
It is the policy of TATA Projects Limited in executing the project to implement a
project QMS which complies with the relevant sections of ISO 9001 and provide
assurance that the services provided to comply with the specified contractual, safety,
environmental, statutory and GEP requirements of the project. In addition, TATA is
committed to provide the following:
3. REVIEW OF DRAWINGS:
I. Technical Specifications
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 26 of 56
4. Quality Control Procedures
Works are carried out by standard specification as per standard Operating
Procedure.
Checklist for every item of work has been implemented and the same is followed
in the site.
Concrete Compressive strength is being done on daily basis and concrete
register is maintained to monitor cube log on daily basis.
Maintaining tower wise daily documentation of checklists.
Construction works are monitored by Execution team and stage wise inspection
is being carried out as per approved check list and proceeding for next activity.
Any Quality Deviation observed and is carried out to the concerned contractor
Manager and Engineer via email and site instruction book as a SOR daily basis.
Structural activities have been going on as per sequence of work.
Electrical works are monitored by MEP team and stage wise inspection is being
carried out as per approved check list and proceeding for next activity. (For
Earthling Pits)
Sl
no Vend Required Submission Approval
or Description Document No Date Date Date Status
PJ/TPL/OPE/QAQC/FQP Approv
1 UIC Field Quality Plan /01 01-Oct-18 17-Oct-18 17-Oct-18 ed
PJ/TPL/OPE/QAQC/PCC Approv
2 UIC PCC Laying /02 01-Oct-18 08-Nov-18 08-Nov-18 ed
PJ/TPL/OPE/QAQC/FF/0 Approv
3 UIC Formwork For footing 3 01-Oct-18 17-Oct-18 17-Oct-18 ed
PJ/TPL/OPE/QAQC/FC/0 Approv
4 UIC Footing Concreting 4 01-Oct-18 14-Oct-18 14-Nov-18 ed
PJ/TPL/OPE/QAQC/SW/ Approv
5 UIC Surveying work 05 01-Oct-18 09-Oct-18 10-Oct-18 ed
PJ/TPL/OPE/QAQC/CR Approv
6 UIC Concrete Repair Work W/06 01-Oct-18 13-Nov-18 13-Nov-18 ed
PJ/TPL/OPE/QAQC/TCE/ Approv
7 UIC Tower Crane Erection 07 01-Oct-18 22-Oct-18 25-Oct-18 ed
PJ/TPL/OPE/QAQC/RWF Approv
8 UIC Retaining Wall formwork /08 01-Oct-18 23-Oct-18 23-Oct-18 ed
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 27 of 56
Work Method Statement Chat
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 28 of 56
BLOCK-B, Grid no: Dismantled the
A / PY1, Column column & clean
no DC5, plumb out with wire brush 01.12.2018
not in alignment Report- (Recast the
2 30.11.2018 CLOSED
up to 10mm + 002 same with
need to rectify taking prior
ASAP. approval from
PMC)
BLOCK-B, Grid no:
PX2-PY1.
Observed column
concrete
proceeded at site Dismantled the
without clearance column & clean 08.12.2018
from PMC. As per with wire brush
drawing column Report- (Recast the
3 06.12.2018 CLOSED
concrete grade is 003 same with
M25 but pouring taking prior
concrete grade approval from
was M20. (Ref DC PMC)
number:
200944754, time of
entry:08:55pm)
Dismantled the
BLOCK-B, Grid no: column & clean
O-004. Improper with wire brush 14.12.2018
workmanship Report- (Recast the
4 12.12.2018 CLOSED
while handling 004 same with
vibrator. taking prior
approval from
PMC)
BLOCK-B, Grid no:
H / 013, plinth Dressing up-to
Report-
5 beam below of the 22.12.2018 the level CLOSED
005
column plumb out matching as 23.12.2018
15mm. per SOP
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 29 of 56
7. Calibration List:
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 30 of 56
8. Quality Observations Reports:
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 31 of 56
Quality Observations Reports
01 September 11 11 00
02 October 11 11 00
03 November 20 19 01
04 December 10 10 00
Total 52 51 01
01 September 01 03 05 01 01
02 October 01 02 02 06 00
03 November 01 02 07 10 00
04 December 00 04 00 06 00
Total 03 11 14 23 01
01 November 30 30 00
02 December 31 31 00
TOTAL 61 61 00
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 32 of 56
9. List of Trainings:
Conducting every morning Quality tool box training to avoid quality deviations.
Layer of soil thickness marking done to ensure the fillup.
Slump & Cube register maintained to monitor the concreting activities.
Cementious coating applied to rebar's.
Providing shear key to concrete structure.
At all construction joints concrete chipped before proceeding for fresh concrete.
Proper curing providing by maintaining & applying gunny bags to concrete structure.
Curing tank water Periodically changing.
End of day meeting conducting every day & discussing regards quality deviations.
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 33 of 56
Good Practices
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 34 of 56
Good Practices for Curing
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 35 of 56
1,1 Sample Approvals:
01 September 00 00 00
02 October 02 02 00
03 November 03 03 00
04 December 00 00 00
Total 05 05 00
Concrete Cubes are casted for every day consignments (Ultratech RMC), 7 days and
28 days’ Compressive strength tests have been tested and results are found OK.
Soil Compaction tests have been tested and result are found ok.
River sand received & the lab test reports found ok.
Waterproofing compound chemical reports reviewed and found ok.
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 36 of 56
Witness/Review of Tests
Cubes Test
on 7 days
M45 42 42 00 42 42 00
M30 01 01 00 01 01 00
M25 80 80 00 80 80 00
M20 14 14 00 14 14 00
M25 WPC 10 10 00 10 10 00
Cubes Test
on 28 days
M45 19 19 00 19 19 00
M30 01 01 00 01 01 00
M25 57 57 00 57 57 00
M20 09 09 00 09 09 00
M25 WPC 10 10 00 10 10 00
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 37 of 56
LAB TEST:
RIVER
SAND
Sieve 01 01 00 01 01 00
Analysis of 13-Nov-
Fine 2018
Aggregate 01 01 00 01 01 00 04-Dec-
2018
01 01 00 01 01 00 18-Dec-
2018
Silt content 01 01 00 01 01 00 13-Nov-
of Fine 2018
Aggregate
01 01 00 01 01 00 04-Dec-
2018
01 01 00 01 01 00 18-Dec-
2018
Silt & Clay 01 01 00 01 01 00 13-Nov-
of Fine 2018
Aggregate
01 01 00 01 01 00 04-Dec-
2018
01 01 00 01 01 00 18-Dec-
2018
River sand received in the month of December 2018, internal site lab test conducted
and results are found ok.
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 38 of 56
12. Action Points for Sub Contractor:
Daily activities on the site to be carried out with approved Quality control procedures.
If there are any quality issues, it has to be brought to the notice of respective block
representative and corrective actions to be attended as per the approved procedures.
For worker’s regular quality TBT should be conducted to follow the procedures as per
given work method statement.
Uneven Shuttering plates should not be used for any type of RCC works.
Level given by surveyor on one column has to be transferred to all columns and it has
to be cross checked before starting of shuttering.
Foam sheet to be placed at starter level before fixing column boxes and at plate to plate
joints to avoid leakage of cement slurry.
Retaining wall, footings & pedestals concreting should be done under proper
supervision to maintain cover, vibration to avoid honey combs and concrete level to
avoid chipping.
Tie rod holes in Retaining walls & Footings should be closed with grout material.
While Back filling avoid large boulders and proper consolidation to be done before
proceeding for next activity.
Column concreting should be done under proper supervision to maintain cover,
vibration to avoid honey combs and concrete level to avoid chipping
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 39 of 56
Site Lab Test PJ/TPL/CSA/QAQC/SLTR/1 Quality 2018-
10 Reports 0 Rack 2022 Active
Concrete Quality 2018-
11 Register PJ/TPL/CSA/QAQC/CR/11 Rack 2022 Active
Quality 2018-
12 Cube Register PJ/TPL/CSA/QAQC/CUR/12 Rack 2022 Active
Quality
Observation PJ/TPL/CSA/QAQC/QOR/1 Quality 2018-
13 Report 3 Rack 2022 Active
Quality 2018-
14 Checklist PJ/TPL/CSA/QAQC/PPC/14 Rack 2022 Active
Quality 2018-
15 Formats PJ/TPL/CSA/QAQC/AF/15 Rack 2022 Active
Concrete Batch Quality 2018-
16 Sheets PJ/TPL/CSA/QAQC/CBS/16 Rack 2022 Active
Project Quality 2018-
17 Specification PJ/TPL/CSA/QAQC/PS/17 Rack 2022 Active
Soil Geo
Technical
Investigation PJ/TPL/CSA/QAQC/GTIR/1 Quality 2018-
18 Report 8 Rack 2022 Active
Quality 2018-
19 Factory Visit PJ/TPL/CSA/QAQC/FV/19 Rack 2022 Active
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 40 of 56
Section – 05 Monthly Safety Report
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 41 of 56
SITE SAFETY RULES:-
These rules are applicable to all persons entering the site including Contractors, Sub-
Contractors, Engineers, Supervisor, Workers, Visitors and others
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 42 of 56
PERSONEL PROTECTIVE EQUIPMENTS:-
All types of Personal Protective Equipment (PPE) required at site shall be made available at stores.
PPE shall confirm to the relevant IS codes. The requirement of PPE shall be assessed well in advance
by doing risk assessment (JSA). The quantity of PPE shall be assessed in construction with the
planning department and labour deployment. Sufficient buffer stock of PPE shall be discarded. Misuse
of PPE shall be monitored and disciplinary action shall be taken against the defaulters
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 43 of 56
ENVIRONMENT
ACHIEVED-DECEMBER-18 PLANNING-JANUARY-19
Ensure for daily house keeping Ensure for daily house keeping
Daily water has sprinkled at all walkways to Ensure to sprinkle water daily to minimise dust
minimise the dust.
Tray install at place to avoid spillage of oil.
Segregation of all plastic material in site area Train workers and staff to use less plastic in site
and labour camp. area to avoid land contamination.
Implementing environment related signage’s. Bring awareness to workers and staff about
environmental importance.
Waste disposal register maintains
Disposal of Bio-medical waste to Tie up
hospital.
Segregation of all machinery waste arise of
work activity
Ensure to sprinkle water daily to minimise dust
Follow MSDS to do work safely
Train workers and staff to use less plastic in
site area to avoid land contamination.
Bring awareness to workers and staff about
environmental importance.
HEALTH
ACHIEVED-DECEMBER-18 PLANNING-JANUARY-19
Labour colony housekeeping done and Doctor visit to labour camp & site twice of a month.
sprinkled bleaching powder.
03 First aid cases attended. Regular cleaning of water tank in a labour camp
and site.
Arranged portable drinking water facility at site Ensure for hygiene and sanitation in labour camp.
and labour camp.
First aid room facility arranged at site. Planning of pest control monthly 4 times.
Near hospital type letter. Cleaning of septic tank as and when required.
Water tank cleaning date display. Work hard to reduce first aid cases to low numbers.
Pest control work has initiated. Planning of fire drill
Competent first aider has hired.
Health and fitness certificate along with eye
test has produced of tower crane operator and
signal man.
Regular cleaning of water tank in a labour
camp and site.
Ensure for hygiene and sanitation in labour
camp
Planning of pest control monthly 4 times.
Cleaning of septic tank as and when required.
Work hard to reduce first aid cases to low
numbers.
SAFETY
ACHIEVED-DECEMBER-18 PLANNING-JANUARY-19
Training given to security team and tracking
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
their entry and
Page 44 of 56
out time.
All deep excavation area has hard barricaded. Placing of safety banners in site to aware of safety
PPE’s has provided for all staff and workers Placing of emergency switch in bar bending and
cutting machines
One tower crane erected successfully. Give body earthing to cutting and bending
machines.
TAG system for scaffolding ELCB&RCCB tester(multi meter) use to check
sensitivity
Safety statistics board All the electrical cables run over head to avoid
obstructions.
Making of assembly point and safety park Implementation of anemometer and safe load
indicator of tower crane
Displaying of emergency contact numbers Tying over running rebar’s of plinth beam to avoid
stabbing, obstructions.
Safety Monique display Use of more aluminium, mild steel ladders to safe
work
Provide efficient illumination to perform work in a
safer manner.
SAFETY INSPECTIONS:
ACHIEVED-DECEMBER-18 PLANNING-JANUARY-19
ACHIEVED-DECEMBER-18 PLANNING-JANUARY-19
Conducted work at height training among all Training about correct use of PPE by the work activity
workers
Induction training to all new workers and Training to Fire drill
employees
Training to use of CT-prop jack pin use
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 45 of 56
NUMBER OF TRAINING PROGRAMMES CONDUCTED
1) The minimum PPE’S like Helmet, shoes and reflective safety jackets shall only be allowed enter site
gate premises
2) Excavation & Filling - Safety Helmet, Protective foot wear, Cotton Hand Gloves, soft and hard
barrication and Sufficient Lighting
3) Reinforcement and Shuttering work- Safety Helmet, Protective foot wear,
Cotton and Rubber hand Gloves, Goggles , full body harness and fall
arrestor.
3) Height works - Safety Helmet, Protective foot wear, full body harness and fall arrestor.
4) Grinding & Chipping works - Safety Helmet, Safety Shoes, Face Shield & leather Gloves.
5) Concreting Works - Safety Helmet, Gumboot, Rubber hand Gloves, full body harness and fall
arrestor.
6) Welding & Gas Cutting - Safety Helmet, Safety Shoes, Face Shield with suitable filter & leather.
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 46 of 56
PPEs Store Inventory Report
1. Full compliance with safe work permit conditions and site relevant procedures shall be ensured
for any activity in construction areas, to protect possible ignition of flammable substances /
gases from construction – associated operation.
2. Electrical equipment will be checked daily for possible defects by the assigned user and
periodically by the competent electrical maintenance personnel.
3. Smoking will be strictly allowed only in the approved smoking area.
4. Drip vans shall be provided under faucets of temporary fuel/ oil drums to catch spills and leaks.
Hand pumps shall be used for transferring flammable liquids.
5. Where fuel tanker is prohibited, approved safety fuel cans shall be used for refuelling of internal
combustion equipment welding machine, roller, compressor etc. Plastic containers are not
acceptable for storing any fuel. Engine of the equipment to be refuelled shall be shut down prior
to refuelling. Proper grounding / bonding shall be observed during equipment refuelling.
6. Welding equipment, hot surfaces and other possible sources of heat/ignition will be kept isolated
from combustible material.
7. Wooden blocks /timbers for any reason shall not be used for oxy acetylene cutting.
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 47 of 56
8. Halogen lamps if used shall be mounted on stands and shall be ensured it is not kept near
combustibles.
9. Hot work crew shall exercise extra precautions in performing hot works and in constant
monitoring of possible indirect ignition sources such as falling hot slag from welding
/cutting/grinding operations.
10. Open fires/open burning will never be permitted at work site.
11. Proper binding and grounding techniques will be applied where static electricity could be
possible source of ignition. Conductors used for grounding and grounding stationary and
movable equipment e.g. welding machines, generators, fuel tankers etc. shall be of adequate
size to carry the anticipated current. Installation and periodic inspection of all bonding/grounding
attachments shall be made by competent electrician.
Height Work Permit – Work at more than 2m height shall be performed with necessary permit. (b). Hot
Work Permit – Any work, tools or equipment (welding, burning, grinding, vehicles, portable welders,
etc.) which might provide a source of ignition for a flammable mixture.
Night Work Permit – Night Work Permit shall be followed exposing the interior of any process
equipment such as tanks, pipes, vessels, etc to the atmosphere.
WELFARE OF WORKMEN:
LABOUR CAMP: Labour camp will be made of material like GI sheet etc. Electrical supply for lighting
in labour camp will be given through safety devices. Suitable crèches with education facilities will be
made available in labour camp.
DRINKING WATER: Drinking water shall be made available in number of places to cater the labour
strength. The container/ tank shall be cleaned regularly. Location of drinking water facilities shall be
identified at later stage.
SANITARY: Toilets shall be constructed for gents and ladies separately at site with proper drainage
arrangements. General disinfestations treatment will be carried out to control mosquito etc. Good
housekeeping will be maintained.
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 48 of 56
01
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 49 of 56
25 Excavation As &when before 03 SRG/TPL/SAF/EP/0
task 2
Power tools Excavation Ladder safety, Alcohol & MATERIAL LIFTING &
safety, safety, safety, scaffolding Tobacco MANUAL SHIFTING
housekeeping, Machine safety, Awareness, HANDLING, procedures,
electrical safety operating HOUSEKEEPI housekeeping, ELECTRICAL PROPER
& PPEs& procedures, NG & PPEs. hot work, SAFETY, ACCESS
labour camp Housekeeping PPEs. HOUSEKEEPI WORKING
cleaning. & PPEs. Concrete work NG & PPEs. AREA, PPEs.
& night work.
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 50 of 56
Alcohol & MATERIAL Ladder safety, Excavation LIFTING & HOUSEKEEPI
Tobacco MANUAL scaffolding safety, safety, SHIFTING NG,
Awareness, HANDLING, safety, Machine procedures,
housekeeping, ELECTRICAL HOUSEKEEPI operating PROPER HOT WORK,
hot work, SAFETY, NG & PPEs. procedures, ACCESS HEIGHT
PPEs. HOUSEKEEPI Housekeeping WORKING WORK &
NG & PPEs. & PPEs. AREA, PPEs. PPEs.
Concrete work LIFTING & MATERIAL Ladder safety, HOUSEKEEPI Alcohol &
& night work. SHIFTING MANUAL scaffolding NG, Tobacco
Ladder safety, procedures, HANDLING, safety, Awareness,
scaffolding PROPER ELECTRICAL HOUSEKEEPI HOT WORK, housekeeping,
safety, ACCESS SAFETY, NG & PPEs. HEIGHT hot work,
HOUSEKEEPI WORKING HOUSEKEEPI WORK & PPEs.
NG & PPEs. AREA, PPEs. NG & PPEs. PPEs. Concrete work
Concrete work Concrete work & night work.
& night work. & night work.
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 51 of 56
SAFETY STATISTICS REPORT
Report Of the Month & Year DECEMBER-18
Total numbers of Workers this month 6371
Total Safe Man Hours Worked this month 70056
Total Cumulative Safe Man Hours Worked 149079
Number of Fire Incidents 00
Number of Near Miss Cases 00
Number of Minor Injuries 00
Number of First Aid Cases this month 03
Number of First Aid Cases Cumulative 09
Man Days Lost 00
Number of LTI(Lost Time Injuries) 00
Number of fatal Accidents 00
Other Mishap/ Dangerous Occurrence 00
Number of Tool Box Talk(TBT,PEP Talk) By SO(Safety Officer) 27
No. Of Tool Box by Staff/ Engineers 02
Number of Health Check Up conducted 00
Number of Workers undergone Health Check up 01
Number of STOP WORK ORDER Issued 00
Safety Meeting For The Month 01
Number of Safety Observation 11
AFR(Cumulative)=(Fatal Accidents*1000000)/Cumulative safe man 00
hours
IFR(This Month)=(First Aid Cases*100000)/Safe Mane Hours This 4.28
Month
IFR(Cumulative)=(First Aid Cases*100000)/ Safe Mane Hours 2.01
Cumulative
IFR=(Near Miss Case*1000000)/Safe man hours this month 00
SR(Severity Rate)=(No of man days lost*100000/Total man days 00
worked)
Average No’s of Workers Daily 205.5
Safety Rewards Awarded
To Staff 00
To Workers 05
Penalty Imposed
Staff Attended 00
Worker/Contractor 00
Safety Induction This Month
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 52 of 56
WELCOME TO JAIN SRI RAM GARDEN PROJECT.
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 53 of 56
SPEECH OF UIC SAFETY OFFICER SAGAR & SANTHOSH FOR CORE IMPORTANCE
HEALTH&SAFETY
AWARDS PRESENTATION
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 54 of 56
AWARD PRESENTATION BY TPL EHS OFFICER SAMIR KUMAR PANDA
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 55 of 56
AWARD PRESENTATION BY UIC EHS OFFICER SANTHOSH NAIK
Reporting Period: 01st December 2018 to 31st December 2018 Date of issue: 9th January 2019 I
Page 56 of 56