FRABELLE SHIPYARD CORPORATION

SANGALI, ZAMBOANGA FISH PORT COMPLEX, ZAMBOANGA CITY

PROGRESS REPORT ON CIVIL WORKS


FOR THE SHIPYARD SITE DEVELOPMENT
AS OF MARCH 25, 2020

Date
Scope of Works Sub-Contractor Completion Rate
Downpayment Mobilization

1. Ground Leveling Megalith 28 Feb 2020


24 Feb 2020 70%
2. Perimeter Fencing Double E 28 Feb 2020
5 Mar 2020 18%
3. Technical Shop Megalith 28 Feb 2020
2 Mar 2020 28%
4. Office and Accomodation Double E 28 Feb 2020
5 Mar 2020 10%
5. Electrical Phase 1 Legendary Seven 28 Feb 2020
28 Feb 2020 8%
SUB-TOTAL 27%
NOTE : ALL CONSTRUCTION WORKS ARE TEMPORARILY SUSPENDED SINCE MARCH 20, 2020 UNTIL
FURTHER NOTICE IN COMPLIANCE WITH THE LGU-ZAMBOANGA's ORDINANCE REGARDING
ENHANCED COMMUNITY QUARANTINE.

PREPARED BY:

PAUL BANDILLA
Superintendent, FSC- Zambo

CHECKED BY:

DAN BOLANOS / CONRAD VIEJO / BOGS DE GUZMAN


FSC-Zambo Project Team
Scope of Works: GROUND LEVELING & GRADING Status as of: 25 Mar 2020
Contractor: MEGALITH BUILDERS Community Quarantine Start: 20 Mar 2020

ACTIVITY: GROUND COMPACTING


ACTUAL DAYS WORKED AS DATED: 22 (EXCLUDING HOLIDAYS, SUNDAYS & NON-WORKING WEATHER DAYS)

- Dry-docking Area (First Picture) and Ship Building Area (Second Picture)
- Waiting for Supplementary Quotations on Sloping works & Dockway entrance conreting
Scope of Works: PERIMETER FENCING Status as of: 25 Mar 2020
Contractor: DOUBLE E Community Quarantine Start: 20 Mar 2020

ACTIVITY: CONCRETE FENCE FOUNDATION LAYING AND PROPERTY MARKS CONFIRMATION


ACTUAL DAYS WORKED AS DATED: 13 (EXCLUDING HOLIDAYS, SUNDAYS & NON-WORKING WEATHER DAYS)

- Fence construction of the left portion of yard; along the gutter of Technical
and Office Bldg
Scope of Works: TECHNICAL SHOPS (MACHINE SHOP/WAREHOUSE) Status as of: 25 Mar 2020
Contractor: MEGALITH Community Quarantine Start: 20 Mar 2020

ACTIVITY: PREPARATIONS FOR HALL ENTRANCE & EXIT GATES


ACTUAL DAYS WORKED AS DATED: 16 (EXCLUDING HOLIDAYS, SUNDAYS & NON-WORKING WEATHER DAYS)

- Renovation & construction works of Technical Shop


Scope of Works: OFFICE AND ACCOMMODATION Status as of: 25 Mar 2020
Contractor: DOUBLE E Community Quarantine Start: 20 Mar 2020

ACTIVITY: OFFICE WALL CONSTRUCTION


ACTUAL DAYS WORKED AS DATED: 13 (EXCLUDING HOLIDAYS, SUNDAYS & NON-WORKING WEATHER DAYS)

- Renovation & construction works of the office and accomodation


Scope of Works: ELECTRICAL LAYOUT PHASE 1 Status as of: 25 Mar 2020
Contractor: LEGENDARY SEVEN Community Quarantine Start: 20 Mar 2020
ACTIVITY: TEMPORARY WAREHOUSE CONSTRUCTION AND CONRETING OF WIREWAYS
ACTUAL DAYS WORKED AS DATED: 16 (EXCLUDING HOLIDAYS, SUNDAYS & NON-WORKING WEATHER DAYS)

- Temporary warehouse for Legendary Seven's materials & equipment (1st picture)
- Construction of foundation of the Panel Boards & electrical components' pedestals.