ID Task Name Duration Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week

Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 Week 17 Week 18
-2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123 124
1 TIME TABLE
2 on-site construction works 126 days
3 preliminaries works 9 days
4 site handling over 1 day
5 site protection 3 days
6 site marking 7 days
7 marking approval 3 days
8 interior works 80 days
9 partition works ( framing, gypsum 52 days
partition, wooden panel backing,
skirtings and cornice, glass partition)
10 3th floor 31 days
11 5th floor 31 days
12 6th floor 31 days
13 7th floor 31 days
14 8th floor 31 days
15 9th floor 31 days
16 10th floor 31 days
17 LG drivers room 14 days
18 ceiling works (demolish existing ceiling, 45 days
framing, plaster ceiling, ceiling features,
paint finishes)
19 3th floor 21 days
20 5th floor 21 days
21 6th floor 21 days
22 7th floor 21 days
23 8th floor 21 days
24 9th floor 21 days
25 10th floor 21 days
26 LG drivers room 7 days
27 wall finishes (repair existing wall, 52 days
wooden panel/wall feature, wall
covering, paint finishes)
28 3th floor 28 days
29 5th floor 28 days
30 6th floor 28 days
31 7th floor 28 days
32 8th floor 28 days
33 9th floor 28 days
34 10th floor 28 days
35 LG drivers room 12 days
36 floor finishes ( 51 days
granite/marble/homogenous floor ; vynil
floor ; carpet tiles installation )
37 3th floor 25 days
38 5th floor 21 days
39 6th floor 21 days
40 7th floor 21 days
41 8th floor 21 days
42 9th floor 21 days
43 10th floor 21 days
44 LG drivers room 10 days
45 door works ( jamb installation; door 46 days
installation )
46 3th floor 10 days
47 5th floor 7 days
48 6th floor 7 days
49 7th floor 7 days
50 8th floor 7 days
51 9th floor 7 days
52 10th floor 7 days
53 LG drivers room 1 day
54 furniture/system furniture/working chair 62 days
( fabrication, mass production and
delivery ; installation )
55 3th floor 30 days
56 5th floor 30 days
57 6th floor 30 days
58 7th floor 30 days
59 8th floor 30 days
60 9th floor 30 days
61 10th floor 30 days
62 LG drivers room 21 days
63 mep, vd, security system works 71 days
64 3th floor 45 days
65 5th floor 45 days
66 6th floor 45 days
67 7th floor 45 days
68 8th floor 45 days
69 9th floor 45 days
70 10th floor 45 days
71 LG drivers room 21 days
72 final works ( mural, artworks, logo & 53 days
room signage; check list & detect
rectification; general cleaning; hand over
)
73 3th floor 14 days
74 5th floor 14 days
75 6th floor 14 days
76 7th floor 14 days
77 8th floor 14 days
78 9th floor 14 days
79 10th floor 14 days
80 LG drivers room 7 days
81 moving stage 10 days
82 pre-packing non active files and 3 days
equipments
83 moving works to new office (batch-1) 7 days
84 unpacking, setting up equipment, 7 days
occupancy
85 reinstatement works 56 days
86 site handling over to contractor 4 days
87 re-instate existing floor, partition, ceiling 30 days
and finishes
88 re-instate existing mep fixtures 30 days
89 checklist with bm/landlord and 14 days
rectification
90 site handling over from client to 3 days
bm/landlord