CONSTRUCTION METHODOLOGY
CONTENTS
1. PROJECT INFORMATION
2. CONSTRUCTION METHODOLOGY
3. MAJOR MILESTONES
4. GENERAL POINTS: PROGRAMME OF WORKS
5. CRITICAL PATH
6. PROGRAMME OF WORKS
1.0 PROJECT INFORMATION
PROJECT NAME
CLIENT
CONSULTANT
MAIN CONTRACTOR
PROJECT DESCRIPTION
COMPLETION DATE
PROJECT DURATION
2.0 CONSTRUCTION METHODOLOGY
CONSTRUCTION METHODOLOGY : STRUCTURAL WORKS
The sequence of commencement of Phase 1Aa & Phase 1Ab buildings are mentioned in the below layout in
numerical order, as per the design programme sequence.
Phase 1B
Phase 1Cb
6 5
SN4
SN3
15 SW1 14 G+5
G+5
G+7 SW2
G+7
Phase 1Aa
Phase 1Ab
SW3
13 G+5 7 4
12 G+7
SW4
SS2
G+7 SS1
RD3 1
G+5
11 G+6
G+7
10 RD2 2 3
Phase 1Ca
8
RD1 SS4 SS3
RD4
Critical path of the project contains Structural Approval from Authorities, Sub structure, Super structure, Partition Works ,
Wall Tile , False Ceiling , MEP Testing .
Project progress will be monitored through Actual vs. Planned percentages of Cash flow or work percentage weightage.
• Partition work: Partition Work will start directly after slab casting and DE shuttering .
• Wall Tile : Wall Tile Works Will start directly after Wall Partition Casting Completion .
• Paint Works : Paint Works will start directly after Tile work Completion .
AL MAMSHA AT MUWEILEH COMMERCIAL AREA, SHARJAH, UAE
CONSTRUCTION METHODOLOGY