PROJECT : VISTA GL TAFT LEGEND:

LOCATION : 1344 Taft Avenue, Ermita, Manila


DATE : JULY 3, 2020 1-Sep-2020 - Target Date Only of Start and Finish (Actual Date will depend on
settlement of issues attach/item of work
SUBJECT : DETAILED BALANCE OF WORKS & TARGET COMPLETION SCHEDULE

DATE DURATION REMARKS JUL'20 AUG'20 SEP'20 OCT'20 NOV'20


SCOPE OF WORKS
START FINISH # OF DAYS (ISSUES/CONCERNS) 15 22 29 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 30
ELECTRICAL ROOM

Depends on Approval of Owner to Additional Cost


Meter Center Works (Installation and Termination) - Ground Floor 1-Sep-2020 7-Sep-2020 7 of Vista Supplier (Lite Corp.) due to Revision of
MCB, Busbar and Breaker Gutter 1 1
Depends on Approval of Owner on Additional on
Meter Center Works (Installation and Termination) - 7th - 10th Floor 7-Sep-2020 30-Sep-2020 24
KWHR Meter 1 1 1 2
Depend on Turn-over of Area (1st Coat Painting
Installation of Smoke Detector & Lighting Fixtures 1-Sep-2020 30-Sep-2020 30
Completion) 1 1 1 1 2
Termination Works for GPP, GLP, 2LPA, 4LPA, 6PPA & 6LPA Panel 20-Jul-2020 23-Jul-2020 4 1
Painting of Pipes (Riser) - 17th TO 43rd Floor (Balance) 22-Jul-2020 2-Aug-2020 12 1 1 1
Testing Works for Admin Panels (Functionality Testing) - including hand-over 1-Oct-2020 30-Nov-2020 61 2 2 2 2 2 2 2 2 2

AUXILIARY ROOM

Depend on Turn-over of Area (1st Coat Painting


Installation of Smoke Detector & Lighting Fixtures 1-Sep-2020 30-Sep-2020 30
Completion) 2 1 2 2 2
Schedule will depend on the completion of wiring
Installation of Fiber Racks and Accessories & Termination Works at Fiber Distribution Panel 1-Sep-2020 30-Sep-2020 30
for Riser (by TEL provider)
Wiring Works for CCTV Riser - Power Supply 2-Aug-2020 2-Aug-2020 1
Rectification of Block-out (Concrete Pouring) - Balance (24th to 42nd Floor) 13-Jul-2020 8-Aug-2020 27 7 5 6 5
Painting of Pipes (Riser) - 10th TO 42nd Floor (Balance) 3-Aug-2020 17-Aug-2020 15 1 1 1
Termination at Fire Alarm Box (Installation of Module and etc.) 6-Aug-2020 15-Aug-2020 10 2 1

Testing and Commissioning Works (TEL, FDAS AND CCTV) - including hand-over 1-Oct-2020 30-Nov-2020 61
2 2 2 2 2 2 2 2 2

BASEMENT
Installation of Grounding Rod & Cadweld Connection (3 pcs.) 7-Aug-2020 7-Aug-2020 1 2
Schedule will Depend on the Delivery of Bare
Wiring of BCW for Lightning Arrester 6-Aug-2020 6-Aug-2020 1
Copper Wire (OSM) 2
Installation of CCTV, Wiring Devices & Emergency Lights 13-Aug-2020 14-Aug-2020 2 2
Installation of MDF (By Philhernst) 1-Sep-2020 5-Sep-2020 5
Installation & Termination of ECB of DPPR, STP & ECB's of Telco Room 13-Aug-2020 14-Aug-2020 2 1
Wiring Works for Power Supply of Telco Rooms 14-Aug-2020 14-Aug-2020 1 1

GROUND FLOOR
Installation of Grounding Rod & Cadweld Connection 11-Aug-2020 15-Aug-2020 5 Schedule will Depend on the Delivery of Bare
Piping at Landscape Area & Wiring of Bare Copper Wire 8-Aug-2020 10-Aug-2020 3 Copper Wire (OSM)
Installation of CCTV Camera, CCTV Monitor and DVR 20-Aug-2020 26-Aug-2020 7 1
Installation of FACP and Other Accessories & Termination of FACP 20-Aug-2020 31-Aug-2020 12 1
Installation for Traffic Management System - Barriers, Sounder and Control Panel (By
3-Sep-2020 9-Sep-2020 7
techsafe) - Testing and Commissioning 1
Wiring for Traffic Management System 1-Sep-2020 2-Sep-2020 2 2 1

PARKING (2nd to 6th FLOOR)


Installation of Lighting Fixtures - Balance (Location of Site Offices and Warehouse of
24-Sep-2020 30-Sep-2020 7 Clearing of Area for Installation
Contractors, Vista and DAAA) 2
Roughing-ins and Wiring Works for CTC (Admin KWHR Meter) 3-Sep-2020 9-Sep-2020 7 Schedule will Depend on the Delivery of Balance 2

Termination at Main EE Room MDP (MCG, DP-EP & DP-STP) 1-Sep-2020 2-Sep-2020 2 Wires (OSM)
2

OFFICES FLOORS (7th to 10th FLOOR)


Installation of Wiring Devices 20-Aug-2020 26-Aug-2020 7 2
Clearing of Area (Stock Materials) and Installation
Installation of Smoke Detector at Units and Hallways 20-Aug-2020 26-Aug-2020 7 2
of Lockset
Installation of Breaker for ACCU ECB and Termination Works 20-Aug-2020 26-Aug-2020 7
````
RESIDENTIAL FLOORS (11th to 42nd Floor)
a. Installation of Wiring Devices, Lighting Fixtures and Smoke Detector's @ Units
a.1 35th Floor 20-Aug-2020 26-Aug-2020 7 4
a.2 36th Floor 27-Aug-2020 2-Sep-2020 7 4
a.3 37th Floor 3-Sep-2020 9-Sep-2020 7 4
a.4 38th Floor 10-Sep-2020 16-Sep-2020 7 Schedule will Depend on Turn-over of Ceiling and 4
a.5 39th Floor 17-Sep-2020 23-Sep-2020 7 Painting Contractor 4
a.6 40th Floor 24-Sep-2020 30-Sep-2020 7 4
a.7 41st Floor 1-Oct-2020 7-Oct-2020 7 4
a.8 42nd Floor 8-Oct-2020 14-Oct-2020 7 4
b. Installation of Lighting Fixtures & FDAS Devices (Hornstrobe, Manual Pull and Fireman's
Jack) @ Hallways and Elevator Lobby
b.1 33rd Floor 13-Aug-2020 19-Aug-2020 7 1
b.2 34th Floor 13-Aug-2020 19-Aug-2020 7 1
b.3 35th Floor 20-Aug-2020 26-Aug-2020 7
b.4 36th Floor 27-Aug-2020 2-Sep-2020 7
b.5 37th Floor 3-Sep-2020 9-Sep-2020 7 Schedule will Depend on Turn-over of Ceiling and
b.6 38th Floor 10-Sep-2020 16-Sep-2020 7 Painting Contractor
b.7 39th Floor 17-Sep-2020 23-Sep-2020 7
b.8 40th Floor 24-Sep-2020 30-Sep-2020 7
b.8 41st Floor 1-Oct-2020 7-Oct-2020 7
b.9 42nd Floor 8-Oct-2020 14-Oct-2020 7
c.Rectification of Punchlist by Painting Contractor, etc. 9-Jul-2020 30-Sep-2020 84 4 4 2 2 2 2 2
d.Hand-over of Units (Inspection and QRT Team to Owner) 1-Oct-2020 30-Nov-2020 61

43RD FLOOR
Installation of Floor Outlets and LED Bulb @ Function Room 13-Aug-2020 19-Aug-2020 7 1
Installation of LED Bulb @ Gym and Study Hall 13-Aug-2020 19-Aug-2020 7 1
Installation of FDAS Devices and CCTV Camera 10-Sep-2020 16-Sep-2020 7 1
Installation of Wall Lamp at Swimming Pool Area 10-Sep-2020 16-Sep-2020 7 1

VIEW DECK
Installation of Smoke Detector 10-Sep-2020 16-Sep-2020 7
Schedule will Depend on the Delivery of Bare
Installation of Lightning Arrester (Balance - Delivery of Photocell) 6-Aug-2020 6-Aug-2020 1
Copper Wire (OSM) 1
Installation of Lighting Fixtures at Pump and Laundromat Room' 17-Sep-2020 23-Sep-2020 7 1
Installation of Emergency Light at Machine Room 17-Sep-2020 23-Sep-2020 7 1
Termination for Branches of DPMR & DPRD Panel 6-Aug-2020 7-Aug-2020 2 2
Interfacing to FDAS of Pressurization Blower, Flowswitch and Elevator - Piping and Wiring 10-Sep-2020 23-Sep-2020 14 2 2

TOTAL DIRECT MANPOWER (ELECTRICIAN, MASON, HELPER, ETC.) 7 7 7 7 10 10 10 12 12 12 12 12 8 8 8 8 6 6 6 6 6