Professional Documents
Culture Documents
1 Scope............................................................ 2
2 Conflicts and Deviations................................ 2
3 References.................................................... 2
4 Abbreviation and Definitions......................... 4
5 Liner Design.................................................. 6
6 Liner Installation.......................................... 14
7 Operation..................................................... 20
8 Documentation............................................ 22
1 Scope
This document refers to the minimum technical requirements for the design, installation
and operation of vented grooved or perforated tight fitting, non-bonded, thermoplastic
liners in carbon steel pipelines. This document covers liners for water injection lines,
pipelines for three phase system and crude oil. These liners shall be designed for
rehabilitating existing carbon steel pipelines and flowlines as well as new pipelines and
flowlines. The design is applicable to aboveground, buried and sub-sea pipelines.
This engineering procedure covers the design of grooved, perforated and smooth liners
to avoid liner collapse due to process depressurization.
2.1 Any conflicts between this procedure and other applicable Saudi Aramco
Materials System Specifications (SAMSSs), Engineering Standards (SAESs),
Standard Drawings (SASDs), or industry standards, codes, and forms shall be
resolved in writing by the Company or Buyer Representative through the
Manager, Consulting Services Department of Saudi Aramco, Dhahran.
2.2 Direct all requests to deviate from this procedure in writing to the Company or
Buyer Representative, who shall follow internal company procedure SAEP-302
and forward such requests to the Manager, Consulting Services Department of
Saudi Aramco, Dhahran.
3 References
The following references in force on the date of the Purchase Order form a
supplementary part of this procedure, as applicable:
Page 2 of 23
Document Responsibility: Nonmetallic Standards Committee SAEP-387
Issue Date: 5 December 2012 Design of Thermoplastic Tight Fit Grooved and
Next Planned Update: 5 December 2017 Perforated Liners for New and Existing Pipelines
Page 3 of 23
Document Responsibility: Nonmetallic Standards Committee SAEP-387
Issue Date: 5 December 2012 Design of Thermoplastic Tight Fit Grooved and
Next Planned Update: 5 December 2017 Perforated Liners for New and Existing Pipelines
Page 4 of 23
Document Responsibility: Nonmetallic Standards Committee SAEP-387
Issue Date: 5 December 2012 Design of Thermoplastic Tight Fit Grooved and
Next Planned Update: 5 December 2017 Perforated Liners for New and Existing Pipelines
Contractor: The party that conduct all or part of the project design, engineering,
procurement, construction, commissioning or management of a project.
Principal: The party, in this case; Saudi Aramco, which initiates the project and pays
for its design and construction. The Principal usually specify the technical requirements
directly to the Contractor or through an agent or consultant working or acting on his
behalf.
Annulus: Space between thermoplastic liner and the host outside carbon steel pipe.
Bell hole: Excavations made at a section joints of a pipeline for the purpose of
insertion of a section of thermoplastic liner.
Butt fusion welding: A method of joining plastic pipe, sheet, or other similar forms of
a thermoplastic resin wherein the two ends to be joined are heated to the molten state
and then bringing the two aligned pipe ends together under pressure and a
predetermined cooling time resulting in a fused joint having a hydrostatic strength equal
to the parent pipe.
Flanges Face: ASME B16.5 code requires that the flange face (raised face and flat
face) has a specific roughness to ensure that this surface be compatible with the gasket
and provide a high quality seal.
Hot plate welding Technique: The process of hot plate welding uses a heated platen
to melt the joining surfaces of the two halves of a thermoplastic pipe. The part halves
are brought into contact with a precisely heated platen for a predetermined period.
Modulus Elastic: The ratio of the stress applied on a body to the strain that results in
the body in response to it. The modulus of elasticity of a material is a measure of its
stiffness and for most materials remains constant over a range of stress.
Page 5 of 23
Document Responsibility: Nonmetallic Standards Committee SAEP-387
Issue Date: 5 December 2012 Design of Thermoplastic Tight Fit Grooved and
Next Planned Update: 5 December 2017 Perforated Liners for New and Existing Pipelines
Permeation: Diffusion of liquid and gas through a plastic layer under the influence of
pressure and temperature. Permeation is a physicochemical mass transfer phenomenon
involving diffusion of a solute through a porous medium. The driving force for mass
transfer is the presence of an activity (e.g., concentration) gradient with respect to the
solute.
Vent connection or point: Vent hole in through the carbon steel outer pipe to allow the
release of gas accumulated in the annulus between the liner and the host carbon steel pipe.
Venting: The release of gas accumulated in the annulus between the thermoplastic
liner and the host carbon steel pipeline.
5 Liner Design
The installation Contractor shall be responsible for the design of the liner including the
dimension of the grooves or perforations, spacing between vent points and frequency of
venting, in line with the design and operating conditions of the host steel pipelines.
The Contractor shall pay particular attention to the types of the thermoplastic liner to be
installed in hydrocarbon service where the effects of stress relaxation, swelling, loss of
plasticizer, permeation and absorption of gases and liquids have significant effect on the
performance of the selected liner and consequently its service life.
The calculation for the required wall thickness of the liner is determined from
three conditions, (a) handling and storage, (b) installation and (c) collapse.
The highest thickness calculated from requirements (a), (b) and (c) is taken as
the design wall thickness. For requirement (c) it is assumed that the pressure in
the annulus is the same as the bore pressure.
Page 6 of 23
Document Responsibility: Nonmetallic Standards Committee SAEP-387
Issue Date: 5 December 2012 Design of Thermoplastic Tight Fit Grooved and
Next Planned Update: 5 December 2017 Perforated Liners for New and Existing Pipelines
The Contractor shall provide the Principal the liner design document as in
outlined above as part of the tender documentation.
(Table 5.1) summarizes the design procedure for determining the thickness of a
liner as a function of fluid type and tightness of liner fit.
Page 7 of 23
Document Responsibility: Nonmetallic Standards Committee SAEP-387
Issue Date: 5 December 2012 Design of Thermoplastic Tight Fit Grooved and
Next Planned Update: 5 December 2017 Perforated Liners for New and Existing Pipelines
In general, for water service the minimum thickness shall be 8 mm, excluding
the depth of the groove, to avoid difficulties in installation and fusion bonding.
However, for hydrocarbon service a thicker liner shall be used as determined by
the procedure given in (5.1). For grooved liner, depth of the groove shall be
added to the calculated thickness.
The definition of liner fit is based on the constant, C, which is defined as:
C
R
Where (mm) is the difference between the inner radius of the carbon
steel pipe and the outer radius of the thermoplastic liner.
3
t 2
if C 0.73 then ;liner tight
R
Page 8 of 23
Document Responsibility: Nonmetallic Standards Committee SAEP-387
Issue Date: 5 December 2012 Design of Thermoplastic Tight Fit Grooved and
Next Planned Update: 5 December 2017 Perforated Liners for New and Existing Pipelines
Ro Ri
R
2
Where Ro and Ri refer to the outer and inner radius of the liner.
NOTES: 1. Liner swell is defined as the average swell across the liner
thickness.
2. The modulus used in the above Sections should be representative
of the thermoplastic liner material at the design temperature and
include allowance for any possible reductions or increases due to
chemical absorption or de-absorption. The visco-elastic nature of
some thermoplastics may also need to be included.
The tolerance on the liner wall thickness shall be -0%/+5% of the
specified value.
Pdes JPmop
If the collapse pressure, Pc, is less than the design pressure, Pdes, of the
pipeline, then the liner wall thickness is not sufficient to prevent collapse
and vise versa. If it is greater, then the liner will not collapse.
The following defines safe design pressure procedure:
Page 9 of 23
Document Responsibility: Nonmetallic Standards Committee SAEP-387
Issue Date: 5 December 2012 Design of Thermoplastic Tight Fit Grooved and
Next Planned Update: 5 December 2017 Perforated Liners for New and Existing Pipelines
Vc
If Pdes Pc then collapse
Vinit
V
If Pdes Pc c then no collapse
Vinit
5.3.4.2 Swelling
Page 10 of 23
Document Responsibility: Nonmetallic Standards Committee SAEP-387
Issue Date: 5 December 2012 Design of Thermoplastic Tight Fit Grooved and
Next Planned Update: 5 December 2017 Perforated Liners for New and Existing Pipelines
t
swell 23.16 then collapse
R
t
swell 23.16 then no collapse
R
If there is potential that the liner will swell and gas is present in
the pipeline fluids, then (5.3.3) shall be used to determine the
collapse pressure.
Grooved thermoplastic lined pipelines shall incorporate vent points. The vent
point shall ensure venting of gases trapped in the annulus between the liner and
the host pipe over the service life of the pipeline. The vent point shall include a
valve to allow closure of the vent. The design of the vent point assembly shall
be proposed by the Contractor and agreed with the Principal. The minimum
number of vent points shall be one at each flanged end of a section of lined pipe.
In addition to its main function of venting the permeated fluid, it is also used to
monitor the integrity of the liner. Venting can be operated by installing valve to
be closed or opened during normal operation.
For water injection lines at temperatures below the 50°C venting during
operation is not necessary and therefore vents are normally plugged.
Lines transporting multi-phase hydrocarbons with H2S concentrations lower
than 50 ppm can have continuously open vents (vents shall be operated through
a valve in order to be able to close the annulus in case of liner leakage or
collapse). For gas transport with H2S concentrations of 50 ppm and higher,
vents will have to be opened and closed on a periodic basis after consultation
with Saudi Aramco Environmental Protection Department.
When checking the vents for pressure or bleeding-off the pressure, they shall be
dealt with in the same manner as breaking the integrity of any system:
2 operators are required;
1 safety person;
Self-contained breathing apparatus shall be worn by worker performing task;
Safety person shall be upwind and a safe distance away;
Record the vent pressure on the venting log sheet;
Annular pressure should be kept below 50 bar at all times;
Vents are to be left in the closed position at all times;
Page 11 of 23
Document Responsibility: Nonmetallic Standards Committee SAEP-387
Issue Date: 5 December 2012 Design of Thermoplastic Tight Fit Grooved and
Next Planned Update: 5 December 2017 Perforated Liners for New and Existing Pipelines
During normal operation the pipeline vents will be filled with 100% glycol.
This will reduce the volume of H2S that can accumulate in the vent lines.
Vent point is usually installed at each flanged end particularly for water service,
stabilized crude oil and oil/water mixture.
The pull-in force, Fpull (N), for a thermoplastic liner is calculated from the sum
of three force components which includes: Ffriction, the friction load from
pulling the liner inside the steel pipe, Fbend, the additional friction loads caused
by bends etc. and Freduce, the load applied to the liner from the installation
technique:
The calculation procedure for determining the maximum loads and stresses
acting on the liner during installation shall be as outlined in this section. If the
Contractor wishes to use an alternative procedure this shall be submitted to the
Principal for approval.
The friction force is derived from two parts. The first one is due to the
weight of the liner and the associated friction factor, while the second
one is associated with the superficial damage to the outside of the
thermoplastic liner, i.e.:
Page 12 of 23
Document Responsibility: Nonmetallic Standards Committee SAEP-387
Issue Date: 5 December 2012 Design of Thermoplastic Tight Fit Grooved and
Next Planned Update: 5 December 2017 Perforated Liners for New and Existing Pipelines
The bending force is derived from the friction factor and the angle of the
bend;
Where; f is the friction factor, Fpull (N) is the pull-in load and is the
bend angle.
Where; t (mm) is the liner wall thickness and D (mm) is the internal
diameter of the steel pipe.
For the different installation techniques, Table 5.6.3 lists the reduction
pressure.
The maximum allowable tensile load on the liner is limited to 50% of the
tensile yield strength, yield (MPa). Therefore, the maximum allowable
pull-in force, Fpull-max, is given by:
Page 13 of 23
Document Responsibility: Nonmetallic Standards Committee SAEP-387
Issue Date: 5 December 2012 Design of Thermoplastic Tight Fit Grooved and
Next Planned Update: 5 December 2017 Perforated Liners for New and Existing Pipelines
The maximum allowable liner insertion length (m) is therefore given by:
L liner
0.5 yield (2 expf) Preduce t(D t) Fscore
Wf
5.7.1 General
The Contractor shall select the end connection and shall submit this for
approval to the Principal. The Contractor shall demonstrate by means of
a qualification test that the end connection meets the same operational
requirements as the thermoplastic liner. The design shall account for
shrinkage, creep, aging of the thermoplastic material and operational
pressure fluctuations.
The thermoplastic flange shall be made from the same material as the
liner and have the same internal diameter as the liner. The minimum
length of the flange shall be 150 mm.
The steel retainer rings shall be such that they fit between the
thermoplastic flange and inside the bolt circle of the steel flanges.
6 Liner Installation
Installation of tight fit liner techniques regardless of the type of liner venting,
i.e., grooved or perforated liners are considered in this procedure.
The process starts with a liner, (pipe) having an outside diameter larger
in size than the inside of the host pipe (the pipe that is being lined) and
reduce it temporarily to enable it to be towed through the host pipe.
Whilst the towing load keeps the liner pipe under tension, it remains in
its reduced size. The thermoplastic pipe (liner) remains fully elastic
throughout the reduction and installation process. As the liner pipe is not
permanently deformed by this method, the release of the towing load
Page 14 of 23
Document Responsibility: Nonmetallic Standards Committee SAEP-387
Issue Date: 5 December 2012 Design of Thermoplastic Tight Fit Grooved and
Next Planned Update: 5 December 2017 Perforated Liners for New and Existing Pipelines
after insertion is the catalyst for the liner to start reverting back towards
its original size. As its original size is larger than that of the host pipe,
the liner expands until it is halted by the inside diameter of the host pipe.
The thermoplastic liner has been prevented from continuous expansion
back to its original state. This produces a residual strain that is locked in
the liner and keeps it pressed tight against the inside of the host pipe,
even with no internal pressure from the product conveyed.
The annulus is continuously vented with the end result being a very tight
interference fit between the liner and the host pipe. This technique
provides the tightest possible liner fit but is the most demanding in terms
of engineering tolerances.
This technique begins with a thermoplastic liner that has a larger outside
diameter than the inside diameter of the steel pipe it protects. The steel
pipeline is cut into sections that allow for the insertion of the pipe lining
system.
A wire line cable is sent through a section of pipeline and is then attached
to the liner. The wire line pulls the internal pipe lining system through the
roller reduction box which is positioned at the insertion end of the pipeline
section. The liner pipe is compressed radially as it passes through the
roller reduction box. This temporary reduction provides sufficient
clearance between the steel pipe and the liner pipe to allow insertion.
Page 15 of 23
Document Responsibility: Nonmetallic Standards Committee SAEP-387
Issue Date: 5 December 2012 Design of Thermoplastic Tight Fit Grooved and
Next Planned Update: 5 December 2017 Perforated Liners for New and Existing Pipelines
For both a new or existing pipeline, the pipe inner surface shall be thoroughly
cleaned before liner installation.
6.3.1 General
The thermoplastic liner pipe shall be joined using butt fusion welding
process, as defined in ASTM D2657, Technique II. Any proposal by the
Contractor to use a different technique, e.g., hand welding, shall be
subject to agreement by the Principal.
Personnel from the Contractor performing the butt fusion welding shall
be certified by the liner Manufacturer in the liner joining procedure.
Page 16 of 23
Document Responsibility: Nonmetallic Standards Committee SAEP-387
Issue Date: 5 December 2012 Design of Thermoplastic Tight Fit Grooved and
Next Planned Update: 5 December 2017 Perforated Liners for New and Existing Pipelines
After completion of the fusion weld, the internal and external bead of the
weld shall be trimmed. After trimming, the surface of the joint shall be
visually examined for evidence of good fusion. Nicks, gouges or
undercuts caused by bead trimming are not acceptable and shall be
removed or cut-out.
The Contractor shall prepare a detailed procedure for each type and size
of joint and fitting to be welded. Separate procedures shall be prepared
for shop and site welding.
Each butt fusion welding procedure shall detail the following information:
welding equipment type and model;
material grade and Manufacturer;
pipe/fitting dimensions at the joint;
welding sequence.
For each pipe butt fusion welding procedure to be used a test spool shall
be prepared and welded. This shall consist of three pipe sections butt
fusion welded together with a flange welded at each end, i.e., 4
circumferential welds in total. The assembly shall be tested as follows:
weld dimensions - within tolerances of approved welding procedure;
visual inspection - no visible defects;
ultrasonic and/or radiographic examination when specified by the
Principal - acceptance criteria to be agreed;
pressure test using water at the maximum design temperature and at a
pressure agreed with the Principal or 1.5 times the equivalent “rated”
Page 17 of 23
Document Responsibility: Nonmetallic Standards Committee SAEP-387
Issue Date: 5 December 2012 Design of Thermoplastic Tight Fit Grooved and
Next Planned Update: 5 December 2017 Perforated Liners for New and Existing Pipelines
For each material grade and weld type, four additional test samples shall
be prepared from the largest diameter represented. The test samples
shall be tested to short-term burst pressure according to ASTM D1599.
The acceptance criterion is that the pipe shall not fail at the weld.
All butt fusion welding operators who successfully complete the above
welding procedure qualification shall be considered qualified for butt
fusion welds of the same type, material grade and diameter range as
represented by the procedure.
All qualified welders shall wear an ID card including a pass photo and
stating name, validity (end date of project) diameter range, wall
thickness and material grade for which they are qualified. The ID card
shall be signed by the Principal.
6.3.3 Testing
The Contractor shall conduct an air test on the fused liner section prior to
installation of the liner. A maximum pressure of 0.3 bars shall be
applied for duration of not more than 3 hours unless otherwise specified
by the Principal. The pipe should be anchored at 5 to 7 meter intervals
with back-fill material before pressuring. A vacuum should not be
pulled. All fusion joints shall be soap-tested in the presence of an
Inspector, approved by the Principal.
Before installation, the Contractor shall clean the pipeline and demonstrate that
the bore of the carbon steel pipeline is free from obstructions (e.g., excessive
weld penetration, dents, etc.) that could interfere with or damage the liner during
installation. A gauging plate shall be used to assess the internal diameter
variations within the carbon steel pipeline.
The wireline unit should be suitably instrumented with footage and weight
indicators, an overload control set to a maximum of 100% of the calculated
Page 18 of 23
Document Responsibility: Nonmetallic Standards Committee SAEP-387
Issue Date: 5 December 2012 Design of Thermoplastic Tight Fit Grooved and
Next Planned Update: 5 December 2017 Perforated Liners for New and Existing Pipelines
maximum allowable pulling force and fitted with a speed controllable reel with
cable spooling and braking facility.
The Contractor should provide suitable pigs and launching equipment to propel
the wireline and pig train through the pipeline.
Once the wireline has been passed through the pipeline section, the pig train is
pulled through, the pulling force being continuously monitored to determine the
location of any constrictions.
The disc plate should be of sufficient diameter to verify that internal weld beads
do not protrude excessively taking into account the dimensional tolerances of
the steel pipe.
The outer diameter of the liner pipe segment should be such that any excess
weld penetration which could result in liner puncture during normal operation is
detected.
The liner test segment attached to the pig train should emerge without serious
damage. Scuffing of the liner surface is permissible but sharp longitudinal scars or
other penetration damage exceeding 0.5 mm or 5% of the wall thickness, whichever
is larger, is unacceptable and would require rectification by further pigging using a
breaker pig or by other means prior to continuing with liner installation.
After rectification another liner test segment should be pulled through.
6.7 Insertion
The actual pull-in load shall be continuously monitored during pull-in. It shall
not be allowed to exceed the maximum allowable pull-in load.
Page 19 of 23
Document Responsibility: Nonmetallic Standards Committee SAEP-387
Issue Date: 5 December 2012 Design of Thermoplastic Tight Fit Grooved and
Next Planned Update: 5 December 2017 Perforated Liners for New and Existing Pipelines
When the liner has been pulled in, flange adapters should be fusion welded to
each end.
Flange bolts shall be tightened with a torque wrench, using greased bolts and
nuts, in sequence and to the torque values as specified by the Manufacturer.
Too great a bolt loading may damage the plastic facing on the flanges.
Appropriate spring washers should be used between the nut and the flange.
Bolts should be re-torqued after an initial service period of 24 hours.
6.9 Testing
The complete lined pipeline system shall be hydro-tested with water at ambient
temperature at 1.5 times the maximum operating pressure or the pressure of the
pipeline strength test for a period of 24 hours. For the duration of the test all
vent points shall remain open.
The pressure may fluctuate due to variations in ambient temperature, and care
shall be taken that the test pressure does not exceed the lowest rated element in
the system. During hydrotesting, temperature and pressure shall be recorded
continuously unless otherwise agreed with the Principal.
During the hydrotest the pressure shall be increased first to 3 times the liner pipe
free-standing pressure rating with all vents open to allow annular fluids to
escape. If all fluids have escaped or after one hour, which ever takes longer, the
pressure shall be increased to the required hydrotest pressure.
At the end of the hydrotest the vents shall all be closed whilst the line is still
under pressure. Two to four weeks after commissioning it is recommended that
all vents should be opened and closed again to allow fluids which may have
permeated through the annulus to the vents to escape as well as to check whether
any liner defects have developed.
7 Operation
7.1 Start-Up
Page 20 of 23
Document Responsibility: Nonmetallic Standards Committee SAEP-387
Issue Date: 5 December 2012 Design of Thermoplastic Tight Fit Grooved and
Next Planned Update: 5 December 2017 Perforated Liners for New and Existing Pipelines
7.2 De-Pressurizing
Before de-pressurizing the pipeline the vent points should be opened for at least
one hour. The rate at which the vent point can relieve the gas trapped in the
annulus should be estimated to ensure that the venting rate, during
de-pressurization, is sufficient to prevent a positive pressure difference between
the annulus and the pipeline, i.e., at no time during de-pressurization should the
annulus pressure be greater than the line pressure.
7.3 Pigging
Pipelines with liners do not usually require pigging. However, if the line
requires pigging to remove fluids, then only foam pigs shall be used.
7.4 Venting
Venting procedures are required to prevent liner collapse during process upset
conditions (large pressure fluctuations) or shutdowns. Venting is required when
gases are present in the pipeline fluids. Venting may not be required for liquid
lines operating at the liner design maximum service temperature.
Venting operations shall be recorded in a log and include: date, length of time
vent remained open, vent pressure, volume of gas vented and other general
observations. The requirement for monthly venting may be revised on
experience using the log entries to justify revising the venting frequency.
Alternatively, it may be decided to operate the pipelines with the vents open
(assuming approval from Saudi Aramco Environmetal Department is obtained),
i.e., continuously venting the annulus. Open vents shall be inspected at least
monthly to check integrity of the thermoplastic liner and blockage of the vent
points.
7.5 Maintenance
Vent points shall be kept free from paint or other deposits. Blocked vent points,
pipes and fittings should be cleaned with low-pressure water only. The use of
rods, steam jets or sharp tools for cleaning shall not be permitted.
The vent holes and flange bolt torques shall be checked regularly.
Page 21 of 23
Document Responsibility: Nonmetallic Standards Committee SAEP-387
Issue Date: 5 December 2012 Design of Thermoplastic Tight Fit Grooved and
Next Planned Update: 5 December 2017 Perforated Liners for New and Existing Pipelines
If toxic gases are present the Environmetal Department shall be consulted before
venting operations.
7.6 Repair
Lined pipes and fittings shall not be repaired by welding, since heat could cause
damage to the liner. If damage occurs to a component of an installed lined
piping system, the damaged component shall be replaced.
8 Documentation
Page 22 of 23
Document Responsibility: Nonmetallic Standards Committee SAEP-387
Issue Date: 5 December 2012 Design of Thermoplastic Tight Fit Grooved and
Next Planned Update: 5 December 2017 Perforated Liners for New and Existing Pipelines
Revision Summary
5 December 2012 New Saudi Aramco Engineering Procedure.
Page 23 of 23