Project Name
CONSTRUCTION METHODOLOGY
CONTENTS
1. PROJECT INFORMATION
2. CONSTRUCTION METHODOLOGY
3. MAJOR MILESTONES
4. GENERAL POINTS: PROGRAMME OF WORKS
5. CRITICAL PATH
6. PROGRAMME OF WORKS
1.0 PROJECT INFORMATION
PROJECT NAME
CLIENT
CONSULTANT
MAIN CONTRACTOR
PROJECT DESCRIPTION
PROJECT COMMENCEMENT DATE
COMPLETION DATE
PROJECT DURATION
2.0 CONSTRUCTION METHODOLOGY
CONSTRUCTION METHODOLOGY : STRUCTURAL WORKS
The sequence of commencement of Phase 1Aa & Phase 1Ab buildings are mentioned in the below layout in
numerical order, as per the design programme sequence.
Phase 1B
Phase 1Cb
6 5
SN4
SN3
15 SW1 14 G+5
G+5
G+7 SW2
G+7
Phase 1Aa
Phase 1Ab
SW3
13 G+5 7 4
12 G+7
SW4
SS2
G+7 SS1
RD3 1
G+5
11 G+6
G+7
10 RD2 2 3
Phase 1Ca
8
RD1 SS4 SS3
RD4
G+9 9 RD5 G+7 G+7 G+7
G+7
AL MAMSHA AT MUWEILEH COMMERCIAL AREA, SHARJAH, UAE
CONSTRUCTION METHODOLOGY
3.0 MAJOR MILESTONES
PROGRAM OF WORKS
Phase 1Aa
RD3 – Major Activities Planned Finish Dates
Structural
works Block Work MEP All Finishes
Roof Floor
1-Oct-19 23-Nov-19 5-Sep-20
6th Floor
14-Aug-19 23-Nov-19 6-Aug-20 5-Sep-20
5th Floor
28-Jul-19 5-Nov-19 20-Jul-20 15-Aug-20
4th Floor
External Wall 27-Jun-19 19-Oct-19 2-Jul-20 25-Jul-20
Planned Finish 3rd Floor
29-Mar-20
8-May-19 1-Oct-19 15-Jun-20 4-Jul-20
2nd Floor
28-Apr-19 14-Sep-19 27-May-20 13-Jun-20
1st Floor
28-Mar-19 27-Aug-19 9-May-20 23-May-20
GF
28-Feb-19 10-Dec-19 20-Aug-20 26-Sep-20
Basement
28-Jan-19 28-Dec-19 25-Aug-20 15-Oct-20
AL MAMSHA AT MUWEILEH COMMERCIAL AREA, SHARJAH, UAE
CONSTRUCTION METHODOLOGY
4.0 GENERAL POINTS:
PROGRAMME OF WORKS
AL MAMSHA AT MUWEILEH COMMERCIAL AREA, SHARJAH, UAE
CONSTRUCTION METHODOLOGY
5. GENERAL POINTS - PROGRAMME OF WORKS
Calendars used in the program
Calendar 1 : 7 days / week
Explanation Regarding Activity ID’s
The ID’s are explained through following examples:
• MAT-Sub-10 : MAT : Material submittal or approval
Sub : Substructure
• Fin-MEP-40 : Fin : Finishing
MEP : MEP
As a logic in Primavera, “Retained Logic” has been used.
AL MAMSHA AT MUWEILEH COMMERCIAL AREA, SHARJAH, UAE
CONSTRUCTION METHODOLOGY
5. GENERAL POINTS - PROGRAMME OF WORKS
Critical path of the project contains Structural Approval from Authorities, Sub structure, Super structure, Partition Works ,
Wall Tile , False Ceiling , MEP Testing .
Project progress will be monitored through Actual vs. Planned percentages of Cash flow or work percentage weightage.
Logic of commencement of major activities is as follows:
• Partition work: Partition Work will start directly after slab casting and DE shuttering .
• Wall Tile : Wall Tile Works Will start directly after Wall Partition Casting Completion .
• Paint Works : Paint Works will start directly after Tile work Completion .
AL MAMSHA AT MUWEILEH COMMERCIAL AREA, SHARJAH, UAE
CONSTRUCTION METHODOLOGY
5.0 CRITICAL PATH
AL MAMSHA AT MUWEILEH COMMERCIAL AREA, SHARJAH, UAE
CONSTRUCTION METHODOLOGY
6.0 PROGRAMME OF WORKS