Event Duration ES EF LS LF TF FF
Scope of Works
ID (day) (Earliest (Earliest (Latest (Latest (Total (Free
A Mobilization 1 0 1 0 1 0 0
B Occupational Safety And Health 70 0 70 0 70 0 0
C BiPSU Standard Project Billboard 1 1 2 1 2 0 0
D Old Stage Demolition 10 2 12 2 12 0 0
E Storage Rooms 5 2 7 7 12 5 -5
F PWD CR 10 2 12 2 12 0 0
G Electrical Room 7 26 33 26 33 0 0
H Adoration Room 14 12 26 12 26 0 0
I Conference Room 14 12 26 12 26 0 0
J Stone Cladding for Columns 20 12 32 13 33 1 -1
K Finishing & Painting 7 26 33 26 33 0 0
L Water Proofing 5 49 54 64 69 15 15
M Tile Works 10 33 43 39 49 6 -6
N Ramp 7 26 33 26 33 0 0
O Wall Louver @ Sprinkler Room 7 12 19 19 26 7 -7
P Louvered Window 8 33 41 41 49 8 -8
Q Perforated Aluminum Cladding 8 33 41 41 49 8 -8
R Fabrication/ Installation of Collapsible Steel Portable Stage 10 49 59 59 69 10 -10
S Rubberize Paint 10 49 59 59 69 10 -10
T Two Rooms & Roofing System 16 33 49 33 49 0 0
U Parking Area 20 49 69 49 69 0 0
V Electrical, Auxillary Works, and Sound System Equipments 30 33 63 39 69 6 -6
W Demobilization 1 69 70 69 70 0 0
V, 30 days
B, 70 day