2010 2011
REMARKS
MARCH ( 1 ) APRIL ( 2 ) MAY ( 3 ) JUNE ( 4 ) JULY ( 5 ) AUGUST ( 6 ) SEPTEMBER ( 7 ) OCTOBER ( 8 ) NOVEMBER ( 9 ) DECEMBER ( 10 ) JANUARY ( 11 ) FEBRUARY ( 12 ) MARCH ( 13 ) APRIL ( 14 )
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56
Project Commencement Topping-off Target Completion
(01 March 2010) (07 April 2011) (30 April 2011)
PROJECT SUPERVISION AND CONTROL (426)
SEALANT AND BACKER CONTINUE
GRAVEL BEDDING/ SOIL POISONING (91) ROD/CONTINUE PLASTERING/
PLASTERING/ SEALANT AND
8 PLASTERING/ CONTINUE CHB LAYING CONTINUE SEALANT AND BACKER BACKER ROD /
CONTINUE CHB (31) ROD/CONTINUE PLASTERING/ CONTINUE CHB ZOCALO FOR
CHB LAYING LAYING LAYING T&B'S
(30) (31) (74) (8)
13 14 16
MOBILIZATI BACKFILLING AND COMPACTION ZOCALO FOR T&B'S
ON / RSB/ FORMWORKS/ (92) (74)
CLEARING CONCRETING/ 11
AND CONTINUE DEMOBILIZ
CONTINUE
GRUBBING EXCAVATION AND
ROOF FRAMING WORKS/ CONTINUE RSB/ ROOF FRAMING ATION (15)
(7) DISPOSAL CONTINUE RSB/ FORMWORKS/ CONCRETING
CONTINUE RSB/ FORMWORKS/ CONCRETING (153) FORMWORKS/ CONCRETING WORKS
(46) (92) (8)
(66)
1 2 3 4 6 12 17 21 22 23 24
EXCAVATION/ CONTINUE FINAL
CONTINUE EXCAVATION AND INSPEC
CLEARING AND DISPOSAL TION
GRUBBING (15) FIRE EXIT, BALCONY, AND LOFT STAIR RAILINGS / BRIDGEWAY (105) (16)
(24)
VAPOR BARRIER / CONTINUE
WATERSTOP CONTINUE WATERSTOP VAPOR BARRIER
(31) (30) (31)
7 9 10
PERIMETER MAIN ENTRANCE TRENCH GRATING SHIP LADDER AND
RAILING 1ST RAILING COVER (28) RUNG LADDER
FLOOR (31) (31) (31)
15 18 19 20
TEMFACIL / CONTINUE MOBILIZATION
(54)
5 ELEVATOR SHAFT EMBED/
MANHOLE COVER/ LADDER
RUNGS
(31)
MISCELLANEOUS WORKS
(426)