TIME SCHEDULE

CONSTRUCTION OF A LAUNDRY ROOM

ETC 30 Days
NO WORK SCOPE BOBOT I REMARKS
Week 1 Week 2 Week 3 Week 4
1 2
1 Scaffolding Rental 2,08 2,08
2 Dismantling or Demolition of Existing Roof 0,35 0,35
3 Hebel Wall Construction 7,5 m 10,48 2,10 8,38
4 Plastering Work 1:4 13,20 13,20
5 Coating Work 6,88 3,44 3,44
6 UPVC Alderon Roofing Work 34,39 17,20 17,20
Installation Holo Frame Ceiling with GRC Covering, Including
7 14,12 14,12
Painting
8 Aluminum Sliding Door Installation 4,86 4,86
9 Window Installation J2 size 180 x 150 cm. 5,77 5,77
10 Wall Painting Work 6,62 6,62
11 Installation of Light Points 0,88 - 0,88
12 Installation of 18-Watt Fluorescent Tube Lights + Fittings 0,20 0,20
13 Installation of Electrical Outlets 0,17 0,17
-

100,00 4,52 42,22 45,39 7,87

Plan 4,52 42,22 45,39 7,87


Comulative Plan 0 4,52 46,74 92,13 100,00

Realization
Comulative Realization
Deviation