You are on page 1of 16

TWO-STOREY RESIDENTIAL BUILDING

PERIOD: W1 - W12
W1 W2
ID WBS ACTIVITY/TASK DAYS START END % PREDECESSOR
1 2 3 4 5 6 7 8 9 10 11 12 13
1 1 SITE WORK
2 1.1 Clearing and grubbing
3 1.2 Rough Grading
4 2 FOUNDATION
5 2.1 Excavation
6 2.1 Reinforcing Steel Bars
7 2.1 Concrete pour
8 2.1 Backfill
9 3 BEAMS
10 3.1 Reinforcing Steel Bars
11 3.1 Concrete pour
12 4 CONCRETE SLAB
13 4.1 Ground Floor Slab
14 4.1.1 Reinforcing Steel Bars
15 4.1.2 Concrete pour
16 4.2 2nd Floor Slab
17 4.2.1 Reinforcing Steel Bars
18 4.2.2 Concrete pour
19 4.3 3rd Floor Slab
20 4.3.1 Reinforcing Steel Bars
21 4.3.2 Concrete pour
22 4.4 Roof Deck Slab
23 4.4.1 Reinforcing Steel Bars
24 4.4.2 Concrete pour
25 5 ROUGH CARPENTRY
26 5.1 Wall (Gnd Floor)
27 5.1.1 Reinforcing Steel Bars
28 5.1.2 CHB
29 5.1.3 Mortar & Plastering
30 5.2 Wall (2nd Floor)
31 5.2.1 Reinforcing Steel Bars
32 5.2.2 CHB
33 5.2.3 Mortar & Plastering
34 5.3 Wall (3rd Floor)
35 5.3.1 Reinforcing Steel Bars
36 5.3.2 CHB
37 5.3.3 Mortar & Plastering
38 5.4 Staircase
39 5.4.1 Reinforcing Steel Bars
40 5.4.2 Concrete pour
41 5.4.3 CHB
42 5.4.4 Square Bar
43 5.5 Installation of Door
44 5.6 Installation of Window
45 6 ELECTRICAL WORKS
46 6.1 Roughing-in
47 6.1.1 PVC Conduit w/ Coupling (20mm)
48 6.1.2 Octagonal Junction Box, 4 K.O
49 6.1.3 PVC Locknut&Bushing
50 6.1.4 Utility Box
51 6.1.5 THHN 3.5mm2 (RED)
52 6.1.6 THHN 3.5mm2 (WHITE)
53 6.1.7 THHN 14.0mm2 (RED)
54 6.1.8 THHN 14.0mm2 (WHITE)
55 6.1.9 THHN 8.0mm2 (GREEN)
56 6.2 Electrical Device & Fixtures
57 6.2.1 23W LED Pin Light
58 6.2.2 50W CFL
59 6.2.3 2x5W LED Wall Light
60 6.2.4 2x10W LED Emergency Ligth
61 6.2.5 Standard C.O (Duplex)
62 6.2.6 Weatherproof C.O (Duplex)
63 6.2.7 Special Outlet
64 6.2.8 1 gang Switch
65 6.2.9 2 gang Switch
66 6.2.10 3 gang Switch
67 6.3 Electrical Panel
68 Main:
69 Branches:
70 7 PLUMBING WORKS
71 7.1 Clean Water Line Rough-in
72 7.1.1 PVC Pipe 3/4" (Blue)
73 7.1.2 Pvc TEE 3/4""
74 7.1.3 Pvc Elbow 3/4""
75 7.1.4 Gate Valve
76 7.1.5 Check Valve
77 7.1.6 Air Capped Chamber 1"
78 7.1.7 PVC TEE 3/4"x1"x3/4"
79 7.2 Waste Water Line Rough-in
80 7.2.1 PVC Pipe 3" (Orange)
81 7.2.2 PVC Pipe 4" (Orange) - Vent Pipe
82 7.2.3 PVC Reducer Tee 3"x4"x3"
83 7.2.4 Pvc TEE 3"
84 7.2.5 P-Trap 1"
85 7.2.6 PVC 90 Deg 3'"
86 7.2.7 Floor Clean-Out 3"
87 7.2.8 Floor Drain 3"
88 7.3 Plumbing Fixtures Installations
89 7.3.1 Lavatory
90 7.3.2 Lavatory Faucet
91 7.3.3 Hose Bibb
92 7.3.4 Kitchen Sink
93 7.3.5 Toilet Bowl
94 7.3.6 Feseal Gum
95 7.3.7 Floor Flange
96 7.3.8 Flared Lead Ferrule
97 7.4 CATCH BASIN
98 7.4.1 Excavation
99 7.4.2 Reinforcing Steel Bars
100 7.4.3 Concrete Pour
101 7.5 SEPTIC TANK
102 7.5.1 Excavation
103 7.5.2 Reinforcing Steel Bars
104 7.5.3 Concrete pour
105 7.5.4 PVC Pipe 4" (Orange)
106 7.5.5 PVC Clean out 4"
107 7.5.6 PVC TEE 4:"
108 8 FLOOR FINISHING
8.1 Installation of Ceramic Tile 40x40
Installation of Ceramic Tile 60x60
8.1
(Ground Floor)
8.1 Ceramic Tile 60x60 (2nd Floor)
9 PAINT
9.1 Primer Paint
9.1.1 Exterior Paint
9.1.2 Interior Paint
9.2 Finishing Paint
9.2.1 Exterior Paint
9.2.2 Interior Paint
9.3 Skimcoat
10 WATER PROOFING
10.1 Water Proofing (Roof Slab)
W2 W3 W4 W5 W6 W7
14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47
W7 W8 W9 W10 W11 W12
48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81
W12
82 83 84

You might also like