DAILY / WEEKLY PROJECT PROGRESS (DAYS)/60

HARI : SENIN
TANGGAL : 16 OKTOBER 2023
PROYEK : BCC JAKARTA

KEGIATAN PROGRESS KERJA (%) VOLUME YANG DIKERJAKAN BOBOT (M2 / lot ) FOTO TARGET SELESAI JUMLAH MP REMAKS

A. 1 F Walls ( 12. Outdoor wall 1 st floor ) TGL : TGL : TGL : 27 Oktober 2023 4 Orang

Finish Concrete Polished epoxy 10,1 31 308

B. 2 F Walls ( 2. Ewi - 3 Stairs Wall ) TGL : TGL : TGL : 30 Oktober 2023 2 Orang

12,5 32 255,6
Repair, Repaint Epoxy

A. 1 F Floor ( 9. Lantai Kitchen ) TGL : TGL : TGL : 19 Oktober 2023 2 Orang

Repair epoxy coating anti slip 34 27 79

C. Atrium dan Corridor TGL : TGL : TGL : 30 Oktober 2023 3 Orang

4 26 625
1. Repair Atrium dan Corridor Walls

A. 1 F Walls ( 3. Toilet staf room. Male / Female TGL : TGL : TGL : 27 Oktober 2023 3 Orang

White waterproof paint


45

Female toilet wall partition, paint white waterproof


25 2 8

Female locker bongkaran dinding, Refinish


33 2 6

Pembuat Laporan PT. DKI Supervisi BCC Project Manager

(….........................) (…..........................) (…..........................)