SL WBS_SL WBS_Works Activity

1 1 Site Preparation, Layout, Mobilization, Office


2 Sub-structure
2.1 Foundation/footing works
2.1.1 Earth Cutting
2.1.2 PCC
2.1.3 shuttering
2.1.4 Footing
2.1.5 Casting
2.2 Pedestal column
2.2.1 Rod binding
2.2.2 shuttering
2.2.3 Casting
2.3 Grade beam
2.3.1 Rod binding
2.3.2 shuttering
2.3.3 Casting
2.4 Brick work
2.5 Sand filling
2.6 Ramp Works
2.6.1 Polythene laying
2.6.2 Rod binding
2.6.3 Casting
2.7 UGWR
2.8 Septic tank
2.9 Soak well
3 Super Structure
3.1 GF column Works with Fins
3.1.1 Rod binding
3.1.2 Shuttering
3.1.3 Casting
3.2 1st floor slab
3.2.1 shuttering
3.2.2 Rod binding
3.2.3 Casting
3.3 2nd floor slab
3.2.1 shuttering
3.2.2 Rod binding
3.2.3 Casting
3.4 Roof slab
3.4.1 shuttering
3.4.2 Rod binding
3.4.3 Casting
3.5 Casting on roof
3.5.1 Parapet wall & Dome
3.6 GF Brick work
3.7 1st floor Brick work
3.8 2nd floor Brick work
3.9 On roof Brick work
3.10 Plaster Work
3.11 Paint work
3.12 Metal works
3.12.1 W

2 2
3 2.1 Earthwork
4 2.2 PCC Works
5 2.3 Ramp (AGL-GL)
6 2.4 RCC works
7 2.4.1 Footing
8 2.4.2 Column
9 2.4.3 G. Beam
10 2.4.4 Stair
11 2.4.5 Fins Column
12 2.4.6 Earth filling work
13 2.5 floor slab
14 2.6 Brick Wall
15 2.7 UGWR
16 2.8 Septic Tank
17 3 Ground Floor Works
18 3.1 RCC works
19 3.1.1 Column
20 3.1.2 Stair
21 3.1.3 Beam
22 3.1.4 Roof Slab
23 3.1.5 Re-Inforcement
24 3.1.6 Brick Wall
25 3.1.7 Plaster Works
26 3.2 Electric Piping
27 4 1st Floor Works
28 4.1 RCC works
29 4.1.1 Column
30 4.1.2 Fins Column
31 4.1.3 Stair
32 4.1.4 Beam
33 4.1.5 floor Slab
34 4.1.6 Minar Stair
35 4.1.7 tie beam / Lintel
36 4.1.8 Re-Inforcement
37 4.1.9 Brick Wall
38 4.1.10 Plaster Works
39 4.2 Electric Piping
40 5 2nd Floor Works
41 5.1 RCC works
42 5.1.1 Column
43 5.1.2 Fins Column
44 5.1.3 Beam
45 5.1.4 Roof
46 5.1.5 Stair
47 5.1.6 Minar Stair
48 5.1.7 tie beam / Lintel
49 5.1.8 Re-Inforcement
50 5.1.9 Brick Wall
51 5.1.10 Plaster Works
52 5.2 Electric Piping
53 6 3rd Floor Works (Roof)
54 6.1 RCC works
55 6.1.1 Column
56 6.1.2 Beam
57 6.1.3 Roof
58 6.1.4 tie beam / Lintel
59 6.1.5 Re-Inforcement
60 6.1.6 Dome
61 6.1.7 Brick Wall
62 6.1.8 Plaster Works
63 7 Door, Window & Grill Works
64 7.1 Ground Floor
65 7.2 1st Floor
66 7.3 2nd Floor
67 7.4 3rd Floor
68 8 Electric Works & Lighting
69 8.1 Ground Floor
70 8.2 1st Floor
71 8.3 2nd Floor
72 9 Plumbing & Sanitary Works
73 10 Titles & Flooring Works
74 11 Deep Tubewell & Pump House
75 12 Fire Safety Equipments
76 13 Sound & PA System
77 14 Solar Power Installation
78 15 CCTV Systems
79 16 Approach Road
80 17 Boundary Wall
81 18 Painting Works