Construction and Project Management

LAB ASSIGNMENT 01

SUBMITTED TO:

Lec Aman Ul Haq

SUBMITTED BY:
Group # 07

Name CMS ID
Mirza Abdullah Baig 376173
Arbaz Abbasi 375544
Zaid Bin Akbar 391321
Muhammad Noman 393680
Tayyab Khalid 381520
Work Breakdown Structure
1. Pre - Construction Phase
1.1 Planning and Design

1.1.1 Architectural Design


1.1.1.1 Conceptualization
1.1.1.2 Schematic Design
1.1.1.3 Design Development
1.1.1.4 Finalization of Plans

1.1.2 Engineering Design


1.1.2.1 Structural Engineering
1.1.2.2 Mechanical, Electrical, Plumbing (MEP)
1.1.2.3 HVAC Systems
1.1.2.4 Fire Safety Systems

1.1.3 Site Analysis and Surveys


1.1.3.1 Topographical Surveys
1.1.3.2 Soil Testing
1.1.3.3 Environmental Impact Assessment

1.2 Regulatory Compliance and Approvals


1.2.1 Building Permits and Zoning
1.2.1.1 Application Submission
1.2.1.2 Reviews and Revisions
1.2.1.3 Final Approval
1.2.2 Environmental Clearances
1.2.2.1 Environmental Impact Studies
1.2.2.2 Compliance Recommendations
1.2.2.3 Clearance Acquisition
1.2.3 Legal and Contractual Compliance
1.2.3.1 Contract Drafting and Review
1.2.3.2 Negotiations
1.2.3.3 Signing and Execution
1.3 Resource Procurement
1.3.1 Material Acquisition
1.3.1.1 Material Specifications
1.3.1.2 Supplier Selection
1.3.1.3 Procurement
1.3.2 Equipment and Machinery Procurement
1.3.2.1 Equipment Requirements Identification
1.3.2.2 Vendor Assessment and Selection
1.3.2.3 Procurement and Delivery
1.3.3 Manpower Hiring and Training
1.3.3.1 Recruitment Planning
1.3.3.2 Training Programs
1.3.3.3 Skill Assessment

2. Construction Phase

2.1 Site Preparation

2.1.1 Clearing and Demolition


2.1.1.1 Site Assessment and Marking
2.1.1.2 Demolition Planning and Permits
2.1.1.3 Structure Demolition
2.1.1.4 Waste Management and Disposal
2.1.2 Excavation and Grading
2.1.2.1 Excavation Planning and Safety
2.1.2.2 Soil Removal and Management
2.1.2.3 Grading and Compaction
2.1.2.4 Trenching for Utilities

2.2 Foundation and Structural Development

2.2.1 Foundation Construction


2.2.1.1 Foundation Design Review
2.2.1.2 Footing Installation
2.2.1.3 Basement Construction
2.2.1.4 Reinforcement and Waterproofing
2.2.2 Framework Erection
2.2.2.1 Structural Steel Fabrication
2.2.2.2 Frame Assembly and Erection
2.2.2.3 Installation of Beams and Columns
2.2.2.4 Roofing and Structural Integrity Checks
2.3 Building Construction

2.3.1 Exterior Construction and Finishing


2.3.1.1 Exterior Wall Construction
2.3.1.2 Window and Door Installation
2.3.1.3 Facade Finishing (Cladding, Painting)
2.3.1.4 Roof Installation and Waterproofing

2.3.2 Systems Installation (MEP)


2.3.2.1 HVAC System Installation
2.3.2.2 Plumbing and Electrical Setup
2.3.2.3 Fire Safety System Integration
2.3.2.4 Testing and Commissioning

2.3.3 Landscaping and Outdoor Amenities


2.3.3.1 Garden and Greenery Setup
2.3.3.2 Pathways and Outdoor Structures
2.3.3.3 Outdoor Furniture Installation
2.3.3.4 Lighting and Feature Installation

2.4 Interior Finishing

2.4.1 Interior Design Implementation


2.4.1.1 Room Layout and Design
2.4.1.2 Material Selection and Procurement
2.4.1.3 Fixture and Fittings Installation
2.4.1.4 Wall Covering and Flooring

2.4.2 Furniture and Fixtures Installation


2.4.2.1 Furniture Procurement and Assembly
2.4.2.2 Placement and Arrangement
2.4.2.3 Artwork and Decoration
2.4.2.4 Final Touches and Quality Checks

3. Post - Construction Phase

3.1 Quality Assurance and Inspections


3.1.1 Quality Checks and Audits
3.1.1.1 Compliance Assessments
3.1.1.2 Structural Integrity Inspections
3.1.1.3 Material Quality Checks
3.1.1.4 System Functionality Testing

3.1.2 Safety Inspections


3.1.2.1 Site Safety Audits
3.1.2.2 Hazard Identification and Mitigation
3.1.2.3 Safety Equipment Assessment
3.1.2.4 Emergency Preparedness Checks
3.2 Finalization and Handover

3.2.1 Finishing Touches and Snagging


3.2.1.1 Defect Identification and Rectification
3.2.1.2 Finishing Corrections
3.2.1.3 Snagging List Compilation
3.2.1.4 Final Inspection and Sign-offs

3.2.2 Client Handover and Acceptance


3.2.2.1 Client Walkthroughs and Orientations
3.2.2.2 Handover Documentation Preparation
3.2.2.3 Key Transfer and Facility Access
3.2.2.4 Acceptance Sign-off and Feedback Collection

3.3 Project Closure and Reporting

3.3.1 Documentation and Reporting


3.3.1.1 Final Project Documentation Compilation
3.3.1.2 As-Built Drawings and Manuals
3.3.1.3 Incident Reports and Issue Logs
3.3.1.4 Lessons Learned Documentation

3.3.2 Financial Closure and Audit


3.3.2.1 Financial Reports and Audits
3.3.2.2 Budget Variance Analysis
3.3.2.3 Final Payments and Settlements
3.3.2.4 Contract Closure and Vendor Settlements
Organizational Breakdown Structure

1.1 Project Leadership


1.1.1 Project Manager (1)

1.2 Design and Planning


1.2.1 Architects/Designers (2)
1.2.1.1 Architectural Design Team
1.2.1.1.1 Interns/Diploma Holders (Included in the team of Architects/Designers)
1.2.2 Civil Engineers (3)
1.2.2.1 Civil Engineering Team
1.2.2.1.1 Assistant Civil Engineer (Included in the team of Civil Engineers)

1.3 Survey and Site Preparation


1.3.1 Surveyors (3)
1.3.1.1 Survey Team
1.3.1.1.1 Diploma Holders (Included in the team of Surveyors)

1.4 Construction
1.4.1 Site Supervisors (1)
1.4.1.1 Site Team
1.4.1.1.1 Labor (55-65)
1.4.1.1.2 Technicians (Number unspecified)
1.4.1.1.3 Electricians (Number unspecified)
1.4.1.1.4 Plumbers (Number unspecified)
1.4.2 Safety Inspectors (1-2)
Activity
Required Required Relationship
Code Lead / Lag (if
Activity Labor Equipment Duration (Predecessor/
(from Applicable)
Resources Resources Successor)
WBS)
1.1.1.1 Schematic Design Architects Computers 14 days 1.1.1 0

1.1.1.2 Design Architects Computers 21 days 1.1.1.1 0


Development

1.1.1.3 Finalization of Architects Computers 7 days 1.1.1.2 0


Plans
1.1.2.1 Structural Structural Computers 7 days 1.1.2 0
Engineering Engineers
1.1.2.2 Mechanical, MEP Engineers Computers 7 days 1.1.2 0
Electrical,
Plumbing (MEP)

1.1.2.3 HVAC Systems HVAC Computers 7 days 1.1.2 0


Engineers
1.1.2.4 Fire Safety Fire Safety Computers 7 days 1.1.2 0
Systems Engineers
1.1.3.1 Topographical Surveyors Surveying 5 days 1.1.3 0
Surveys Equipment
1.1.3.2 Soil Testing Soil Engineers Drilling 9 days 1.1.3.1 5 days lag
Equipment,
Testing
Equipment
1.1.3.3 Environmental Environmental Computers 3 days 1.1.3.2 0
Impact Scientists
Assessment
1.2.1.1 Application Permit Computers 2 days 1.2.1 0
Submission Specialists
1.2.1.2 Reviews and Permit Computers 2 days 1.2.1.1 0
Revisions Specialists
1.2.1.3 Final Approval Permit Computers 3 days 1.2.1.2 7 days lag
Specialists
1.2.2.1 Environmental Environmental Computers, 3 days 1.2.2 0
Impact Studies Scientists Environmental
Monitoring
Equipment
1.2.2.2 Compliance Environmental Computers 5 days 1.2.2.1 0
Recommendations Specialists

1.2.2.3 Clearance Environmental Computers 3 days 1.2.2.2 0


Acquisition Specialists
1.2.3.1 Contract Drafting Lawyers Computers 5 days 1.2.3 0
and Review
1.2.3.2 Negotiations Lawyers Computers 7 days 1.2.3.1 0
1.2.3.3 Signing and Lawyers Computers 7 days 1.2.3.2 0
Execution
1.3.1.1 Material Procurement Computers 4 days 1.3.1 0
Specifications Specialists
1.3.1.2 Supplier Selection Procurement Computers 3 days 1.3.1.1 0
Specialists
1.3.1.3 Procurement Procurement Computers 6 days 1.3.1.2 4 days lag
Specialists
1.3.2.1 Equipment Procurement Computers 5 days 1.3.2 0
Requirements Specialists
Identification
1.3.2.2 Vendor Procurement Computers 3 days 1.3.2.1 0
Assessment and Specialists
Selection
1.3.2.3 Procurement and Procurement Computers 7 days 1.3.2.2 0
Delivery Specialists
1.3.3.1 Recruitment HR Specialists Computers 3 days 1.3.3 0
Planning
1.3.3.2 Training HR Specialists, Computers, 4 days 1.3.3.1 0
Programs Trainers Training
Equipment
1.3.3.3 Skill Assessment HR Specialists, Computers, 3 days 1.3.3.2 0
Trainers Assessment
Tools
2.1.1.1 Site Assessment Site Engineers Surveying 9 days 2.1.1 0
and Marking Equipment,
Marking Tools
2.1.1.2 Demolition Site Engineers, Computers, 5 days 2.1.1.1 5 days lag
Planning and Demolition Permits
Permits Contractors
2.1.1.3 Structure Demolition Excavators, 14 days 2.1.1.2 7 days lag
Demolition Crew Bulldozers,
Cranes
2.1.1.4 Waste Waste Trucks, 7 days 2.1.1.3 0
Management and Management Dumpsters
Disposal Specialists
2.1.2.1 Excavation Site Engineers Surveying 5 days 2.1.2 3 days lag
Planning and Tools, Safety
Safety Equipment
2.1.2.2 Soil Removal and Excavators, Dumpsters 7 days 2.1.2.1 2 days lag
Management Trucks
2.1.2.3 Grading and Graders, Surveying 5 days 2.1.2.2 0
Compaction Rollers Tools
2.1.2.4 Trenching for Excavators, Surveying 6 days 2.1.2.3 0
Utilities Surveying Tools
Tools
2.2.1.1 Foundation Structural Computers 3 days 2.2.1 0
Design Review Engineers
2.2.1.2 Footing Concrete Crew, Excavators, 12 days 2.2.1.1 0
Installation Excavators, Concrete
Formworkers Mixers, Cranes
2.2.1.3 Basement Concrete Crew, Excavators, 18 days 2.2.1.2 4 days lag
Construction Formworkers, Concrete
Waterproofing Mixers, Cranes,
Specialists Waterproofing
Materials
2.2.1.4 Reinforcement Reinforcements Cranes, 25 days 2.2.1.3 0
and Workers, Reinforcing
Waterproofing Waterproofing Materials,
Specialists Waterproofing
Materials
2.2.2.1 Structural Steel Steel Welding 7 days 2.2.2 0
Fabrication Fabricators Equipment,
Cranes
2.2.2.2 Frame Assembly Steelworkers, Cranes, Steel 10 days 2.2.2.1 0
and Erection Crane Beams and
Operators Columns
2.2.2.3 Installation of Steelworkers, Cranes, Steel 7 days 2.2.2.2 5 days lag
Beams and Crane Beams and
Columns Operators Columns
2.2.2.4 Roofing and Roofers, Cranes, 3 days 2.2.2.3 0
Structural Structural Roofing
Integrity Checks Engineers Materials,
Inspection
Tools
2.3.1.1 Exterior Wall Masons Cranes, 5 days 2.3.1 0
Construction Scaffolding,
Masonry
Materials
2.3.1.2 Window and Door Carpenters Cranes, 3 days 2.3.1 0
Installation Scaffolding,
Carpentry
Tools
2.3.1.3 Facade Finishing Masons, Cranes, 7 days 2.3.1 0
(Cladding, Painters Scaffolding,
Painting) Masonry
Materials,
Painting
Equipment
2.3.1.4 Roof Installation Roofers, Cranes, 14 days 2.3.1 8 days lag
and Waterproofing Roofing
Waterproofing Specialists Materials,
Waterproofing
Materials
2.3.2.1 HVAC System HVAC Cranes, 9 days 2.3.2 0
Installation Technicians Scaffolding,
HVAC
Equipment
2.3.2.2 Plumbing and Plumbers, Cranes, 7 days 2.3.2 0
Electrical Setup Electricians Scaffolding,
Plumbing
Fixtures,
Electrical
Wires and
Cables
2.3.2.3 Fire Safety Fire Safety Cranes, 7 days 2.3.2 0
System Technicians Scaffolding,
Integration Fire Safety
Equipment
2.3.2.4 Testing and HVAC Testing 3 days 2.3.2.1, 0
Commissioning Technicians, Equipment 2.3.2.2,
Plumbers, 2.3.2.3
Electricians
2.3.3.1 Garden and Gardeners Gardening 6 days 2.3.3 0
Greenery Setup Tools
2.3.3.2 Pathways and Landscapers Excavators, 7 days 2.3.3 0
Outdoor Bulldozers
Structures
2.3.3.3 Outdoor Furniture Landscapers Gardening 3 days 2.3.3.1, 0
Installation Tools 2.3.3.2

2.3.3.4 Lighting and Electricians Electrical 4 days 2.3.3.1, 0


Feature Wires and 2.3.3.2
Installation Cables,
Lighting
Fixtures
2.4.1.1 Room Layout and Interior Computers, 10 days 2.4.1 0
Design Designers Drafting and
Design Tools
2.4.1.2 Material Selection Interior Computers 3 days 2.4.1.1 0
and Procurement Designers

2.4.1.3 Fixture and Carpenters, Cranes, 10 days 2.4.1.2 0


Fittings Electricians Scaffolding,
Installation Carpentry
Tools,
Electrical
Wires and
Cables
2.4.1.4 Wall Covering Carpenters, Cranes, 14 days 2.4.1.3 0
and Flooring Painters Scaffolding,
Carpentry
Tools, Painting
Equipment
2.4.2.1 Furniture Furniture Computers 3 days 2.4.2 0
Procurement and Installers
Assembly
2.4.2.2 Placement and Interior Computers 3 days 2.4.2.1 0
Arrangement Designers
2.4.2.3 Artwork and Interior Computers 7 days 2.4.2.2 0
Decoration Designers
2.4.2.4 Final Touches and Interior Computers 2 days 2.4.2.3 0
Quality Checks Designers

3.1.1.1 Compliance Auditors Computers 7 days 3.1.1 0


Assessments
3.1.1.2 Structural Structural Computers 3 days 3.1.1 0
Integrity Engineers,
Inspections Inspection
Tools
3.1.1.3 Material Quality Quality Inspection 7 days 3.1.1 0
Checks Inspectors Tools
3.1.1.4 System Engineers, Testing 7 days 3.1.1 0
Functionality Technicians Equipment
Testing
3.1.2.1 Site Safety Audits Safety Computers, 3 days 3.1.2 0
Inspectors Inspection
Tools
3.1.2.2 Hazard Safety Computers, 3 days 3.1.2.1 0
Identification and Inspectors, Inspection
Mitigation Engineers Tools
3.1.2.3 Safety Equipment Safety Inspection 10 days 3.1.2.2 0
Assessment Inspectors Tools

3.1.2.4 Emergency Safety Computers, 7 days 3.1.2.3 0


Preparedness Inspectors Emergency
Checks Response
Equipment
3.2.1.1 Defect Site Computers, 7 days 3.2.1 0
Identification and Supervisors, Inspection
Rectification Tools
Quality
Inspectors

3.2.1.2 Finishing Carpenters, Cranes, 3 days 3.2.1.1 0


Corrections Electricians, Scaffolding,
Painters Carpentry
Tools,
Electrical
Wires and
Cables,
Painting
Equipment
3.2.1.3 Snagging List Quality Computers 2 days 3.2.1.2 0
Compilation Inspectors
3.2.1.4 Final Inspection Project Computers, 5 days 3.2.1.3 0
and Sign-offs Managers, Inspection
Quality Tools
Inspectors
3.2.2.1 Client Project Computers, 3 days 3.2.2 0
Walkthroughs and Managers, Presentation
Orientations Client Equipment
Representatives
3.2.2.2 Handover Project Computers 7 days 3.2.2.1 0
Documentation Managers
Preparation
3.2.2.3 Key Transfer and Project Security Access 10 days 3.2.2.2 0
Facility Access Managers, Cards, Facility
Security Keys
Personnel
3.2.2.4 Acceptance Sign- Project Computers 2 days 3.2.2.3 0
off and Feedback Managers,
Collection Client
Representatives
3.3.1.1 Final Project Project Computers 3 days 3.3.1 0
Documentation Managers,
Compilation Technical
Writers
3.3.1.2 As-Built Engineers, Computers, 7 days 3.3.1.1 0
Drawings and Technical Drafting and
Manuals Writers Design Tools
3.3.1.3 Incident Reports Quality Computers 2 days 3.3.1.2 0
and Issue Logs Inspectors,
Project
Managers
3.3.1.4 Lessons Learned Project Computers 1 day 3.3.1.3 0
Documentation Managers,
Engineers,
Technical
Writers
3.3.2.1 Financial Reports Accountants, Computers, 14 days 3.3.2 0
and Audits Auditors Financial
Documentation
3.3.2.2 Budget Variance Finance Computers, 7 days 3.3.2.1 0
Analysis Managers, Financial
Project Documentation
Managers
3.3.2.3 Final Payments Finance Computers, 10 days 3.3.2.2 22 days lag
and Settlements Managers, Financial
Procurement Documentation,
Specialists Payment
Processing
Tools
3.3.2.4 Contract Closure Project Computers, 3 days 3.3.2.3 0
and Vendor Managers, Contract
Settlements Legal Counsel Documentation,
Payment
Processing
Tools

Table 1: Details for Schedule and Resources


Resources Working Number Maximum Productivity(m^3/hr)
hours hours
Carpentry 40 sets
Tool
Electrical 28 sets
Tools
Plumbing 25 sets
Measuring 32
tape
Soil Testing 8 sets
Equipment
Surveying 6 sets
Equipment
Trucks 5 4 20 150(m^3/hr)
Excavators 5 2 10 28(m^3/hr)
Mobile 6 1 6 56(m^3/hr)
Concrete
Power
Boom Lifts 4 2 8 70(m^3/hr)
Tower 6 1 6 120(m^3/hr)
Cranes
Civil 8 3 24
Engineers
Architects 8 2 16
Project 8 1 8
Manager
Surveyors 8 3 24
Diploma 8 3 24
Holder
(surveyor)
Site 8 3 24
Supervisors
Labors 8 65 520
Safely 8 2 16
Inspectors
Electricians 8 3 24
Plumber 8 4 32
Technicians 8 8 64

Table 2: Equipment, machinery, and labor