Professional Documents
Culture Documents
LAB ASSIGNMENT 01
SUBMITTED TO:
SUBMITTED BY:
Group # 07
Name CMS ID
Mirza Abdullah Baig 376173
Arbaz Abbasi 375544
Zaid Bin Akbar 391321
Muhammad Noman 393680
Tayyab Khalid 381520
Work Breakdown Structure
1. Pre - Construction Phase
1.1 Planning and Design
2. Construction Phase
1.4 Construction
1.4.1 Site Supervisors (1)
1.4.1.1 Site Team
1.4.1.1.1 Labor (55-65)
1.4.1.1.2 Technicians (Number unspecified)
1.4.1.1.3 Electricians (Number unspecified)
1.4.1.1.4 Plumbers (Number unspecified)
1.4.2 Safety Inspectors (1-2)
Activity
Required Required Relationship
Code Lead / Lag (if
Activity Labor Equipment Duration (Predecessor/
(from Applicable)
Resources Resources Successor)
WBS)
1.1.1.1 Schematic Design Architects Computers 14 days 1.1.1 0