You are on page 1of 8

PROJECT: UPDATED: 03.05.

2014
IR # Brief description of activity
Date
submitted
Date
returned
Comments
AD7176/CVL/IR-001
Inspection for Gate Level (Temp. Gate Level = +2.59 M=0.00) as per
DM approved drawing # A-001 & DM Survey Section Bench mark level
10.07.2013 13.07.2013
Approved
(Refer DC comments)
AD7176/CVL/IR-002 Inspection for Main Villa Layout Foundation as per Drawing no. S-101 01.08.2013 04.08.2013
Approved
(Refer DC comments)
AD7176/CVL/IR-003
Inspection for Completion of Stone Columns as per approved drawing
# DBB/AM87855/GI/LA/1001 Rev.0.
19.08.2013 20.08.2013
Approved
(Refer DC comments)
AD7176/CVL/IR-004 Formation & Blinding Inspection for underground water tank base. 26.08.2013 31.08.2013
Approved
(Refer DC comments)
AD7176/CVL/IR-005 Inspection of formation level for Main Villa footings 26.08.2013 31.08.2013
Approved
(Refer DC comments)
AD7176/CVL/IR-006
Inspection for Blinding and Anti Termite Treatment for 29 nos. Main
Villa Footings
01.09.2013 03.09.2013
Approved
(Refer DC comments)
AD7176/CVL/IR-007 Inspection of Blinding for 19 Nos. Boundary Wall Footings 01.09.2013 03.09.2013
Approved
(Refer DC comments)
AD7176/CVL/IR-008
Inspection for 2 layers water proofing and protection board works at
under ground water tank
10.09.2013 17.09.2013 Approved
AD7176/CVL/IR-009 Inspection for Main Villa & Compound Wall Footings (55 Nos.) 14.09.2013 18.09.2013 Approved as Noted
AD7176/CVL/IR-010
Inspection for Balance Footing of Main Villa (10 Nos.) and Compound
Wall (2 Nos.)
19.09.2013 05.10.2013 Approved
AD7176/CVL/IR-011
Rebar & Formworks Inspection for Strap Beam (8 Nos.)
G-F / 1-3 and F-G / 11-13
19.09.2013 05.10.2013 Approved
AD7176/CVL/IR-012 Rebar & Formworks inspection for Neck Column 26.09.2013
AD7176/CVL/IR-013
Rebar & Formworks Partial inspection for Boundary Wall
Tie Beam
26.09.2013
AD7176/CVL/IR-014 Rebar & Formworks inspection for UG Water Tank 28.09.2013 05.10.2013 Approved
AD7176/CVL/IR-015 Inspection for Bituminous Painting for Main villa Neck column 29.09.2013 05.10.2013 Approved
AD7176/CVL/IR-016 Inspection for Bituminous Painting for Main villa Footing 29.09.2013 05.10.2013 Approved
AD7176/CVL/IR-017 inspection of bituminous painting for boundary wall footing (part) 29.09.2013 05.10.2013 Approved
AD7176/CVL/IR-018
Rebar & Formworks inspection for boundary wall - tie beam and neck
column grid G
01.10.2013 05.10.2013 Approved
AD7176/CVL/IR-019
Rebar & Formworks inspection for garage columns (grid F/G - 1 to 3,
11, 12, 13 - total 10 nos.)
03.10.2013 05.10.2013 Approved
AD7176/CVL/IR-020
REBAR & FORMWORK INSPECTION FOR UNDER GROUND WATER TANK
SLAB
03.10.2013 28.10.2013 Approved
AD7176/CVL/IR-021
REBAR & FORMWORK INSPECTION FOR MAIN VILLA TIE BEAM Tie
beam # PB109 on Grid 2/F-D and 12/F-D (2 nos)
07.10.2013 28.10.2013 Approved
AD7176 - G+1 x 2 NOS. VILLAS AT UMM AL SHEIF
INSPECTION REQUEST LOG
CIVIL WORKS
A Dutco Balfour Beatty Company WI PM 015/Jan. 2012
AD7176/CVL/IR-022
REBAR & FORMWORK INSPECTION FOR MAIN VILLA TIE BEAM GRID
E (3, 4, 5, 6, 8, 9, 10 & 11) and GRID F (6, 7, 8)
07.10.2013 28.10.2013 Approved
AD7176/CVL/IR-023
REBAR & FORMWORK INSPECTION FOR MAIN VILLA (OUTSIDE)
FOOTINGS GRID A, B (2 & 4)
07.10.2013 28.10.2013 Approved
AD7176/CVL/IR-024
REBAR & FORMWORK INSPECTION FOR BOUNDARY WALL TIE BEAM
GRID 1 (B-F), PB1 Section 3-3
09.10.2013 28.10.2013 Approved
AD7176/CVL/IR-025
REBAR & FORMWORK INSPECTION FOR CANTILEVER SLAB (GRID F (11-
12) MAIN VILLA & GARAGE AREA
12.10.2013 28.10.2013 Approved
AD7176/CVL/IR-026
REBAR & FORMWORK INSPECTION FOR TIE BEAM MAIN VILLA (1 & 2)
GRID A-E (2-12)
13.10.2013 28.10.2013 Approved
AD7176/CVL/IR-027
REBAR & FORMWORK INSPECTION FOR CANTILEVER SLAB (GRID F (3-6)
MAIN VILLA # 1
13.10.2013 28.10.2013 Approved
AD7176/CVL/IR-028
INSPECTION OF TERMITE / REBAR WORKS FOR GRADE SLAB (125MM
THICK) IN BETWEEN GRID A-D / 2-7 (Refer attached highlighted on
drawing # S-103
30.10.2013
AD7176/CVL/IR-029
INSPECTION FOR REBAR OF GROUND FLOOR COLUMN (VILLA) IN
BETWEEN GRID F-A / 2-12
05.11.2013 06.11.2013 Approved
AD7176/CVL/IR-030
INSPECTION FOR REBAR & FORMWORKS FOR GARAGE ROOF IN
BETWEEN GRID 11-13 / F-G
05.11.2013 06.11.2013 Approved
AD7176/CVL/IR-031
REBAR & FORMWORK INSPECTION FOR GARAGE ROOF SLAB (GRID E 1-
3 / F-G) - MAIN VILLA # 1
12.11.2013 26.11.2013 Approved as Noted
AD7176/CVL/IR-032
FORMWORKS INSPECTION FOR GRAOUND FLOOR COLUMNS IIN
BETWEEN GRID A-F/2-7 (COLUMNS 15 NOS.) - MAIN VILLA 1
13.11.2013 26.11.2013 Approved as Noted
AD7176/CVL/IR-033
FORMWORK FOR GF COLUMN IN BETWEEN GRID 7-12/A-F MAIN VILLA
1
18.11.2013 26.11.2013 Approved as Noted
AD7176/CVL/IR-034
REBAR & FORMWORKS BOUNDARY WALL COLUMN & COPPING ON
GRID 1 /A-F & GRID 13 / A-F - MAIN VILLA # 1
18.11.2013 26.11.2013 Approved as Noted
AD7176/CVL/IR-035 Rebar & Formwork for Staircase 1 & 2 up to Second Landing 25.11.2013 09.12.13 Approved
AD7176/CVL/IR-036 Grade Slab Concrete Grid B-F / 7-12 25.11.2013 09.12.13 Approved
AD7176/CVL/IR-037 Grade Slab Concrete Grid C-F / 2-12 25.11.2013 09.12.13 Approved
AD7176/CVL/IR-038 Inspection of Reinforcement and Formworks for FF main villa A-F/2-12 14.12.2013 24.12.13 Approved as Noted
AD7176/CVL/IR-039
Form works and concreting of electrical & plumbing manhole @
garage 1 & 2 (6+6 manholes)
15.12.2013
AD7176/CVL/IR-040
AD7176/CVL/IR-041
Inspection for Formwork & Reinforcement of First Floor Columns Villa
1 & 2 (Total 24). Grid 2-12 / A-F
28.12.13 Approved
AD7176/CVL/IR-042
Inspection for Rebar / Formwork for Concrete of First Floor Columns
Villa 1 & 2 (Column# C2, C4, C12, C14, C15, C16, C17, C11, C20, C3, C5 &
C9)
28.12.13 Approved
AD7176/CVL/IR-043 Inspection for Block work layout for Car Parking (Garage Area) 28.12.13 Approved
AD7176/CVL/IR-044 Inspection for Deshuttering of Slab Villa 1 & 2 (Grid B-E / 2-10) 29.12.13
AD7176/CVL/IR-045
Inspection for Reinforcement Formwork & Concrete for Columns @
Villa 1 (Grid A-F / 7-12)
28.12.13
AD7176/CVL/IR-046
Inspection for Deshuttering of First Floor Slab Main Villa Grid A-F / 10-
12
31.12.13
AD7176/CVL/IR-047
INSPECTION FOR MOCK-UP OF PAINTING WORKS EXTERNAL STONE
PAINT 20% LIGHTER
06.01.14 09.03.14
AD7176/CVL/IR-048
INSPECTION FOR BLOCK WORK LAYOUT VILLA 2
Grid A-F/7-12 07.01.14 09.01.14 Approved
AD7176/CVL/IR-049
INSPECTION FOR BLOCK WORK LAYOUT VILLA 1
Grid A-F/2-7 09.01.14 14.01.14 Approved as Noted
AD7176/CVL/IR-050 INSPECTION FOR ROOF SLAB SCAFFOLDING.
AD7176/CVL/IR-051 INSPECTION FOR ROOF SLAB FORMWORK. 20.01.14 26.01.14 Approved as Noted
AD7176/CVL/IR-052
INSPECTION FOR REINFORCEMENT, SHUTTERING AND CONCRETE OF
PARAPET WALL
Grid A-F/7-12
01.02.14 5.0214 A
AD7176/CVL/IR-053
INSPECTION FOR REINFORCEMENT, SHUTTERING AND CONCRETE OF
ROOF SLAB 4 COLOUMN
Grid A-F/7-12
01.02.14 5.0214 A
AD7176/CVL/IR-054
INSPECTION FOR REINFORCEMENT, SHUTTERING AND CONCRETE OF
GARAGE AREA GROUND FLOOR BUILDING 1 & 2
Grid G-F/1-3, 11-13
01.02.14 5.0214 A
AD7176/CVL/IR-055 INSPECTION FOR DE SHUTTERING OF ROOF SLAB FOR ALL BUILDING. 03.02.14 12.02.14 A
AD7176/CVL/IR-056 INSPECTION FOR ROOF SLAB FOUR COLUMN GRID - D/3,4,5 05.02.14 12.02.14 A
AD7176/CVL/IR-057 INSPECTION FOR ROOF SLAB UPSTAND CONCRETE GRID D/3,4,10,11 09.02.14 12.02.14 A
AD7176/CVL/IR-058
INSPECTION FOR SHUTTER REINFORCEMENT CONCRETE OF PARAPET
WALL GRID A-F/2-7
09.02.14 12.02.14 A
AD7176/CVL/IR-059
INSPECTION FOR ROOF SLAB SHUTTER, REINFORCEMENT & CONCRETE.
GRID-D/3, D/11 15.02.14 16.02.14 A
AD7176/CVL/IR-060
INSPECTION FOR WATER TANK UPSTAND FOOTING 300X1800X850.
GRID-C-D/4-5, C-D/9-10 15.02.14 16.02.14 A
AD7176/CVL/IR-061 INSPECTION FOR PUMP FOUNDATION CONCRETE 850 X 1350. 15.02.14 16.02.14 A
AD7176/CVL/IR-062
INSPECTION FOR SKY LIGHT OPENING SHUTTER, REINFORCEMENT &
CONCRETE.
GRID-C-D/6-7, C-D/7-8
15.02.14 16.02.14 A
AD7176/CVL/IR-063
INSPECTION FOR SKY LIGHT OPENING SHUTTER, REINFORCEMENT &
CONCRETE.
GRID-B-C/6-7, B-C/7-8
15.02.14 16.02.14 A
A Dutco Balfour Beatty Company WI PM 015/Jan. 2012
AD7176/CVL/IR-064 INSPECTION FOR GARAGE AREA PLASTER PREPARATION WORKS. 15.02.14 16.02.14 A
AD7176/CVL/IR-065
INSPECTION FOR GARAGE AREA PARAPET WALL SHUTTER,
REINFORCEMENT & CONCRETE.
GRID- F-G/1-3, F-G/11-13
15.02.14 16.02.14 A
AD7176/CVL/IR-066
INSPECTION FOR FIRST FLOOR BLOCK WORK LAYOUT.
GRID- A-F/2-7 22.02.14. 26.02.14 B
AD7176/CVL/IR-067
INSPECTION FOR FIRST FLOOR BLOCK WORK LAYOUT.
GRID- A-F/7-12 24.02.14 04.03.14 B
AD7176/CVL/IR-068
INSPECTION FOR GROUND FLOOR PLASTER WORK PREPARATION.
GRID- B-C/11-12 24.02.14 04.03.14 B
AD7176/CVL/IR-069
INSPECTION FOR CAR PARK AREA PLASTER WORK PREPARATION.
GRID- F-G/1-3 24.02.14 04.03.14 B
AD7176/CVL/IR-070
INSPECTION FOR ROOF SLAB PARAPET BLOCK WORK.
GRID- D/3-11 24.02.14 04.03.14 B
AD7176/CVL/IR-071
INSPECTION FOR ROOF SLAB PARAPET BLOCK WORK.
GRID- A-F/7 24.02.14
AD7176/CVL/IR-072
INSPECTION FOR PLASTER WORK PREPARATION AT GUEST ROOM AND
GUEST TOILET.
04.03.14 09.03.14 B
AD7176/CVL/IR-073
INSPECTION FOR ROOF SLAB FOAM WORK WATER PROOFING.
GRID 2-12/A-F 11.03.14 19.03.14 A
AD7176/CVL/IR-074
INSPECTION FOR BOUNDARY WALL EXCAVATION FOR BLINDING
CONCRETE.
11.03.14 19.03.14 A
AD7176/CVL/IR-075 INSPECTION FOR PLASTER WORK DINING ROOM & LIVING ROOM. 13.03.14 19.03.14 A
AD7176/CVL/IR-076
INSPECTION FOR BOUNDARY WALL FOOTING SHUTTER,
REINFORCEMENT AND CONCRETE.
GRID 1-13
19.03.14 24.03.14 A
AD7176/CVL/IR-077 INSPECTION FOR EXTERNAL PLASTER WORK (MOCK-UP) 19.03.14 24.03.14 A
AD7176/CVL/IR-078 INSPECTION FOR PAINT AT GUEST & TOILET ROOM (MOCK-UP) 23.03.14 29.03.14 A
AD7176/CVL/IR-079 INSPECTION FOR WINDOW AT GUEST & TOILET ROOM (MOCK-UP) 23.03.14 29.03.14 NOT APPROVED
AD7176/CVL/IR-079
Rev.01
INSPECTION FOR WINDOW AT GUEST & TOILET ROOM (MOCK-UP) 02.04.14 06.04.14 A
AD7176/CVL/IR-080 INSPECTION FOR CEILING AT GUEST & TOILET ROOM (MOCK-UP) 23.03.14 29.03.14 A
AD7176/CVL/IR-081
INSPECTION FOR BOUNDARY WALL TIE BEAM REINFORCEMENT AND
CONCRETE.
23.03.14 29.03.14 A
AD7176/CVL/IR-082 INSPECTION FOR ROOF FOAM CONCRETE VILLA 1 & 2. 25.03.14 29.03.14 A
AD7176/CVL/IR-083 INSPECTION FOR ROOF FOAM CONCRETE GARAGE 1 & 2. 25.03.14 29.03.14 A
AD7176/CVL/IR-084
INSPECTION FOR ROOF FOAM CONCRETE TOP STAIRCASE PANTRY
SLAB.
25.03.14 29.03.14 A
AD7176/CVL/IR-085
INSPECTION FOR PLASTER PREPARATION OF MAID ROOM AND
KITCHEN ROOM.
25.03.14 29.03.14 A
AD7176/CVL/IR-086
INSPECTION FOR WATER PROOFING PRIMER & MEMBRANE
APPLICATION
AT VILLA 1 & 2. 28.03.14 08.04.14 B
AD7176/CVL/IR-087
INSPECTION FOR WATER PROOFING PRIMER & MEMBRANE
APPLICATION
AT GARAGE 1 & 2. 28.03.14 08.04.14 A
AD7176/CVL/IR-088 INSPECTION FOR GUEST BED ROOM FLOOR TILE LAYOUT 30.03.14 19.04.14 A
AD7176/CVL/IR-089
INSPECTION FOR ROOF WATER PROOFING.
GRID A-F / 2-7 01.04.14 08.04.14 B
AD7176/CVL/IR-090
INSPECTION FOR PLASTER PREPARATION AND PLASTER WORK OF 1ST
FLOOR BEDROOM-1, MASTER BED ROOM-4, TOILET, STUDY ROOM,
LOBBY AND PANTRY. 01.04.014 08.04.14 B
AD7176/CVL/IR-091
INSPECTION FOR ROOF SLAB WATER PROOFING TESTING.
GRID A-F / 7-12 01.04.014 08.04.14 B
AD7176/CVL/IR-092
INSPECTION FOR WATER PROOFING TESTING AT GARAGE AREA.
GRID F-G / 1-3 & F-G/11-13
08.04.14 19.04.14 A
AD7176/CVL/IR-093
INSPECTION FOR PLASTER PREPARATION AND PLASTER OUTSIDE
WALL.
07.04.14 19.04.14 A
AD7176/CVL/IR-094
INSPECTION FOR PLASTER PREPARATION AND PLASTER WORK
ELEVATION-3.
07.04.14 19.04.14 A
AD7176/CVL/IR-095
INSPECTION FOR PLASTER PREPARATION AND PLASTER WORK
GROUND FLOOR LOBBY
07.04.14 19.04.14 A
AD7176/CVL/IR-096
INSPECTION FOR PLASTER PREPARATION AND PLASTER WORK FIRST
FLOOR FLANGE.
07.04.14 19.04.14 A
AD7176/CVL/IR-097 INSPECTION FOR MOCK UP SAMPLE FOR GRC CORNICE TYPE - 2. 15.04.14 19.04.14 A
AD7176/CVL/IR-098 INSPECTION FOR BLINDING PCC AT PUMP ROOM. 15.04.14 19.04.14 A
AD7176/CVL/IR-099
INSPECTION FOR CAST ALUMINUM RAILING SAMPLE WITH TIMBER
TOP SUBMITTED BY REGENT STEEL.
15.04.14 19.04.14 NOT APPROVED
AD7176/CVL/IR-100
SAMPLE FOR INTERLOCK PAVING - (1) RED 200 X 100 X 60 EXTERNAL
(2) GREY 200 X100X80 EXTERNAL (3) GREY 300 X 300.
15.04.14 19.04.14 A
AD7176/CVL/IR-101
INSPECTION FOR MOCKUP GRANITE SAMPLE FOR MAIN ENTRANCE
FLOOR / STEPS (a) SAUDI BIANCO (b) GOLDEN LEAF (c) ROSA PURINE
(d) NAJRAN BROWN (e) SAND DUNE (f) ROYAL CREAM.
15.04.14 19.04.14 Comments on IR
AD7176/CVL/IR-102
INSPECTION FOR MOCKUP PANTRY KIT CABINET COLOUR CHART FOR
VENEER
15.04.14 19.04.14 A
A Dutco Balfour Beatty Company WI PM 015/Jan. 2012
AD7176/CVL/IR-103
INSPECTION FOR WALL, FLOOR TILE FIXING AT KITCHEN AND UNITY
ROOM.
19.04.14 23.04.14 A
AD7176/CVL/IR-104
INSPECTION FOR SCREED AT MAIDS ROOM, KITCHEN FLOOR, POWDER
ROOM, STORE, DINING, LIVING AND ENTRANCE LOBBY.
19.04.14 23.04.14 A
AD7176/CVL/IR-105 INSPECTION FOR WATER TANK GRP AT BUILDING 1 & 2. 19.04.14 23.04.14 A
AD7176/CVL/IR-106
INSPECTION FOR ROOF FILE FIXING AT BUILDING 1 & 2.
GRID: A-F / 2-7, A-F/7-12
19.04.14 23.04.14 A
AD7176/CVL/IR-107
INSPECTION FOR FOOTING WALL, SHUTTER, REINFORCEMENT AND
CONCRETE FOR PUMP ROOM
23.04.14 26.04.14 A
AD7176/CVL/IR-108
MOCKUP INSPECTION FOR EXTERNAL SAND STONE WALL CLADDING
OPTION 1 BY AL FAHAD MARBLE
OPTION 2 BY OVERSEAS MARBLE
26.04.14 26.04.14 A
PROJECT: UPDATED: 03.05.2014
IR # Brief description of activity
Date
submitted
Date
returned
Comments
AD7176/MEP/IR-001 Laying of underground piping and gravity test - grid 7-12 / C-F 18.11.2013 26.11.2013 B
AD7176/MEP/IR-002
Laying of underground piping and gravity test as per the
highlighted drawing ref. # CEC-P-132-DR-04 & D-01 Rev. 0 and
between grid nos. C-E/2-7.
23.11.2013 24.12.13 C
AD7176/MEP/IR-003
Inspection of UPVC Duct Piping for Electrical Cables & Telephone
Cables
24.11.2013 26.11.2013 B
AD7176/MEP/IR-004
Inspection for Laying of Underground Drainage Piping from
Manhole # 5 to Manhole # 13A - Grid D-G / 2-13
10.12.2013
AD7176/MEP/IR-005 Inspection for Openings & Sleeves in the First Floor Slab 14.12.2013
AD7176/MEP/IR-006 Inspection for Conduits & Junction Boxes in the FF Slab 14.12.2013
AD7176/MEP/IR-007
Inspection for Gravity Test For the installation of underground
drainage pipes from manhole no.5 to 13A as per highlighted
drawing
22.12.13 30.12.13 B
AD7176/MEP/IR-008
INSPECTTION OF INSTALLATION AND GRAVITY TEST OF
UNDERGROUND DRAINAGE PIPES FROM MANHOLE NO.11 TO
FIC MANHOLE AS PER THE HIGHLIGHTED DRAWING
19.01.14 12.02.14 A
AD7176/MEP/IR-009
INSPECTTION OF INSTALLATION OF RAIN WATER PIPE AND
BALCONY DRAIN PIPE ALONG THE GRID NOS. B/10-12 AND
GRAVITY TEST OF THE RAIN WATER PIPES BETWEEN THE GRID
G/2-3 & G/11-12 AS PER THE HIGHLIGHTED DRAWING
(GOLDEN SUN IR # EL-01)
19.01.14 12.02.14 A
AD7176/MEP/IR-010
INSPECTTION OF CONDUITS & JUNCTION BOXES IN THE ROOF
FLOOR SLAB AS PER THE ATTACHED DRAWINGS.
(GOLDEN SUN IR # EL-02)
21.01.14 12.02.14 A
AD7176/MEP/IR-011
INSPECTTION OF MARKING FOR THE LOCATION OF SWITCHES &
SOCKETS AS PER THE ATTACHED DRAWINGS.
(GOLDEN SUN IR # EL-03)
04.02.14 12.02.14 A
AD7176/MEP/IR-012
INSPECTION OF INSTALLATION AND GRAVITY TEST FOR THE
DRAINAGE PIPES BETWEEN THE GRID NOS. B/2-7 AND E/2-7 AS
PER ATTACHED DRAWINGS.
(GOLDEN SUN IR # M-8)
08.04.14 19.04.14 A
AD7176/MEP/IR-013
INSPECTION OF INSTALLATION AND GRAVITY TEST FOR THE
DRAINAGE PIPES BETWEEN THE GRID NOS. B/7-12 AND E/7-12
AS PER ATTACHED DRAWINGS.
(GOLDEN SUN IR # M-9)
10.04.14 19.04.14 A
INSPECTION REQUEST LOG
MEP WORKS
AD7176 - G+1 x 2 NOS. VILLAS AT UMM AL SHEIF
A Dutco Balfour Beatty Company WI PM 015/Jan. 2012
AD7176/MEP/IR-014
INSPECTION OF MOCK UP INSTALLATION OF ACOUSTIC
INSULATION FOR DRAINAGE PIPES BETWEEN THE GRID NOS. B/7-
12 AND E/7-12 AS PER ATTACHED DRAWINGS.
(GOLDEN SUN IR # M-10)
12.04.14 19.04.14 A