1. REFER TO GENERAL NOTES DRAWING.
2. THIS DRAWING IS TO BE READ IN CONJUNCTION WITH ALL
OTHER ENGINEERING DRAWINGS SUCH AS ARCHITECTURAL
STRUCTURAL, PLUMPING, ELECTRO-MECHANICAL,---- etc.
3. ALL DIMENSIONS ARE IN MILLIMETERS AND ALL LEVELS ARE IN
METERS U.N.O.
4. THE 28 DAY CYLINDER COMPRESSIVE DESIGN STRENGTH
350 4000 300 4000 350 SHALL NOT BE LESS THAN:
1-BLINDING
11mpa
2-REINFORCEMENT CONCRETE 30mpa
300 300 3-SCREEED 30mpa
5. THE CLEAR CONCRETE COVER TO REINFORCEMENT SHALL BE AS
FOLLOWS:
FOUNDATIONS ........................................................................70mm
SUB-STRUCTURE ELEMENTS IN CONTACT WITH SOIL ..........50mm
COLUMN ..............................................................................50mm
WALLS AND BEAMS ...............................................................40mm
SOLID SLABS .........................................................................30mm
6. ALL REINFORCING BARS SHALL BE DEFORMED NEW BILLET
STEEL CONFORMING TO ASTM DESIGNATION A615M/A615
GRADE 420 (60).
7. IN CASE OF ANY DISCREPANCY BETWEEN STRUCTURAL
DRAWINGS AND ANY OTHER DISCIPLINE, SITE ENGINEER MUST
REFER BACK TO SHOP DRAWING DEPARTMENT TO CHECK
AND FINALIZE WITH CONSULTING ENGINEER
8. FOR LOCATION AND LEVELS OF OPENING AND SLEEVES IN ALL
MEMBERS REFER TO GENERAL ARRANGEMENT DRAWINGS IN
CONJUNCTION WITH ALL OTHER ENGINEERING DRAWINGS
1000
9. THE CEMENT FOR CONCRETE SHALL BE ORDINARY PORTLAND
CEMENT TO B.S.12 OR AASHTO M&S TYPE-I
10 T20-01-200-B1/T1
LAYER
Y2501 Y1203 SPACING
BAR MARK
DIA. OF BAR
NO. OF BARS
400
650
Y2501
TOP SLAB DETAILS SECTION A - A)
Scale 1: 30
4800 30000 4800
REVISION
ISSUED FOR CONSULTANT APPROVAL 23-07-2021
2x34 Y12 04-250 T. & B.
04
2x34 Y12 03-250 T.& B.
03 ISSUED FOR CONSULTANT APPROVAL 08-02-2021
34 Y12 03-250 T.& B.
02 ISSUED FOR CONSULTANT APPROVAL 11-02-2021
01 ISSUED FOR CONSULTANT APPROVAL 01-02-2021
00 ISSUED FOR CONSULTANT APPROVAL 20-12-20
NO. REVISION DESCRIPTION ACTION DATE BY
CODE
DESIGN DRAWING REFERENCES
300 NO. DWG. No. DRAWING TITLE REV. DATE
01 N17036-0100D-TD-RO1-BR-0001 GENERAL NOTES 1 17-4-2018
300 02 N17036-0100D-TD-RO1-BR-2001 BOX CULVERTS G.A. 1 17-4-2018
DETAILS
03 N17036-0100D-TD-RO1-BR-2002 BOX CULVERTS R.C. 1 17-4-2018
B
DETAILS
750
750
LETTERS & RFI'S REFERENCES
400 400 NO. DOC. No. DOCUMENT DESCRIPTION DATE
01
(17)
(17)
(17)
02
03
KEY PLAN
2x197 Y25 01-150 T. & B.
(17)
(17)
(17)
PROJECT:
CONSTRUCTION OF FIRST POOL OF LONNG TERM
INV.FOR FLOOD CONTROL IN IBADAN, OYO STATE.
CLIENT:
400 400
CONSULTANT:
750
750
Dar Al - Handasah Consultant
B Shair & Partners
GENERAL CONTRACTOR:
TOP SLAB OF CULVERT
INLET & OUTLET OF BOX CULVERT ZONE NAME:
Scale 1:125 DRAWING TITLE:
DRAWN BY: T. OSHO DATE: 23-7-2021
CHECKED BY: L.LAWAL
SCALE: 1:70
REVIEWED BY: M.DENG
APPROVED BY: SHEET SIZE: A3
DRAWING & TRANSMITTAL No.
SHD-CGGC-01-A01-0042-BR-19-2002-0002-01