You are on page 1of 32

The Employer The Construction Manager

D . A . ABCEDE
& ASSOCIATES

REQUEST FOR
No. FOOTING PLAN ACTUAL
1 GL 5/E 125 130
2 GL 1-2/C 123.2 125
3 GL 1-2/D 123.2 125
4 GL 3/A 39 43
5 GL 3/B 57.024 60
6 GL 2/B 73.6 77
7 GL 4/A 39 43
8 GL 5/A 39 41
9 GL 5/B 118.44 135.5
10 GL 4/B 118.44 156
11 GL 3/C 105.8 121
12 GL 3/D 112.8 137.5
13 GL 2/E 112.8125 136
14 GL 6/A 39
15 GL 6/B 118.44 154
16 GL 4/C 157.464 213
17 GL 5/C 157.46 180
18 GL 4/D 125 136
GL 5/D 125 143
GL 3/E 112.8125 118
GL 4/E 125 125
GL 3/F 74.52 87
GL 4/F 125 138.5
GL 3/G' 16.2 21
GL 4/G 97.2 105
GL 5/F 125 139.5
GL 4/H 64.69 73
GL 5/D 125 143

as of Oct. 23, 2023


No. RW Footing PLAN ACTUAL
1 GL 2/C-D 17.2 20
2 GL 2-3/A-B 25.2 25.5
3 GL 2/A-C 18.375 19
4 GL 1-3/A-C 36.29 66
5 GL 3-4/A 13.125 23
6 GL 4-5/A 13.125 21
7 GL 3-4/A-C 33.25 33
8 GL 5-6/A 13.125 23
9 GL 2/D-E 10.9375 19
10 GL 4-5/B-C 7.88
24
11 GL 5-6/B-C 7.88
12 GL 2-3/E-G 56.163 61
as of Oct. 23, 2023

No. RW 1st Lift PLAN ACTUAL


1 GL 2/C-D 16.64 20
2 GL 2-3/A-C 34.1145 40
3 GL 2-3/D-L/4 15.936
as of Oct. 23, 2023

No. RW 2nd Lift PLAN ACTUAL


1 GL 2/C-D 25.3 26
2 GL 2-3/A-C 34.1145 40
3 GL 2/D-E 15.936 18
4 GL 2-3/D-E 15.09
5 GL 2/C-D 20.03 21

as of Oct. 23, 2023

No. COLUMN 1ST LIFT PLAN ACTUAL


1 GL 5/E 1.57 1.57
2 GL C/1 & D/1 4.523 8
3 GL 2/C-D 4.84 4.84
4 GL 3/B 2.42 3
5 GL 2/B, 3/C, 3/D 8.22 10
6 GL 2/E 2.714 3
7 GL 4/C 2.9 3
8 GL 4/D 2.98 3
9 GL 3/B 2.78 3
10 GL 5/C 2.4 3
11 GL 3/E 2.904 3
12 GL 4/E 2.904 3
13 GL 3/G' 1.88 3
14 GL 4/F 2.714 3
15 GL 3/G 1.88 3
16 GL 3/F & 3/F' 4.6 6
17 GL 5/D 2.5 3
as of Oct. 23, 2023

No. COLUMN 2ND LIFT PLAN ACTUAL


1 GL 2/C & 2/D 5.56 5.6
2 GL 3/D 2.783 3
3 GL 3/C 2.78 3
4 GL 4/C 2.662 3
5 GL 2/E 2.488 3
as of Oct. 23, 2023

No. PRESSURE SLAB PLAN ACTUAL


1 GL 2-3/A-C 87.275 92
2 GL 3-6/A-B 238.05 252
as of Oct. 23, 2023
TOTAL VOL 3259.5435
uction Manager The General Contractor

D . A . ABCEDE DAHN BERGER PHILS. CONST. CORP.


& ASSOCIATES

QUEST FOR INFORMATION REGISTER


VARIANCE
5
1.8
1.8
4
2.976
3.40000000000001
4
2
17.06
37.56
15.2
24.7
23.1875

35.56
55.536
22.54
11
18
5.1875
0
12.48
13.5
4.8
7.8
14.5
8.31
18

369.897
VARIANCE
2.8
0.300000000000001
0.625
29.71
9.875
7.875
-0.25
9.875
8.0625

8.24

4.837
81.9495

VARIANCE
3.36
5.8855

VARIANCE
0.699999999999999
5.8855
2.064
-15.09
0.969999999999999

VARIANCE
0
3.477
0
0.58
1.78
0.286
0.1
0.02
0.22
0.6
0.0960000000000001
0.0960000000000001
1.12
0.286
1.12
1.4
0.5
11.681

VARIANCE
0.04
0.217
0.22
0.338
0.512
1.327

VARIANCE
4.72499999999999
13.95
18.675
SM CITY LAOAG

CONST. CORP.

Brgy. Nangalisan West & Brgy.


ER Nalbo, Laoag City, Ilocos Norte
The Employer

WORK INSPECT
according to

no. date NTP

1 Aug-17-2023
2 Aug-24-2023
3a Aug-25-2023
3b Aug-24-2023
4 Sept-11-2023
5 Sept-11-2023
6 Sept-16-2023
a
b
7a Sept-13-2023
7b Sept-14-2023
8 Sept-15-2023
9 Sept-17-2023
10 Sept-17-2023
11 Sept-19-2023
12a Sept-19-2023
12b Sept-20-2023
13 Sept-21-2023
14 Sept-23-2023
15a Sept-23-2023
15b Sept-27-2023
16 Sept-28-2023
17 Sept-27-2023
18 Sept-29-2023
19 Sept-29-2023
20 Sept-30-2023
21 Sept-30-2023
22 Oct-01-2023
a
b
23 Oct-07-23
a
b
24 Oct-06-23
25 Oct-03-2023
26 Oct-03-2023
27 Oct-11-23
28 Oct-04-23
29 Oct-07-23
30 Oct-07-23
31 Oct-15-23
32 Oct-10-23
33 Oct-10-23
34 Oct-10-23
35 Oct-11-23
36 Oct-11-23
37 Oct-06-23
38 Oct-06-23
39
40 Oct-10-23
41 Oct-11-23
42 Oct-08-23
43 Oct-12-23
44
45 Oct-12-23
46 Oct-12-23
47 Oct-14-23
48 Oct-14-23
49
50
51
a
b
52
53
54 19-Oct-23
55
56
57
58
59
60
61 18-Oct-23
62 19-Oct-23
63 19-Oct-23
64 Oct-13-23
65 18-Oct-23
66 19-Oct-23
66 19-Oct-23
67 19-Oct-23
68 27-Oct-23
69 19-Oct-23
70 20-Oct-23
71 20-Oct-23
72 21-Oct-23
73 19-Oct-23
October 23 to October 29, 2023
74 23-Oct-23
75
76
77
78 Oct-27-23
79
80
81
82 20-Oct-23
83 26-Oct-23
84
85
86
87
88 10/27/2023
89
90
91
92
93
94
95 10/30/2023
96 10/30/2023
97
98
99 10/30/2023
100
97
98
99 10/27/2023
100
101 10/30/2023
102
103 10/30/2023
104
105
106
107
108
109
110
111
112 10/28/2023
113
114
115
116
117
118
119
120
121
122
123
124
125
126
127
128
129
130
131
132
133
134
135
136
137
138
139
140
141
142
143
144
145
146
147
148
149
150
151
152
153
154
155
156
157
158
159
160
161
162
163
164
165
166
167
168
169
170
171
172
173
174
175
176
177
178
179
180
181
182
183
184
185
186
187
188
189
190
191
192
193
194
195
196
The Construction Manager

D . A . ABCEDE
& ASSOCIATES

WORK INSPECTION REPORT


according to WIR
cu.m as per plan
discipline
A
Footing @ GL 5/E, F19;C7 125
Column @ GL 5/E 1st lift 1.57
Footing @ GL 1-2/C-D and Retaining wall 123.2
Footing @ GL 1-2/C-D and Retaining wall 123.2
Column @ GL C/1 & D/1, C2 1st lift 4.523
Retaining wall footing @ GL 2/C-D 17.2
Column @ GL 2/C-D, C4A, 1st lift & Retaining wall @ GL 2/C-D
column 4.84
retaining wall 16.64
Footing @ GL 3/A and Retaining Wall (Footing) 39
Footing @ GL 3/B and Retaining Wall (Footing) 57.024
Retaining wall footing @ Gl 2-3/A-B 25.2
Footing @ GL 2/B 73.6
Retaining wall footing @ GL 2/A-C 18.375
Column @ GL 3/B 1st lift 2.42
Column Footing @ GL 4/A & GL 5/A 39
Column Footing @ GL 4/A & GL 5/A 39
Retaining wall footing @ GL 1-3/A-C 36.29
Column Footing @ GL 5/B 118.44
Retaining wall footing @ GL 3-4/A 13.125
Retaining wall footing @ GL 4-5/A 13.125
Column Footing @ GL 4/B 118.44
Footing @ Gl 3/C 105.8
Pressure Slab @ GL 2-3/A-C 87.275
Footing @ GL 3/D 112.8
Retaining wall footing @ GL 3-4/A-C 33.25
Footing @ GL 2/E 112.8125
Footing @ GL 6/A & Retaining wall footing @ GL 5-6/A
footing 39
retaining wall footing 13.125
Retaining wall 1st lift @ GL 2-3/A-C
1st NTP 34.1145
2nd NTP
Column footing @ GL 6/B 118.44
Column 1st lift @ GL 2/B, 3/C & 3/D 8.66
Retaining wall footing @ GL 2/D-E 10.9375
Retaining wall 1st lift @ GL 2-3/D-(L/4) 15.936
Column footing @ GL 4/C 157.464
Column footing @ GL 5/C 157.46
Footing @ GL 4/D 125
Footing @ GL 5/D 125
Footing @ GL 3/E 112.8125
Retaining Wall 2nd lift @ GL 2/C-D 25.3
Column 2nd lift @ GL 2/C and 2/D 5.56
Column 1st lift @ GL 2/E 2.714
Footing @ GL 4/E 125
Retaining wall footing @ GL 4-5/B-C 7.88
Retaining wall footing @ GL 5-6/B-C 7.88

Retaining wall 2nd lift @ GL 2/C-D 20.3


Column 2nd lift @ GL 3/D 2.783
Column 1st lift @ GL 4/C 2.9
Column 1st lift @ GL 4/D 2.98
Column 2nd lift @ GL 3/C 2.78
Footing @ GL 3/F 74.52
Footing @ GL 4/F 125
Footing @ GL 3/G' 16.2
Footing @ GL 4/G 97.2
Retaining wall 2nd lift GL 2-3/A-C 35.488

Column 1st lift 1/C and 1/D


1C 2.6
1/D 2.6
Column 1st lift 2/B & 3/B 5.38292
Fire Tank RW 1st lift @ GL 2-3/B-C 12.714
Column 1st lift @ GL 5/C 2.4

Column 2nd lift GL 4/C 2.662

Retaining Wall 2nd lift GL 2/D-E 17.346


column 2nd lift @ GL 2/E 2.488
column 1st lift @ GL 3/E 2.904
Column 1st lift GL 4/E 2.904
Pressure Slab @ GL 3-6/A-B 238.05
Column 1st lift @ GL 3'/G 1.88
Column 1st lift @ GL 4/F 2.714
Retaining wall 2nd lift @ GL 2-3/D-E 15.09
Column 1st lift GL 4/G 2.714
Column 1st lift @ GL 3/F and 3/F' 4.6
Column 1st lift @ GL 5/D 2.5
Footing @ GL 4/H 64.69
Footing @ GL 5/F 125
Retaining wall footing @ GL 2-3/E-G 56.163
October 23 to October 29, 2023
Column 2nd lift @ GL 4/D 2.783

Footing @ GL 5/I 26.4

Column 2nd lift @ GL 4/E 2.783


Fire Tank RW 1st lift @ GL 2-3/A-B 14.87

Column 1st lift 4/H 2.9524

Column 1st lift 4/A 2.904


Column 1st lift 5/A 2.4

RW 1st lift @ GL 2-5/A 26.04

Footing @ GL 15/A 50.4

Column 1st lift GL 3/A 2.904

RW 1st lift @ GL 5-6/A 10.95

RW and Column 3rd lift @ GL 2/C-D 17.67


uction Manager The General Contractor

D . A . ABCEDE DAHN BERGER PHILS. CONST. CORP.


& ASSOCIATES

ON REPORT
actual vol Volume
Percentage Remarks
B A-B
130 5
3 1.43
143 19.8
125 1.8
8 3.477
20 2.8

21 21

43 43 9
60 60
25.5 25.5
77 77
19 19
3 3
41 41 20
43 43
66 66
135.5 135.5
23 23
21 21
156 156
121 121
92 92
137.5 137.5
33 33
136 136
52.125 52.125

80 80

40 40

154 154
9 9
19 19
18.5 18.5
213 213
180 180
136 136
143 143
118 118
26 26
5.6 5.6
3 3
125 125

24 24

21 21
3 3
3 3
3 3
3 3
87 87
138.5 138.5
21
105
37.5
3
3
6
14
3

18 18
3
3
3
252 252
3
3

3
6
3
73
139.5
61

31

3
17

incl. WIR 99, 105, 107/


51 cu.m

62
CONST. CORP.