Kushtia Zilla Parishad Work Schedule

Task ID WBS Duration(days) Start time Finish time

1 Structural
1.1 8th floor slab casting 45 19-Sep-20 3-Nov-20
1.2 Roof slab Casting 45 3-Nov-20 18-Dec-20
Over head water tank, lift room, parapet wall
1.3 casting 45 18-Dec-20 1-Feb-21
2 Finishing Schedule
2.1 Brick Work 113 19-Sep-20 10-Jan-21
2.2 Door frame fitting works 40 19-Oct-20 28-Nov-20
2.4 Plaster works 80 19-Oct-20 7-Jan-21
2.5 Plumbing Works 204 19-Sep-20 11-Apr-21
2.5.1 4"/6" upvc pipe works through duct and drain 30 19-Oct-20 18-Nov-20
2.5.2 (12 mm -50 mm) water supplying pipe installation 30 18-Nov-20 18-Dec-20
2.5.3 Fitting sanitary ware (Basin, commode etc) 30 18-Dec-20 17-Jan-21
2.6 Electrical Works 204 19-Sep-20 11-Apr-21
2.6.1 Pipe and accessories
2.6.2 Wire 45 18-Nov-20 2-Jan-21
2.6.3 Switch, socket and SDB 45 2-Jan-21 16-Feb-21
2.7 Aluminium & False ceiling Works
2.7.1 Aluminium sliding & fixed window 73 7-Jan-21 21-Mar-21
2.7.2 Aluminium swing door 73 7-Jan-21 21-Mar-21
2.7.3 Curtain wall 73 7-Jan-21 21-Mar-21
2.7.4 Glass partition 73 7-Jan-21 21-Mar-21
2.7.5 Aluminium composite panel 73 17-Jan-21 31-Mar-21
2.7.6 Gypsum/veenerd board works 30 31-Mar-21 30-Apr-21
2.8 Metal Works
2.8.1 Window grill 45 5-Nov-20 20-Dec-20
2.8.2 Veranda grill 30 5-Dec-20 4-Jan-21
2.8.3 Stair railing 30 4-Jan-21 3-Feb-21
2.8.4 Rolling Shutter 30 4-Jan-21 3-Feb-21
2.9 Tiles & Marble works 129 26-Nov-20 4-Apr-21
2.10 Lift, escalator, AC work 150 5-Nov-20 4-Apr-21
3.00 Paint works 94 7-Jan-21 11-Apr-21
4.00 Correction of defects 94 11-Apr-21 28-May-21
5.00 Hand over 1 29-May-21 29-May-21