September 2023

Monday Tuesday Wednesday Thursday Friday Saturday Sunday


1 2 3

4 5 6 7 8 9 10

11 12 13 14 15 16 17
SURVEY LAYOUT, 3 days

18 19 20 21 22 23 24
Excavation, 7 days

25 26 27 28 29 30
Excavation, 7 days Earth dressing, 3 days PCC foundation, 3 days
October 2023
Monday Tuesday Wednesday Thursday Friday Saturday Sunday
1
PCC foundation, 3 days

2 3 4 5 6 7 8
PCC foundation, 3 days RCC of foundation, 7 days

9 10 11 12 13 14 15
RCC of foundation, 7 days Column up to plinth, 3 days

16 17 18 19 20 21 22
Column up to plinth, 3 days Plinth beam Rcc, 7 days

23 24 25 26 27 28 29
Plinth beam Rcc, 7 days Column up to slab, 4 days
Complition of Sub structure

30 31
Column up to slab, 4 days
November 2023
Monday Tuesday Wednesday Thursday Friday Saturday Sunday
1 2 3 4 5
Column up to slab, 4 days Ground floor Slab, 10 days

6 7 8 9 10 11 12
Ground floor Slab, 10 days

13 14 15 16 17 18 19
Ground floor Slab, 10 days Column up to slac, 4 days

20 21 22 23 24 25 26
Column up to slac, 4 days First floor Slab, 10 days

27 28 29 30
First floor Slab, 10 days
December 2023
Monday Tuesday Wednesday Thursday Friday Saturday Sunday
1 2 3
First floor Slab, 10 days

4 5 6 7 8 9 10
First floor Slab, 10 days Column up to slac, 4 days Second floor Slab, 10 days

11 12 13 14 15 16 17
Second floor Slab, 10 days

18 19 20 21 22 23 24
Second floor Slab, 10 days column up to slab, 4 days

25 26 27 28 29 30 31
column up to slab, 4 days third floor slab, 10 days
January 2024
Monday Tuesday Wednesday Thursday Friday Saturday Sunday
1 2 3 4 5 6 7
third floor slab, 10 days

8 9 10 11 12 13 14
third floor slab, 10 days

15 16 17 18 19 20 21

22 23 24 25 26 27 28

29 30 31