DAILY / WEEKLY PROJECT PROGRESS (DAYS)/41

HARI : SENIN
TANGGAL : 6 NOVEMBER 2023
PROYEK : BCC JAKARTA

ITEM DI BQ KEGIATAN PROGRESS VOLUME YANG BOBOT (M2 / FOTO FOTO TARGET JUMLAH REMAKS
C. Atrium dan Corridor KERJA (%) DIKERJAKAN lot ) SELESAI
06-Nov-2023 MP
6 Orang

1. Repair Atrium dan Corridor


Walls 79 492 625

2. Epoxy Mowilex
26 165 625

A. 1 F Ceiling Plan EC - 1 ( Koridor Atrium ) 5 Orang

1. Repair
59 246 415

2. Epoxy Mowilex
7 30 415

A. 1 F Walls ( Café Walls & Colum 08-Nov-2023 6 Orang


repair polish
Bar, Roastery, Entrance, Vip
lounge 1 St & 2 nd
Repair
39 205 522,8

Epoxy Mowilex

A. 1 F Window and Door Ewe + Ewi 14-Nov-2023 2 Orang

Repair , Repaint
27 12 45

B. ME 1 F Perapihan kabel instalasi 10-Nov-2023 4 Orang


50 0,5 1

Pasang Socket Outlet


44 22 50

Landscape 10-Nov-2023 2 Orang

Repair and Repainting Pos Jaga


10 3,00 30

Pembuat Laporan PT. DKI Jaya Supervisi BCC Project Manager

(…......................) (…..........................) (…......................)