You are on page 1of 12

FRABELLE SHIPYARD CORPORATION

SANGALI, ZAMBOANGA FISH PORT COMPLEX, ZAMBOANGA CITY

PROGRESS REPORT ON CIVIL WORKS


FOR THE SHIPYARD SITE DEVELOPMENT
AS OF MARCH 13, 2020

Date
Scope of Works Sub-Contractor Completion Rate
Downpayment Mobilization

1. Ground Leveling Megalith 28 Feb 2020 24 Feb 2020 60%


2. Perimeter Fencing Double E 28 Feb 2020 5 Mar 2020 15%
3. Technical Shop Megalith 28 Feb 2020 2 Mar 2020 25%
4. Office and Accomodation Double E 28 Feb 2020 5 Mar 2020 5%
5. Electrical Phase 1 Legendary Seven 28 Feb 2020 28 Feb 2020 5%
SUB-TOTAL 22%

PREPARED BY:

PAUL BANDILLA
Superintendent, FSC- Zambo

CHECKED BY:

DAN BOLANOS / CONRAD VIEJO / BOGS DE GUZMAN


FSC-Zambo Project Team
Scope of Works: GROUND LEVELING & GRADING Progress as of: 13 Mar 2020
Contractor: MEGALITH BUILDERS Actual Start: 24 Feb 2020

ACTIVITY: EARTHWORKS IN SHIP-BUILDING AREA


ACTUAL DAYS WORKED AS DATED: 18 (EXCLUDING HOLIDAYS, SUNDAYS & NON-WORKING WEATHER DAYS)

REMARKS
- Done with initial area clearing (grass, scraps & other obstruction).
- Ongoing completion filling-up works of uneven ground areas.
- For completion of ground grading works and manual clearing from remaining solid
& sharp objects
Scope of Works: GROUND LEVELING & GRADING Progress as of: 13 Mar 2020
Contractor: MEGALITH BUILDERS Actual Start: 24 Feb 2020

ACTIVITY: SLOPE EXCAVATION AND OBSTRUCTION REMOVAL


ACTUAL DAYS WORKED AS DATED: 18 (EXCLUDING HOLIDAYS, SUNDAYS & NON-WORKING WEATHER DAYS)

REMARKS
- Ongoing excavation of slope and removal of the concrete obstruction
Scope of Works: GROUND LEVELING & GRADING Progress as of: 13 Mar 2020
Contractor: MEGALITH BUILDERS Actual Start: 24 Feb 2020

ACTIVITY: EARTHWORKS IN SHIP-REPAIR AREA


ACTUAL DAYS WORKED AS DATED: - (EXCLUDING HOLIDAYS, SUNDAYS & NON-WORKING WEATHER DAYS)

REMARKS
- Done with initial area clearing (grass, scraps & other obstruction).
- Ongoing filling-up works of uneven ground areas
Scope of Works: PERIMETER FENCING Progress as of: 13 Mar 2020
Contractor: DOUBLE E Actual Start: 5 Mar 2020

ACTIVITY: CONCRETE FENCE FOUNDATION LAYING


ACTUAL DAYS WORKED AS DATED: 8 (EXCLUDING HOLIDAYS, SUNDAYS & NON-WORKING WEATHER DAYS)

REMARKS
- Laying of new fence concrete foundations within the propety line
Scope of Works: PERIMETER FENCING Progress as of: 13 Mar 2020
Contractor: DOUBLE E Actual Start: 5 Mar 2020

ACTIVITY: TREE BRANCH CLEARING


ACTUAL DAYS WORKED AS DATED: 8 (EXCLUDING HOLIDAYS, SUNDAYS & NON-WORKING WEATHER DAYS)

REMARKS
- Done clearing of tree branches obstruction
Scope of Works: TECHNICAL SHOPS (MACHINE SHOP/WAREHOUSE) Progress as of: 13 Mar 2020
Contractor: MEGALITH Actual Start: 2 Mar 2020

ACTIVITY: INSTALLATION OF BUILDING ROOF GUTTER


ACTUAL DAYS WORKED AS DATED: 11 (EXCLUDING HOLIDAYS, SUNDAYS & NON-WORKING WEATHER DAYS)

REMARKS
- Done painting of building structural frames.
- Ongoing installation of roof gutter.
Scope of Works: TECHNICAL SHOPS (MACHINE SHOP/WAREHOUSE) Progress as of: 13 Mar 2020
Contractor: MEGALITH Actual Start: 2 Mar 2020
ACTIVITY: INSTALLATION OF TECHNICAL SHOP COVER
ACTUAL DAYS WORKED AS DATED: 11 (EXCLUDING HOLIDAYS, SUNDAYS & NON-WORKING WEATHER DAYS)

REMARKS:
- Ongoing installation of metal sheet cover and steel matting for the structural
cover of the technical shop
Scope of Works: OFFICE AND ACCOMMODATION Progress as of: 13 Mar 2020
Contractor: DOUBLE E Actual Start: 5 Mar 2020

ACTIVITY: PUNCHING-IN OF BUILDING'S WALL OPENING


ACTUAL DAYS WORKED AS DATED: 8 (EXCLUDING HOLIDAYS, SUNDAYS & NON-WORKING WEATHER DAYS)

REMARKS
- Ongoing punching-in of the building's opening (such as door and windows).
Scope of Works: OFFICE AND ACCOMMODATION Progress as of: 13 Mar 2020
Contractor: DOUBLE E Actual Start: 5 Mar 2020

ACTIVITY: LAYING-OUT OF DIVISION AND FOUNDATION


ACTUAL DAYS WORKED AS DATED: 8 (EXCLUDING HOLIDAYS, SUNDAYS & NON-WORKING WEATHER DAYS)

REMARKS
- Laying out of the division and foundation of the building
Scope of Works: ELECTRICAL LAYOUT PHASE 1 Progress as of: 13 Mar 2020
Contractor: LEGENDARY SEVEN Actual Start: 2 Mar 2020
ACTIVITY: TEMPORARY WAREHOUSE CONSTRUCTION AND CONRETING OF WIREWAYS
ACTUAL DAYS WORKED AS DATED: 11 (EXCLUDING HOLIDAYS, SUNDAYS & NON-WORKING WEATHER DAYS)

REMARKS
- Ongoing construction of temporary warehouse of Legendary Seven; for the
cable and wires
- Ongoing concreting of wireways
Scope of Works: OTHER UPDATES Progress as of: -
Contractor: - Actual Start: -
ACTIVITY: SITE BLESSING
DATE CONDUCTED: 11 Mar 2020

REMARKS
- Conducted site blessing in the entire leased area.

You might also like