Site Organization and Work Methodology

1.1. Site layout

This is a plan of site and area around it shows the exact location placing the resources of construction.
The job layout for a project depends upon various factors such as:

Nature of the project

Location of the project

Safety measure

Availability of materials and equipment

Soil conditions

1.2. Storing and stacking materials on site Material on site should be stored so as to prevent

Deterioration or mixing with each other. Following are of prime importance while storing materials
should be protected from atmospheric agencies- rain, sun, etc. Construction materials should be stored
by adopting suitable measures against risks Materials susceptible to fine should be stored so as to
prevent fire hazards Materials easily affected by moisture should stake on the platform with
waterproofing

1.3. Preparation of actual job layout

Job layout is the first duty of the site engineer before the execution of work. A careful site layout
/planning ensures: Effective and efficient methods of works Safety to workman and visitors Avoid
wastage and deteriorat9ion of materials

1.4. No interference or disturbance to adjacent facilities

The job layout in the site organization should consider the area available for:

Warehouses Offices Storage of materials Equipment Formwork Bar bending space Toilets Entry and exit
Method Statement .We consider policies and procedures related to:

Quality Assurance Management Planning Safety& health Controlling & monitoring

Construction method statement Proposed Workflow and Services

Prepare construction plan by determining:

Type and quantity of materials required for the construction Quantity and duration of operation Labor
required for the work,(skilled and unskilled )

Money required at different stages of the project Total time to complete the project
Prepare construction scheduling of: Construction schedule Material schedule Labor schedule Equipment
schedule Financial schedule Resource mobilization delivery

2. CONSTRACTION METHODOLOGY

Construction methodology or project execution methodology refers to the planned method of


construction, taking into account all contractual and legal requirements,

Construction constraints, risks, and opportunities. Project Methodology includes the temporary and
permanent works and the services required to complete the construction works. Given a detailed
methodology for construction of a civil project, which can be used for planning a good project and to
show the clients and consultants that a civil main

Contracting company is able to manage a project. This approach can be customized as per site
requirements and can help planning & operation departments to prepare professional construction
methodology.

3. IMPLEMENTATION STRATEGY PLANS & PROCEDURAL APPROACH

This project implementation strategy also called construction methodology provides general information
of the methods procedures and sequencing to be used for the project. Where specific areas of work are
of a difficult nature, safety concern or there is a specific requirement a detailed method statement will
be prepared in the future In developing the planning the site location should be considered nod it will be
necessary to mobilize and establish at the site various temporary facilities and equipment prior to
commencing the works. It is also necessary to establish and hare certain staff at the site for the works.
This will be at an agreed location with the client. Initial planning, preparation of shop drawings, detailing
material procurement and arrangement of sub-contractors will be carried out from the head office.

4. PROJECT CONTROL SYSTEM

The planning and documentation requirements listed here are considered adequate control for the
works and no further criteria for the detailed plans or procedures are

Deemed necessary. Upon the award of the contract a detailed project quality

and management plan would be prepared. This will address in detail the requirements of the contract
and specifically the procedures and plans outlined in the various annexure for schedule project control
services.

5. CONSTRUCTION METHODOLOGY PROJECT PLANNING


The construction methodology or execution planning services will be provided in accordance with
contract requirements. The level I works master schedule will be based on the tender scheme program
and will be submitted initially after the contract award.

Following the review and approval of the level I program the more detailed levels of programs will be
prepared.

Project control is required for the following documentation.

a) Shop drawing preparation.

b) Material procurement.

c) Arranging subcontractors.

d) Material delivery

The program dates for these items will be derived from the overall project schedule. Exporting these
items from the primavera database to a spread sheet will be done to implement this. This will allow the
preparation of customizable report showing the status on each of these activities. Initially all of the
planning activities will be carried out in

the company head office using a senior planner. The work carried out on a project will comprise of
monitoring progress, updating the schedule and providing

Short term look ahead programs. Actual progress of the works is continuously monitored and compared
with the schedule. Variances are defined and assessed In case of any delay,

a recovery plan is prepared along With costs and resources impact.


 Summarize professional experience over the last 7 years.

From To Company/project/position/relevant
2009 to 2015 technical and management
experience.

Attach the certificates and cv By own company, sub


contract,&employer
Attach the certificates and cv By own company, sub
contract,&employer
Attach the certificates and cv
Attach the certificates and cv By own company, sub
contract,&employer
Attach the certificates and cv
Attach the certificates and cv
Attach the certificates and cv By own company, sub
contract,&employer

APPLICATION FORM (5B)

CURRICULUM VITAE

KEY CONTRACTOR’S PERSONNEL

Name Abel berhanu

Profession professional engineer in construction technology management.

Years with firm 9/9/2009 NATIONALITY ETHIOPEA

Date of birth 13/8/1984

Proposed position on the project …………………..E.

Key qualifications
CONSTRACT WITH TIME COST QUALITY.

Education

Dire Dawa University since 1/2/2004 to 20/10/2008.

Experience record

7yrs both on our company and others


MISSION STATEMENT

To ensure the delivery of cutting edge construction & consultancy services and products which
enhance the development of quality life of the society. ABEL BERHANU GC realizes these ideals
through:

Strategic Business Plan

Attracting and retaining skilled employees creating and maintaining partnership on the basis of
mutual benefits technical advances Taking care of natural environment

VISSION STATEMENT

To become a strong and leading contractor in the construction industry in Ethiopia to be an


ethical and professional contractor. Engineering service and product provider nationally and
internationally.

QUALITY POLICY

ABEL BERHANU GC is committed to satisfy customers’’ needs and Expectations by providing on


time cost quality service.

The Management and Employees’’ commitment to continual improvement and meeting


customers’’ expectation is the foundation for achieving our quality objectives.

Values

Provision of efficient, effective and fair construction services tailored to the best satisfaction of
our customers Efficient and effective utilization of our resources

Service Giving construction works, like water supply, Irrigation and drainage, Culvert and
bridge, building construction.
CONTENTS

1. SITE ORGANIZATION AND WORKMETHODOLOGY

2 SITELAYOUT

3 STORING&STACKING MATERIAL ON SITE

4. PREPARATION OF ACTUAL JOB LAYOUT

5. NO INTERFERENCE OR DISTURBANE TO ADJECENT FACILITES

6. CONSTRACTION METHODOLOGY

7. IMPLEMENTATION STRATEGY PLANS & PROCEDERAL APPROACH

8. PROJECT CONTROL SYSTEM

9. PROJECT PLANNING

10. COMPANY EQUPMENT & MANPOWER

11. SCHEJULE