Basic Data Entry

Fill in all of the white cells with the necessary information.

Project Name ROB AT 68+680

Customer Name/Location PATEL INFRA / HISAR

Estimated Project Start Date 1-Mar-22

Estimated Project End Date 10-Apr-22

Project Manager Name Mr. R K Srivastava

Project Team Members, Task Groups & Stakeholders

Sr. No. Name & Designation Contact


1 Mr. R K Srivastava (GM technical)
2 Mr. Gaurav Sood (Manager Marketing)
3 Mr. J P Singh (Sr. GM)
4 Mr. Rakesh Sharma (PPC)
5 Mr. Sameer Goel (Site Engineer)
6 Mr. Gurnam (Contractor)
7
8
9
10
ROB AT 68+680

PATEL INFRA / HISAR

1-Mar-22 1-Mar-22

10-Apr-22 10-Apr-22

Mr. R K Srivastava

Holidays/Time Off Projects

Date Holiday
Planning
IMPORTANT NOTICE:
It is very important that tasks are entered with unique names. If task names are repeated, the data will not carry over correc
differently.
Task Owner must be selected from Drop Down list only, otherwise systems will not accept any entry

Project Task Information

Sr. NO. Project Task Estimated Start


Date
1 Supply of S1 30 mtr LHS Span 1-Mar-22
2 Assembly of S1 30 mtr LHS Span 7-Mar-22
3 Torquing of S1 30 mtr LHS Span 10-Mar-22
4 Launching of S1 30 mtr LHS Span 12-Mar-22
5 Bracing of S1 30 mtr LHS Span 14-Mar-22
6 Lowering of S1 30 mtr LHS Span 16-Mar-22
7 Supply of S2 30 mtr LHS Span 1-Mar-22
8 Assembly of S2 30 mtr LHS Span 7-Mar-22
9 Torquing of S2 30 mtr LHS Span 11-Mar-22
10 Launching of S2 30 mtr LHS Span 13-Mar-22
11 Bracing of S2 30 mtr LHS Span 16-Mar-22
12 Lowering of S2 30 mtr LHS Span 18-Mar-22
13 Fabrication of S1 43 mtr LHS Span 1-Mar-22
14 Supply of S1 43 mtr LHS Span 13-Mar-22
15 Assembly of S1 43 mtr LHS Span 18-Mar-22
16 Torquing of S1 43 mtr LHS Span 22-Mar-22
17 Launching of S1 43 mtr LHS Span 25-Mar-22
18 Bracing of S1 43 mtr LHS Span 27-Mar-22
19 Lowering of S1 43 mtr LHS Span 30-Mar-22
20 Fabrication of S3 30 mtr RHS Span 1-Mar-22
21 Supply of S3 30 mtr RHS Span 9-Mar-22
22 Assembly of S3 30 mtr RHS Span 11-Mar-22
23 Torquing of S3 30 mtr RHS Span 14-Mar-22
24 Launching of S3 30 mtr RHS Span 16-Mar-22
25 Bracing of S3 30 mtr RHS Span 18-Mar-22
26 Lowering of S3 30 mtr RHS Span 20-Mar-22
27 Fabrication of S4 30 mtr RHS Span 1-Mar-22
28 Supply of S4 30 mtr RHS Span 9-Mar-22
29 Assembly of S4 30 mtr RHS Span 11-Mar-22
30 Torquing of S4 30 mtr RHS Span 14-Mar-22
31 Launching of S4 30 mtr RHS Span 16-Mar-22
32 Bracing of S4 30 mtr RHS Span 18-Mar-22
33 Lowering of S4 30 mtr RHS Span 20-Mar-22
34 Fabrication of S2 30 mtr RHS Span 1-Mar-22
35 Supply of S2 30 mtr RHS Span 21-Mar-22
36 Assembly of S2 30 mtr RHS Span 25-Mar-22
37 Torquing of S2 30 mtr RHS Span 28-Mar-22
38 Launching of S2 30 mtr RHS Span 1-Apr-22
39 Bracing of S2 30 mtr RHS Span 3-Apr-22
40 Lowering of S2 30 mtr RHS Span 5-Apr-22
41
42
43
44
45
46
ted, the data will not carry over correctly. Make sure to name each task

cept any entry

mation

Estimated Task Owner


Completion Date (MUST USE DROP DOWN MENU)
7-Mar-22
9-Mar-22
11-Mar-22
13-Mar-22
15-Mar-22
17-Mar-22
7-Mar-22
10-Mar-22
12-Mar-22
15-Mar-22
17-Mar-22
19-Mar-22
12-Mar-22
17-Mar-22
21-Mar-22
24-Mar-22
26-Mar-22
29-Mar-22
31-Mar-22
8-Mar-22
11-Mar-22
13-Mar-22
15-Mar-22
17-Mar-22
19-Mar-22
21-Mar-22
8-Mar-22
11-Mar-22
13-Mar-22
15-Mar-22
17-Mar-22
19-Mar-22
21-Mar-22
20-Mar-22
25-Mar-22
27-Mar-22
31-Mar-22
2-Apr-22
4-Apr-22
6-Apr-22
Work Schedule Monitoring
GANTT CHART LEGEND
HOLIDAY/VACATION/NO WORK
PLANNED PROJECT WORK DAY
SCHEDULE FOR FABRICATION, SUPPLY & ERECTION
TASK COMPLETED
CONSTRUCTION OF EIGHT LANE VADODARA-KIM EXPRESSWAY (PHASE IA PKG 3)
ROB BETWEEN THAM AND SAMINI STATION AT CH 293+014 COMPLETION STATUS LEGEND

TASK COMPLETED AHEAD OF SCHEDULE


TASK COMPLETED BEHIND SCHEDULE

Project Task Information WEEK 1 WEEK 2 WEEK 3 WEEK 4 WEEK 5 WEEK 6 WEEK 7 WEEK 8 WEEK 9 WEEK 10 WEEK 11 WEEK 12 WEEK 13 WEEK 14 WEEK 15

Estimated Actual 28-Feb-22 7-Mar-22 14-Mar-22 21-Mar-22 28-Mar-22 4-Apr-22 11-Apr-22 18-Apr-22 25-Apr-22 2-May-22 9-May-22 16-May-22 23-May-22 30-May-22 6-Jun-22
Sr. No. Estimated Actual Start
Project Task Completion Completion Comments
Start Date Date 28 1 2 3 4 5 7 8 9 10 11 12 14 15 16 17 18 19 21 22 23 24 25 26 28 29 30 31 1 2 4 5 6 7 8 9 11 12 13 14 15 16 18 19 20 21 22 23 25 26 27 28 29 30 2 3 4 5 6 7 9 10 11 12 13 14 16 17 18 19 20 21 23 24 25 26 27 28 30 31 1 2 3 4 6 7 8 9 10 11
Date Date
M T W T F S M T W T F S M T W T F S M T W T F S M T W T F S M T W T F S M T W T F S M T W T F S M T W T F S M T W T F S M T W T F S M T W T F S M T W T F S M T W T F S M T W T F S

1 Supply of S1 30 mtr LHS Span 1-Mar-22 7-Mar-22 X X X X X X


2 Assembly of S1 30 mtr LHS Span 7-Mar-22 9-Mar-22 X X X
3 Torquing of S1 30 mtr LHS Span 10-Mar-22 11-Mar-22 X X
4 Launching of S1 30 mtr LHS Span 12-Mar-22 13-Mar-22 X
5 Bracing of S1 30 mtr LHS Span 14-Mar-22 15-Mar-22 X X
6 Lowering of S1 30 mtr LHS Span 16-Mar-22 17-Mar-22 X X
7 Supply of S2 30 mtr LHS Span 1-Mar-22 7-Mar-22 X X X X X X
8 Assembly of S2 30 mtr LHS Span 7-Mar-22 10-Mar-22 X X X X
9 Torquing of S2 30 mtr LHS Span 11-Mar-22 12-Mar-22 X X
10 Launching of S2 30 mtr LHS Span 13-Mar-22 15-Mar-22 X X
11 Bracing of S2 30 mtr LHS Span 16-Mar-22 17-Mar-22 X X
12 Lowering of S2 30 mtr LHS Span 18-Mar-22 19-Mar-22 X X
13 Fabrication of S1 43 mtr LHS Span 1-Mar-22 12-Mar-22 X X X X X X X X X X X
14 Supply of S1 43 mtr LHS Span 13-Mar-22 17-Mar-22 X X X X
15 Assembly of S1 43 mtr LHS Span 18-Mar-22 21-Mar-22 X X X
16 Torquing of S1 43 mtr LHS Span 22-Mar-22 24-Mar-22 X X X
17 Launching of S1 43 mtr LHS Span 25-Mar-22 26-Mar-22 X X
18 Bracing of S1 43 mtr LHS Span 27-Mar-22 29-Mar-22 X X
19 Lowering of S1 43 mtr LHS Span 30-Mar-22 31-Mar-22 X X
20 Fabrication of S3 30 mtr RHS Span 1-Mar-22 8-Mar-22 X X X X X X X
21 Supply of S3 30 mtr RHS Span 9-Mar-22 11-Mar-22 X X X
22 Assembly of S3 30 mtr RHS Span 11-Mar-22 13-Mar-22 X X
23 Torquing of S3 30 mtr RHS Span 14-Mar-22 15-Mar-22 X X
24 Launching of S3 30 mtr RHS Span 16-Mar-22 17-Mar-22 X X
25 Bracing of S3 30 mtr RHS Span 18-Mar-22 19-Mar-22 X X
26 Lowering of S3 30 mtr RHS Span 20-Mar-22 21-Mar-22 X
27 Fabrication of S4 30 mtr RHS Span 1-Mar-22 8-Mar-22 X X X X X X X
28 Supply of S4 30 mtr RHS Span 9-Mar-22 11-Mar-22 X X X
29 Assembly of S4 30 mtr RHS Span 11-Mar-22 13-Mar-22 X X
30 Torquing of S4 30 mtr RHS Span 14-Mar-22 15-Mar-22 X X
31 Launching of S4 30 mtr RHS Span 16-Mar-22 17-Mar-22 X X
32 Bracing of S4 30 mtr RHS Span 18-Mar-22 19-Mar-22 X X
33 Lowering of S4 30 mtr RHS Span 20-Mar-22 21-Mar-22 X
34 Fabrication of S2 30 mtr RHS Span 1-Mar-22 20-Mar-22 X X X X X X X X X X X X X X X X X
35 Supply of S2 30 mtr RHS Span 21-Mar-22 25-Mar-22 X X X X X
36 Assembly of S2 30 mtr RHS Span 25-Mar-22 27-Mar-22 X X
37 Torquing of S2 30 mtr RHS Span 28-Mar-22 31-Mar-22 X X X X
38 Launching of S2 30 mtr RHS Span 1-Apr-22 2-Apr-22 X X
39 Bracing of S2 30 mtr RHS Span 3-Apr-22 4-Apr-22 X
40 Lowering of S2 30 mtr RHS Span 5-Apr-22 6-Apr-22 X X
41
42
43
44
45
46
47
30
Issue Log

Date Issue Responsible


Action Taken
Reporting

Running and Pending Task Status Overall Progress Status Total Time Left

18% 5%

Task is running behind


schedule
Task is behind schedule and Task complete
not started yet Total Time Consumed
Not started Yet
Task is running on time Total time left
Under Process
Task is scheduled for this
time frame

82%
100% 95%

Task Number Task Owner Task to be completed Task Status Due on On Going Status

1 Supply of S1 30 mtr LHS Span NOT STARTED YET 7-Mar-22 Task is behind schedule and not started yet
2 Assembly of S1 30 mtr LHS Span NOT STARTED YET 9-Mar-22 Task is scheduled for this time frame
3 Torquing of S1 30 mtr LHS Span NOT STARTED YET 11-Mar-22 Task is scheduled for this time frame
4 Launching of S1 30 mtr LHS Span NOT STARTED YET 13-Mar-22 Task is scheduled for this time frame
5 Bracing of S1 30 mtr LHS Span NOT STARTED YET 15-Mar-22 Task is scheduled for this time frame
6 Lowering of S1 30 mtr LHS Span NOT STARTED YET 17-Mar-22 Task is scheduled for this time frame
7 Supply of S2 30 mtr LHS Span NOT STARTED YET 7-Mar-22 Task is behind schedule and not started yet
8 Assembly of S2 30 mtr LHS Span NOT STARTED YET 10-Mar-22 Task is scheduled for this time frame
9 Torquing of S2 30 mtr LHS Span NOT STARTED YET 12-Mar-22 Task is scheduled for this time frame
10 Launching of S2 30 mtr LHS Span NOT STARTED YET 15-Mar-22 Task is scheduled for this time frame
11 Bracing of S2 30 mtr LHS Span NOT STARTED YET 17-Mar-22 Task is scheduled for this time frame
12 Lowering of S2 30 mtr LHS Span NOT STARTED YET 19-Mar-22 Task is scheduled for this time frame
13 Fabrication of S1 43 mtr LHS Span NOT STARTED YET 12-Mar-22 Task is behind schedule and not started yet
14 Supply of S1 43 mtr LHS Span NOT STARTED YET 17-Mar-22 Task is scheduled for this time frame
15 Assembly of S1 43 mtr LHS Span NOT STARTED YET 21-Mar-22 Task is scheduled for this time frame
16 Torquing of S1 43 mtr LHS Span NOT STARTED YET 24-Mar-22 Task is scheduled for this time frame
17 Launching of S1 43 mtr LHS Span NOT STARTED YET 26-Mar-22 Task is scheduled for this time frame
18 Bracing of S1 43 mtr LHS Span NOT STARTED YET 29-Mar-22 Task is scheduled for this time frame
19 Lowering of S1 43 mtr LHS Span NOT STARTED YET 31-Mar-22 Task is scheduled for this time frame
20 Fabrication of S3 30 mtr RHS Span NOT STARTED YET 8-Mar-22 Task is behind schedule and not started yet
21 Supply of S3 30 mtr RHS Span NOT STARTED YET 11-Mar-22 Task is scheduled for this time frame
22 Assembly of S3 30 mtr RHS Span NOT STARTED YET 13-Mar-22 Task is scheduled for this time frame
23 Torquing of S3 30 mtr RHS Span NOT STARTED YET 15-Mar-22 Task is scheduled for this time frame
24 Launching of S3 30 mtr RHS Span NOT STARTED YET 17-Mar-22 Task is scheduled for this time frame
25 Bracing of S3 30 mtr RHS Span NOT STARTED YET 19-Mar-22 Task is scheduled for this time frame
26 Lowering of S3 30 mtr RHS Span NOT STARTED YET 21-Mar-22 Task is scheduled for this time frame
27 Fabrication of S4 30 mtr RHS Span NOT STARTED YET 8-Mar-22 Task is behind schedule and not started yet
28 Lowering of S2 30 mtr RHS Span NOT STARTED YET 6-Apr-22 Task is scheduled for this time frame
29
30