Date
Scope of Works Sub-Contractor Completion Rate
Downpayment Mobilization
PREPARED BY:
PAUL BANDILLA
Superintendent, FSC- Zambo
CHECKED BY:
REMARKS
- Done with initial area clearing (grass, scraps & other obstruction).
- Ongoing completion filling-up works of uneven ground areas.
- For completion of ground grading works and manual clearing from remaining solid
& sharp objects
Scope of Works: GROUND LEVELING & GRADING Progress as of: 13 Mar 2020
Contractor: MEGALITH BUILDERS Actual Start: 24 Feb 2020
REMARKS
- Ongoing excavation of slope and removal of the concrete obstruction
Scope of Works: GROUND LEVELING & GRADING Progress as of: 13 Mar 2020
Contractor: MEGALITH BUILDERS Actual Start: 24 Feb 2020
REMARKS
- Done with initial area clearing (grass, scraps & other obstruction).
- Ongoing filling-up works of uneven ground areas
Scope of Works: PERIMETER FENCING Progress as of: 13 Mar 2020
Contractor: DOUBLE E Actual Start: 5 Mar 2020
REMARKS
- Laying of new fence concrete foundations within the propety line
Scope of Works: PERIMETER FENCING Progress as of: 13 Mar 2020
Contractor: DOUBLE E Actual Start: 5 Mar 2020
REMARKS
- Done clearing of tree branches obstruction
Scope of Works: TECHNICAL SHOPS (MACHINE SHOP/WAREHOUSE) Progress as of: 13 Mar 2020
Contractor: MEGALITH Actual Start: 2 Mar 2020
REMARKS
- Done painting of building structural frames.
- Ongoing installation of roof gutter.
Scope of Works: TECHNICAL SHOPS (MACHINE SHOP/WAREHOUSE) Progress as of: 13 Mar 2020
Contractor: MEGALITH Actual Start: 2 Mar 2020
ACTIVITY: INSTALLATION OF TECHNICAL SHOP COVER
ACTUAL DAYS WORKED AS DATED: 11 (EXCLUDING HOLIDAYS, SUNDAYS & NON-WORKING WEATHER DAYS)
REMARKS:
- Ongoing installation of metal sheet cover and steel matting for the structural
cover of the technical shop
Scope of Works: OFFICE AND ACCOMMODATION Progress as of: 13 Mar 2020
Contractor: DOUBLE E Actual Start: 5 Mar 2020
REMARKS
- Ongoing punching-in of the building's opening (such as door and windows).
Scope of Works: OFFICE AND ACCOMMODATION Progress as of: 13 Mar 2020
Contractor: DOUBLE E Actual Start: 5 Mar 2020
REMARKS
- Laying out of the division and foundation of the building
Scope of Works: ELECTRICAL LAYOUT PHASE 1 Progress as of: 13 Mar 2020
Contractor: LEGENDARY SEVEN Actual Start: 2 Mar 2020
ACTIVITY: TEMPORARY WAREHOUSE CONSTRUCTION AND CONRETING OF WIREWAYS
ACTUAL DAYS WORKED AS DATED: 11 (EXCLUDING HOLIDAYS, SUNDAYS & NON-WORKING WEATHER DAYS)
REMARKS
- Ongoing construction of temporary warehouse of Legendary Seven; for the
cable and wires
- Ongoing concreting of wireways
Scope of Works: OTHER UPDATES Progress as of: -
Contractor: - Actual Start: -
ACTIVITY: SITE BLESSING
DATE CONDUCTED: 11 Mar 2020
REMARKS
- Conducted site blessing in the entire leased area.