51 Chancery Lane

Date: October 2 2019

PLOT PERIODS
PLAN PLOT 1/2 PERCENT
ACTIVITY PLAN START 1/2
DURATION Duration COMPLETE
Start
Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20
33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78
1 Structural Works Zone 2 ( 2 units semi-d)
4 Ground beams 38 3
5 1st sty slabs 39 4
6 1st sty coulumns and RC walls 42 2
7 2nd Sty Beams and Slabs 43 2
8 2nd Sty Columns and RC walls 44 2
9 Attic Beams and Slabs 45 3
10 Attic columns 47 1
11 RC Flat Roof 48 2
12 Architectural Works PLOT 3/4/5
13 Brick Works 36 5 44 5
14 Waterproofing 39 5 47 5
15 Alum Window and Door Frames Installation
20 Installation of Frame 40 7 47 7
21 Installation of Door and window panel 48 4 52 4
22 Plastering / Skim Coating Works 39 12 51 12
23 Floor Screeding 45 4 57 4
24 Tiling/Marble works
28 Screeding/Plastering 41 8 49 8
29 Installation 46 12 58 10
30 Ceiling Works 49 7 56 6
31 Timber Flooring 52 6 58 6
32 Timber Door
38 Door frame installation 50 3 53 3
39 Installation of door leaf 58 2 60 2
40 Glazing Works 57 4 61 4
41 Railing Works 49 6 55 6
42 External Painting 49 8 57 8
44 Internal Painting 52 8 60 8
46 Aluminum Screen 58 6 64 4
47 Landscape Works 62 4 66 4
48 House Signage 60 2 62 2
49 ID Works and Confirmation
50 Confirmation of power points and switches location on site 41 1
51 Issuance of confirmed Dry and Wet kitchen drawing to Merger 44 1
52 Installation of of Dry and wet kitchen 52 6 58 6
Issuance of bathroom and cabinet and wardrobe drawing to
53 38 1
Merger
54 Installation of Bathrooms cabinetry 49 6 55 6
55 Installation of Wardrobe and wall panel if any 58 6 64 6
PLOT PERIODS
PLAN PLOT 1/2 PERCENT
ACTIVITY PLAN START 1/2
DURATION Duration COMPLETE
Start
Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20
33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78
56 M & E Works
57 Sanitary and Plumbing Works
60 Underground Piping and IC works Completion 49 2 51 2
61 Above Ground piping works 37 12 49 12
63 Delivery of concealed fittings 42 1
64 Installation of S&P fittings 58 3 61 3
65 Electrical & Security System
68 Conduit pipes installation 37 12 49 12
69 Pulling of wires 46 7 53 7
70 Delivery of concealed light box 44 1
71 Installation of electrical & Security fittings 57 6 63 8
72 ACMV
75 Refrigerant Pipe Installation 36 8 44 8
76 FCU installation 40 12 52 12
77 CU installation 51 3 54 3
78 NEA noise Test 59 2 61 2
79 Testing and Commisioning 61 1 66 1
80 Lift
83 Lift Delivery 50 2 52 2
84 Installation 53 6 59 2
85 Lift Testing 61 3 64 2
86 Lift Permit to Operate 64 1 65 1
87 Swimming Pool System
90 Piping works 23 14 37 10
91 pumps and filter 58 3 61 3
92 Testing and Commisioning 61 1 66 1
93 Telecom/ Fiber Readiness 65 1 66 1
94 PUB Water Turn On 60 1 64 1
95 SP Power Turn On 60 1 64 1
96 TOP Inspection 68 1 72 1
97 Target Handover to Client 72 1 76 1

Dec 7 2018 Page 2 of 2